Opinion · Supreme Court of the United States

United States v. McMullen

United States v. McMullen, 222 U.S. 460 (1912)

Type
Opinion
Court
Supreme Court of the United States
Jurisdiction
Federal
Date
1912-01-09
Topic
general

*467 Me. Justice Holmes delivered the opinion of the court. This is a suit upon a contract for dredging and a bond made part of the contract, both executed by the New York Dredging Company as principal and by the defendants in error as sureties. The plaintiff got judgment in the Circuit Court, but in the Circuit Court of Appeals the judgment was reversed on the ground that the time for performance had been extended, and was ordered to be entered for the defendants. 167 Fed. Rep. 460. 93 C.

Citator

UpLaw has not yet analyzed United States v. McMullen. The absence of a flag is not a finding that it is good law.

Cited by
40 opinions

Headnotes

  1. Contracts Law — Suretyship Where a government contract expressly contemplates that the time for performance may be extended, and the bond is made part of the contract, the sureties are not discharged by extensions granted pursuant to the contract, because, whether their assent is a question of construction and good sense, the sureties must be taken to have contemplated such extensions as permissible against themselves. 222 U.S. at 466-468
  2. Contracts Law — Liquidated Damages Where a contract provides for deductions of a fixed sum per day as liquidated damages for avoidable delay, and the Government does not take steps to collect such penalties from the contractor, the sureties are not discharged thereby, since the contract is not altered and insistence by the United States would have availed them nothing. 222 U.S. at 468
  3. Contracts Law — Termination for Default — Meaning of "Annul" The government's election to annul a contract upon the contractor's default does not rescind or avoid the contract, but means only that the Government will proceed no further with the contractor under it and will charge the contractor with the reasonable difference in cost caused by the default, the obligations of the contract remaining in full force so far as applicable to a case of default. 222 U.S. at 468-469
  4. Contracts Law — Government Contracts — Reprocurement Costs Where the Government, after a contractor's default, relets the contract to the lowest bidder in the manner required, the price obtained must be assumed to be reasonable in the absence of evidence to the contrary, especially where the resulting difference in cost is less than the sum stipulated as liquidated damages. 222 U.S. at 469
  5. Contracts Law — Suretyship The sureties on a defaulted government contract are not relieved of liability because the contract as relet differs from the original in terms that diminish the cost of the work, so long as the work performed toward the contract's object was work the original contractor had agreed to perform and the Government had reserved the right of choice in that regard. 222 U.S. at 469-470
  6. Contracts Law — Government Contracts — Certainty and Mutuality A government contract is not unenforceable for uncertainty or want of mutuality merely because it reserves to the United States the power to make changes, where it provides adequate means for ascertaining a change in compensation when any such change is proper. 222 U.S. at 470
  7. Contracts Law — Government Contracts — Limitation by Appropriations The amount of work to be done under a government contract depends upon the appropriations made by Congress for carrying on the work, and this limitation is implied whether expressed in the contract or not. 222 U.S. at 470
  8. Civil Procedure — Admission by Implication — Execution of Contract Where the answer does not deny that the contract was signed by the United States, and the contract itself declares that it is made by the United States and is signed by the Chief of the Bureau of Yards and Docks, the answer admits the execution by implication, and the signature is sufficient. 222 U.S. at 470
  9. Contracts Law — Government Contracts — Secretary as Third Party The question whether, where a contractor is given a right to an extension of time if the Secretary of the Navy approves, the Secretary is to be regarded as a third party or as representing the United States, is reserved and not decided. 222 U.S. at 468