Opinion · Supreme Court of the United States

United States v. Gleason

175 U.S. 588

Type
Opinion
Court
Supreme Court of the United States
Jurisdiction
Federal
Date
1900-01-08
Topic
general

How later courts describe this case

  • re-statirig test as requiring “allegation and proof of bad faith, or of mistake or negligence so great, so gross, as to justify an inference of bad faith”

Citator

UpLaw has not yet analyzed United States v. Gleason. The absence of a flag is not a finding that it is good law.

Cited by
186 opinions

Headnotes

  1. Contracts Law — Impossibility A party who by contract assumes an obligation that is possible to perform is bound to perform it unless performance is rendered impossible by the act of God, by operation of law, or by the act of the other party; unforeseen difficulties, however great, will not excuse nonperformance, and where the parties have made no provision for a dispensation, neither law nor equity will supply one.
  2. Contracts Law — Finality of Engineer's Decision Parties to a government construction contract may agree that the decision of an engineer or other designated officer on specified matters of dispute arising during performance shall be final and conclusive, and in the absence of fraud, or of mistake or negligence so gross as to necessarily imply bad faith, that decision is not subject to the revisory power of the courts.
  3. Contracts Law — Extension of Time — Engineer's Discretion Where a construction contract provides that additional time may in writing be allowed for completion if the contractor is prevented by freshets, ice, or other force or violence of the elements, and by no fault of his own, the right or privilege of the contractor to a further extension of time depends upon the judgment of the engineer in charge when applied to; the engineer decides both whether the failure to complete was attributable to the excepted causes rather than the contractor's own fault, and, if so, what additional time is just and reasonable, and the words "may be allowed" are not to be construed as "shall be allowed," because the provision exists to prevent dispute and uncertainty and vests the determination in the officer's discretion. 175 U.S. 588 (opinion of the Court)
  4. Contracts Law — Engineer's Decision — Refusal of Extension Is Final Where the granting of additional time by the engineer under a government construction contract would be final and irrevocable, his refusal to allow it is equally final; the privilege of procuring an extension is conditional on the officer's action whether he grants or refuses it, and the contractor may not substitute an absolute right to have the question of prevention, whether by freshets or by fault, determined by the courts in place of an appeal to the officer's discretion and decision. 175 U.S. 588 (opinion of the Court)
  5. Contracts Law — Engineer's Decision — Conclusiveness Where a contract expressly provides that a matter shall be ascertained and fixed by a designated government officer, his action in the premises is conclusive upon the contractor as well as upon the government, and the contract, being free from ambiguity, permits no exposition contrary to its express words; his determination may be set aside only for fraud or such gross mistake as would necessarily imply bad faith or a failure to exercise an honest judgment.
  6. Contracts Law — Consideration In a bona fide exercise of the discretion conferred upon him, an engineer in charge, when applied to for a further extension of time under a government construction contract, may properly consider the conduct of the contractors through the entire scope of their past performance thereunder, including delinquencies during prior periods and the futility of extensions theretofore granted, in deciding what weight to give their promises as to the future and whether previous grants of extension had produced the efforts the circumstances required; an indefinite succession of extensions is not within the contemplation of such a contract. 175 U.S. 588 (opinion of the Court)
  7. Contracts Law — Implied Covenant of Good Faith In the absence of evidence of bad faith on the part of the engineer in charge, a court is required to presume that he acted with due regard to his duty as between the government and the contractors; a mere allegation that the engineer's refusal to grant an extension was wrongful and unjust, because he decided the submitted issue against the contractor, is insufficient to upset his judgment, and the courts may not revise that judgment by their own views except upon allegation and proof of bad faith, or of mistake or negligence so gross as to justify an inference of bad faith. 175 U.S. 588 (opinion of the Court)
  8. Contracts Law — Waiver Where no actual damage or loss is definitely shown to have been suffered by the government from the noncompletion of the work, and no forfeitures of retained percentages were declared at the time of the several extensions, the right to such forfeitures may be deemed to have been waived, and the contractor may recover the retained percentages of compensation for work actually done and accepted. 175 U.S. 588 (opinion of the Court)