Mr. Justice Harlan, after stating the case, delivered the opinion of the court. The written contract between the parties in this case does not materially differ from the one before this court in Martinsburg & Potomac Railroad Co. v. March, 114 U. S. 549, 553. *193 In that case the contractor did not allege in his declaration that the engineer ever certified in writing the complete performance of the contract, together with an estimate of the work done and the amount of compensation due him according to the prices established by the parties; which certificate and estimate was made by the agreement a condition of the liability of the company to pay the contractor the balance, if any, due him.

Citator

UpLaw has not yet analyzed Chicago, Santa Fé & California Railroad v. Price. The absence of a flag is not a finding that it is good law.

Cited by
98 opinions

Headnotes

  1. Contracts Law — Conclusiveness of Engineer's Determination Where a construction contract provides that work shall be executed under the direction and supervision of the railway company's chief engineer, that the quantities and amounts of the several kinds of work shall be determined by his measurements and calculations, and that his determination shall be conclusive upon the parties, the engineer's action in making the estimates and certificates contemplated by the contract is a determination binding upon the parties in an action at law; such determination is conclusive in the absence of fraud on the engineer's part, or of such gross mistakes as necessarily imply bad faith, and the parties, having chosen to risk his estimates, cannot revise his determination for mere errors or mistakes. 138 U.S. at 193–195
  2. Contracts Law — Conclusiveness of Engineer's Determination — Limits The final and conclusive effect of an engineer's determination under a construction contract is subject to the implied condition, which the law presumes the parties did not intend to waive, that the engineer shall at all times, and in respect to every matter submitted to his determination, exercise an honest judgment and commit no such mistakes as under all the circumstances would imply bad faith; the mere negligence or incompetency of the engineer does not overcome the conclusiveness of his determination unless his mistakes were so gross as to imply bad faith. 138 U.S. at 193–194
  3. Contracts Law — Monthly Estimates as Certificate of Complete Performance Where a construction contract provides for monthly payments to the contractor on the certificate of the engineer for work done, and the monthly estimates are prepared by the division engineer, approved and certified by the assistant chief engineer and chief engineer, and acted upon by the parties through successive payments, the last monthly estimate of work done, followed by acceptance by the company of the whole work, constitutes, within a reasonable interpretation of the contract, a certificate of complete performance entitling the contractor to be paid in full according to the terms of the contract. 138 U.S. at 194
  4. Contracts Law — Reclassification and Final Estimate After Acceptance Where the work has been substantially completed, accepted, and taken possession of by the company, and the contractor has been paid from time to time according to monthly estimates, the company may not go behind those estimates on the basis of a later remeasurement and reclassification made without the contractor's knowledge or cooperation, in the absence of a finding of fraud or of such gross mistakes by the engineer as imply bad faith. 138 U.S. at 194–195