Opinion · Supreme Court of the United States

United States v. O'BRIEN

United States v. O'BRIEN, 220 U.S. 321 (1911)

Type
Opinion
Court
Supreme Court of the United States
Jurisdiction
Federal
Date
1911-04-03
Topic
general

How later courts describe this case

  • finding that a contractor's right to continue to dredge in order to perform a contract was conditional on the government engineer's satisfaction with their work but ultimately the failure to satisfy the engineer did not breach the contract

Citator

UpLaw has not yet analyzed United States v. O'BRIEN. The absence of a flag is not a finding that it is good law.

Cited by
20 opinions

Headnotes

  1. Contracts Law — Interpretation A government contract that makes a contractor's right to continue work depend upon the approval of the engineer in charge will not, absent express terms, be construed as making the engineer's dissatisfaction with the progress of the work conclusive of a breach by the contractor. 220 U.S. at 325–326
  2. Contracts Law — Breach Where the contract's only material express promise is to complete the work by a specified date, performance by that date discharges the promise regardless of irregularity or delay in earlier months; the government is concerned with the completed result, not the stages of performance, and time enough remaining to finish under the contract when the contractor is dismissed precludes treating the contract as broken. 220 U.S. at 325
  3. Contracts Law — Government Contracts — Right to Recover Excess Completion Costs A provision giving the government the right to recover the expense of completing the work in excess of the original price applies only upon the contractor's failure to complete the contract as specified and agreed upon, meaning failure to complete by the stipulated completion date, and not a failure to complete because the contractor was discharged by the engineer before that date arrived. 220 U.S. at 326
  4. Contracts Law — Government Contracts — Annulment Clause A provision authorizing annulment of a government contract upon the engineer's judgment of the contractor's failure to prosecute the work diligently, with forfeiture of reserved percentages and money due, is the protection expressly stipulated by the government and provides for no further consequence absent plainer words imposing liability for the expense of completion. 220 U.S. at 326
  5. Contracts Law — Interpretation The word "annul," as used in a contract and in the notice terminating it, is not to be taken literally; it means a refusal to perform further, not a rescission or avoidance of the contract, particularly where the contract itself provides that rights shall arise upon annulment, which would be impossible if the contract were thereby made naught. 220 U.S. at 327