Opinion · Supreme Court of the United States

Guaranty Co. v. Pressed Brick Co.

Guar. Co. v. Pressed Brick Co., 191 U.S. 416 (1903)

Type
Opinion
Court
Supreme Court of the United States
Jurisdiction
Federal
Date
1903-12-07
Topic
general

How later courts describe this case

  • “In an ordinary guaranty the guarantor understands perfectly the nature and extent of his obligation.”

Citator

UpLaw has not yet analyzed Guaranty Co. v. Pressed Brick Co.. The absence of a flag is not a finding that it is good law.

Cited by
183 opinions

Headnotes

  1. Contracts Law — Discharge by Extension of Time Under the general law of suretyship, any change in the contract for the performance of which a guarantor is liable, made without his consent — such as an extension of time for payment made upon sufficient consideration — discharges the guarantor from liability. 191 U.S. at 424
  2. Federal Government Contracts — Claims A bond given under the Act of August 13, 1894, for the protection of persons furnishing labor and materials for the construction of public works contains two entirely distinct and separate obligations: one that the contractor faithfully perform his contract with the government, and another that he promptly pay all persons supplying him labor and materials in the prosecution of the work; the covenants are read together, and the latter is interpreted in light of the former. 191 U.S. at 423
  3. Contracts Law — Payments to Materialmen — Notice of Parties and Amounts Where a surety guarantees payment of the claims of unknown materialmen who may supply a government contractor, the surety is ignorant of the parties with whom the principal may contract, the amount, nature, and value of the materials required, and the time payment will become due, and the surety is assumed to contract with knowledge of these facts. 191 U.S. at 425-426
  4. Contracts Law — Extension of Time — Prejudice Required Where a surety has contracted for an uncertain liability to unknown materialmen, a customary extension of credit to the principal obligor, unaccompanied by any loss or injury to the surety, does not discharge the surety from liability; the rule of strictissimi juris ought not to be extended to contracts outside its reason, particularly where the bond is underwritten by a corporation that has undertaken for profit to insure against the principal's failure of performance. 191 U.S. at 426-427
  5. Federal Government Contracts — Bond for Materialmen — "Promptly Make Payment" A bond covenant that the principal shall "promptly" pay materialmen is satisfied by payment that the subcontractor accepts as promptly made, and does not require payment on the very day the bills become due; the failure of immediate payment cannot be set up by the surety as a defense, since a contrary narrow construction would destroy the principal value of the security. 191 U.S. at 426
  6. Contracts Law — Third-Party Beneficiaries A covenant in a public works bond for the prompt payment of materialmen inures solely to the benefit of the subcontractors, not the government obligee, and should be interpreted liberally in favor of the subcontractor to further the beneficent object of the statute, though this rule does not extend to cases of fraud or unfair dealing by the subcontractor. 191 U.S. at 425, 427