Opinion · Supreme Court of the United States

United States v. Bethlehem Steel Co.

205 U.S. 105

Type
Opinion
Court
Supreme Court of the United States
Jurisdiction
Federal
Date
1907-03-11
Topic
general

How later courts describe this case

  • noting courts will enforce liquidated damages clauses “without proof of the damages actually sustained”
  • “The amount is not so extraordinarily disproportionate to the damage which might result from the [breach], as to show that the parties must have intended a penalty and could not have meant liquidated damages.”

Citator

UpLaw has not yet analyzed United States v. Bethlehem Steel Co.. The absence of a flag is not a finding that it is good law.

Cited by
204 opinions

Headnotes

  1. Contracts Law — Parol Evidence Rule The rule that prior negotiations are merged in a written contract is general in nature and does not preclude reference to letters exchanged between the parties before the contract's execution where the contract's language regarding deductions for delay leaves room for construction as to whether the parties intended a penalty or liquidated damages. 205 U.S. 105
  2. Contracts Law — Interpretation Prior negotiations may be referred to not for the purpose of making a contract for the parties, but to understand what contract was actually made, where doubt exists as to the meaning of language actually used in the agreement. 205 U.S. 105
  3. Contracts Law — Liquidated Damages The question whether a stipulated sum for delay in performance is a penalty or liquidated damages depends on the intention of the parties as disclosed by the language used and the circumstances surrounding the contract, and when that intention is ascertained it is ordinarily the duty of the court to carry it out; the mere use of the word "penalty" is not conclusive of the technical legal character of the provision. 205 U.S. 105
  4. Contracts Law — Liquidated Damages Where, in response to Government advertisements, the same party submits different bids with the largest price corresponding to the shortest time of delivery, the acceptance of the bid for the shorter time is evidence that the element of time is of the essence, and a stipulated deduction per day equivalent to the difference between the short and long time for delivery is to be construed as liquidated damages for whatever delay occurs, and not as a penalty, although the word "penalty" may have been used in some portions of the contract. 205 U.S. 105
  5. Contracts Law — Liquidated Damages A stipulated per diem deduction for delay is properly regarded as liquidated damages where the circumstances are such that it would be almost necessarily impossible to show what damages would naturally result from a failure to fulfill the contract, and the amount is not so disproportionately large relative to the damage that might result as to show the parties must have intended a penalty. 205 U.S. 105
  6. Contracts Law — Liquidated Damages The fact that after the contract was signed the importance of time as an element largely disappeared and practically no damage accrued to the party aggrieved on account of the failure to deliver cannot affect the meaning of the liquidated damages clause as used in the contract or render its language substantially worthless as security for performance. 205 U.S. 105