The Baseline Schedule, Time Impact Analysis, and Delay Damages Toolkit
40 U.S.C. § 3131
- Type
- Toolkit
- Jurisdiction
- National
- Date
- 2025-06-29
- Topic
- Construction
This toolkit supplies the documents that make a construction schedule claim provable and the forms that create the record before anyone anticipates a dispute. It opens with a delay event log, a notice letter, and a time extension request incorporating the schedule analysis that constructive acceleration claims require. Analysis tools include a windows worksheet identifying the controlling critical path in each period, a concurrency analysis form, and a measured mile worksheet with its prerequisites stated. Damages tools cover extended field overhead and unabsorbed home office overhead calculations with the required showings. Project control tools include a daily report form, a request for information log, and a scheduling specification outline. Owner tools include a liquidated damages derivation memorandum and a claim evaluation worksheet. It closes with liquidating agreement terms, an authority map, and intake questions.
The Baseline Schedule, Time Impact Analysis, and Delay Damages Toolkit
Construction > Delay, Acceleration, and Construction Schedule Claims | Published 29 June 2025 - Updated 16 January 2026 | UpLaw - uplaw.us
Tool 1 — Delay event log
⚠️ Maintain from day one. Reconstructing this log later is the most common cause of missed notice.
| # | Date known | Event | Cause | Party responsible | Activities affected | Critical? | Notice sent (date) | Time extension requested | Owner response | Impact (days) |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | ☐ | ☐ |
☐ One row per event, entered the day it becomes known ☐ ☐ Notice deadline computed from the contract and entered as a due date ☐ ☐ Activities identified by schedule activity number ☐ ☐ Criticality determined from the current update, not from intuition ☐ ☐ Reviewed weekly against the notice deadlines ☐
Tool 2 — Delay notice letter
[Date] — DELIVERED BY [method required by the Contract]
To: [Owner], Attn: [ ] cc: [Architect / Construction Manager] Re: [Project]; Notice of Delay — [Event]
Pursuant to Section [ ] of the Contract, [Contractor] gives notice of a delay as follows.
1. Event. On [date], [describe what occurred, factually and without characterization].
2. Date first known. [Date], through [how].
3. Cause. [State the cause and, where applicable, the contract provision under which the Owner bears responsibility.]
4. Activities affected. Schedule activities [numbers and descriptions], which as of Update No. [ ] dated [ ] are on the critical path with [ ] days of total float.
5. Anticipated impact. [Contractor] presently anticipates an impact of approximately [ ] days to the Contract completion date. This estimate is preliminary; [Contractor] will submit a time impact analysis in accordance with Section [ ] when the effect can be quantified.
6. Mitigation. [Contractor] is [describe steps taken or proposed].
7. Reservation. [Contractor] reserves all rights to a time extension and to additional compensation, including field and home office overhead, escalation, equipment, and productivity impacts.
[Signature, title]
☐ Send within the contract period, without exception ☐ ☐ Retain proof of delivery ☐ ☐ Send even where the parties expect to resolve informally ☐ ☐ Do not characterize or argue; state facts and reserve rights ☐
Tool 3 — Time extension request
[Date]
To: [Owner] Re: [Project]; Request for Extension of Time — [Event(s)]
Pursuant to Section [ ], [Contractor] requests an extension of the Contract Time of [ ] calendar days.
1. Events. [List, with notice dates and reference numbers.]
2. Schedule of record. Update No. [ ], data date [ ], accepted or submitted on [ ].
3. Analysis. A time impact analysis is attached. For each event, the analysis inserts a fragnet into the schedule as it existed immediately before the event and recalculates. Results:
Event Schedule used Fragnet duration Completion before Completion after Impact (days) 4. Concurrency. During each impacted period, [Contractor]'s own work proceeded as follows: [describe, with reference to daily reports and manpower records]. No [Contractor]-caused delay independently affected the critical path during these periods.
5. Requested relief. Extension of the Contract completion date from [ ] to [ ].
6. Costs. [Contractor] reserves its right to compensation and will submit a cost proposal separately. [Or: A cost proposal is attached.]
7. Response requested by [date]. [Contractor] notes that if the extension is not granted and [Contractor] is required to maintain the current completion date, [Contractor] will be compelled to accelerate and will seek the resulting costs.
☐ ⚠️ Paragraph 7 is what preserves the constructive acceleration claim ☐ ☐ Attach the analysis and the native schedule files ☐ ☐ Track the owner's response deadline ☐
Tool 4 — Windows analysis worksheet
| Window | From | To | Schedule of record | Controlling path activities | Driver of the critical path | Party responsible | Days gained or lost |
|---|---|---|---|---|---|---|---|
| 1 | Update No. |
Procedure:
☐ Define windows by schedule update dates, or by significant events ☐ ☐ For each window, identify the critical path from the update in effect at its start ☐ ☐ Determine what actually drove progress during the window from daily reports ☐ ☐ Compare planned to actual completion of the controlling activities ☐ ☐ Attribute the variance ☐ ☐ Carry the resulting completion date forward to the next window ☐ ☐ Reconcile the cumulative result to the actual completion date ☐ ☐ ⚠️ A windows analysis that does not reconcile to the actual completion date has an unexplained gap, and the gap will be found.
Tool 5 — Concurrency analysis form
| Period | Owner delay event | Contractor activity status | Was contractor work delayed? | Independently critical? | Concurrent? | Basis |
|---|---|---|---|---|---|---|
| ☐ | ☐ | ☐ |
Evidence to assemble for each period:
☐ Daily reports showing crews, activities, and idle time ☐ ☐ Manpower curves planned versus actual ☐ ☐ Procurement logs and delivery dates for materials needed in the period ☐ ☐ Subcontractor correspondence regarding readiness ☐ ☐ Inspection records ☐ ☐ Any contractor-caused rework in the period ☐
Pacing documentation, where asserted:
☐ Contemporaneous record of the decision to slow ☐ ☐ Evidence the contractor had the ability to proceed ☐ ☐ Evidence the pace was a response to the owner delay rather than an independent constraint ☐ ☐ Communication to the owner at the time, where possible ☐
Tool 6 — Measured mile worksheet
| Period | Type | Activity | Quantity installed | Labor hours | Unit rate (hrs/unit) | Variance |
|---|---|---|---|---|---|---|
| Unimpacted ☐ Impacted ☐ |
Prerequisites to confirm before relying on this method:
☐ Same or substantially similar work in both periods ☐ ☐ Same crews, or comparable crew composition ☐ ☐ An identifiable unimpacted period of meaningful duration ☐ ☐ Quantities tracked by activity ☐ ☐ Labor hours coded to the same activities ☐ ☐ Impacting conditions documented and attributable ☐ ☐ Learning curve and weather effects considered ☐
Calculation:
☐ Unimpacted unit rate: ______ hours per unit ☐ ☐ Impacted unit rate: ______ hours per unit ☐ ☐ Lost hours = (impacted rate − unimpacted rate) × impacted quantity = ______ ☐ ☐ Loaded labor rate: $______ ☐ ☐ Productivity loss: $______ ☐ ☐ ⚠️ Without activity-coded labor data, this method is unavailable and the claim falls back to disfavored approaches.
Tool 7 — Extended overhead calculation
Extended field overhead, by month of the compensable extension:
| Item | Monthly cost | Months | Total |
|---|---|---|---|
| Project manager | |||
| Superintendent | |||
| Field engineer | |||
| Administrative | |||
| Office trailer and utilities | |||
| Storage and temporary facilities | |||
| Temporary power, water, sanitation | |||
| Small tools and consumables | |||
| Site security | |||
| Insurance and bond extension | |||
| Total |
☐ Actual costs, not estimates ☐ ☐ Only the compensable extension period included ☐ ☐ Costs already recovered through change orders excluded ☐
Unabsorbed home office overhead:
☐ Contract billings: $______ ☐ ☐ Total company billings for the period: $______ ☐ ☐ Allocation ratio: % ☐ ☐ Total home office overhead for the period: $ ☐ ☐ Allocable overhead: $______ ☐ ☐ Days of performance: ______ ☐ ☐ Daily rate: $______ ☐ ☐ Compensable delay days: ______ ☐ ☐ Amount: $______ ☐
Prerequisites:
☐ Owner-caused delay of uncertain duration ☐ ☐ Contractor required to remain on standby ☐ ☐ Inability to take on replacement work during the period ☐ ☐ ⚠️ All three must be established; the calculation alone is not enough.
Tool 8 — Daily report form
DAILY REPORT — [Project] — [Date]
Weather: start ______ mid-day ______ temperature range ______ precipitation ______ Ground conditions: ______
Manpower | Trade / Subcontractor | Foremen | Journeymen | Apprentices | Hours | Area / Activity | |---|---|---|---|---|---|
Equipment (identify operating versus idle, and reason for idle)
Work performed (by activity number and location, with quantities where measurable)
Deliveries received
Inspections requested / performed / result
Visitors and purpose
Delays or interferences — describe, with cause, duration, and crews affected
Directions received — from whom, content, and how communicated
Safety — incidents, observations, corrections
Photographs — reference numbers
Prepared by ______ Reviewed by ______
☐ Completed daily, on site ☐ ☐ Reviewed and preserved unaltered ☐ ☐ ⚠️ This is the most valuable document in any construction dispute ☐
Tool 9 — Request for information and submittal log
| No. | Date submitted | Subject | Drawing/spec reference | Response due | Response received | Days elapsed | Schedule activity affected | Impact noted |
|---|
☐ Contract response periods extracted and entered as due dates ☐ ☐ Follow-up sent when a response is overdue, and logged ☐ ☐ Impact on schedule activities noted contemporaneously, not later ☐ ☐ Patterns identified: repeated requests on the same drawings, indicating design deficiency ☐ ☐ Submittals logged with the same fields, including resubmittals and rejection reasons ☐ ☐ Long-lead items flagged with procurement durations ☐ ☐ ⚠️ Response time data persuades without an expert.
Tool 10 — Scheduling specification outline (owner)
☐ Required software and native file submission with every update ☐ ☐ Baseline submission deadline, content requirements, and acceptance process ☐ ☐ Maximum activity duration ☐ ☐ Required activity coding: area, trade, responsibility, phase ☐ ☐ Restrictions on constraints, negative lags, and out-of-sequence progress ☐ ☐ Monthly update requirement with a narrative addressing progress, logic changes, and delays ☐ ☐ Requirement that logic and duration changes be identified and explained ☐ ☐ Express float ownership provision ☐ ☐ Requirement that any time extension request include a time impact analysis in a specified form ☐ ☐ Requirement that the contractor identify the critical path in each update ☐ ☐ Retention and delivery of native files for a period after completion ☐ ☐ Consequences for non-conforming submissions, including withholding of payment ☐
Tool 11 — Liquidated damages derivation memorandum (owner)
MEMORANDUM — DERIVATION OF LIQUIDATED DAMAGES RATE
Project: [ ] Date: [ ] Prepared by: [ ]
1. Anticipated losses from late completion. Extended construction financing: $______ per day (basis: loan amount × rate ÷ 365) Additional rent or holdover at existing facility: $______ per day Lost revenue or delayed occupancy: $______ per day (basis: ) Extended consultant fees: $ per day Extended owner staff: $______ per day Additional moving or transition costs: $______ Other: ______
2. Total anticipated daily loss: $______
3. Rate adopted: $______ per calendar day. [If lower than the computed loss, note that the rate is conservative.]
4. Difficulty of estimation. Actual damages from delayed completion are difficult to determine with precision because [ ].
5. Conclusion. The rate is a reasonable forecast of anticipated loss and is not a penalty.
☐ Prepare before bid and retain ☐ ☐ Revisit if the project scope or schedule changes materially ☐ ☐ ⚠️ Penalty analysis applies at contracting — Priebe & Sons v. United States — so the memorandum must predate the contract.
Tool 12 — Claim evaluation worksheet (owner)
| Item | Finding |
|---|---|
| Notice for each event: timely? | ☐ |
| Claim submission: timely? | ☐ |
| Supplementation: timely? | ☐ |
| Each event within a relief clause? | ☐ |
| Characterization accurate? | ☐ |
| Activities critical at the time, per the contractor's own updates? | ☐ |
| Float available and consumed by whom? | ☐ |
| Contractor performance during each period | |
| Concurrent delay identified? | ☐ |
| Causation, including intervening causes | |
| Costs actual, documented, allocable? | ☐ |
| Markups per contract? | ☐ |
| Home office overhead prerequisites met? | ☐ |
| Double counting between categories? | ☐ |
| Offsets: liquidated damages, backcharges, defective work, prior payments | |
| Independent consultant engaged? | ☐ |
| Quantified owner position | $ |
Tool 13 — Liquidating agreement terms
LIQUIDATING AGREEMENT
- Recitals. [Subcontractor] asserts claims arising from acts or omissions of [Owner]. [Contractor] has no independent damages for these impacts.
- Admission of liability, liquidated. [Contractor] acknowledges liability to [Subcontractor] for the claims described in Exhibit A, liquidated to and payable solely out of amounts actually recovered from [Owner] on account of those claims.
- Prosecution. [Contractor] shall present and prosecute the claims in its own name, in good faith, and shall keep [Subcontractor] informed.
- Cooperation. [Subcontractor] shall provide all records, witnesses, and analysis required, at its own cost, and shall cooperate in discovery.
- Costs. Costs of prosecution, including expert and legal fees, shall be [allocated as follows].
- Settlement. [Contractor] shall not settle the [Subcontractor] portion without [Subcontractor]'s consent, not to be unreasonably withheld.
- Distribution. Amounts recovered attributable to the [Subcontractor] claims shall be paid to [Subcontractor] within [ ] days of receipt, net of allocated costs.
- No independent liability. Except as provided herein, [Contractor] has no liability to [Subcontractor] for the claims described.
- Release. Upon distribution, [Subcontractor] releases [Contractor] from the claims described.
☐ Execute before submitting the claim ☐ ☐ Attach a schedule identifying the claims covered ☐ ☐ Confirm enforceability in the governing jurisdiction ☐
Tool 14 — Authority map
Tool 15 — Intake questions
☐ What is the contract completion date, and what is the actual or projected date? ☐ ☐ Was there an accepted baseline schedule, and do you have the native file? ☐ ☐ Were monthly updates submitted, and were they genuinely updated? ☐ ☐ What events do you say delayed the project, and on what dates? ☐ ☐ Did you send written notice for each, and when? ☐ ☐ Did you request time extensions, and what happened? ☐ ☐ Were you told to maintain the original completion date? ☐ ☐ What was your own work doing during each of these periods? ☐ ☐ Do your daily reports exist for the whole project? ☐ ☐ Is labor coded to activities? ☐ ☐ What does the contract say about notice, and about damages for delay? ☐ ☐ Is there a liquidated damages provision, and at what rate? ☐ ☐ Is this a public contract, and if federal, has a certified claim been submitted? ☐
Related Documents
- The Schedule Is the Evidence: How Construction Delay Claims Are Actually Won and Lost
- Construction Delay and Acceleration: A Comprehensive Guide to Critical Path Analysis, Concurrency, Notice, and Damages
- Preserving or Defeating a Construction Delay Claim: A Practical Checklist
- Claim Construction and the Markman Hearing: A Practical Checklist
- The Surety Bond, Miller Act, and Construction Claim Toolkit
- Construction Site Safety: A Comprehensive Guide to Fall Protection, Scaffolds, Excavations, Multi-Employer Citations, and Inspections
- Pursuing or Defending a Construction Defect Claim: A Practical Checklist
- Litigating Design Patents: From Claim Construction to Total-Profit Damages
- Running a Safe Site or Contesting a Construction Citation: A Practical Checklist
- Cited for a Hazard That Endangered Somebody Else's Crew: How Construction Safety Liability Actually Works
- The Construction Law Toolkit
- Hiring a Contractor and Resolving a Construction Dispute: A Practical Checklist
- The Crack That Took Nine Years to Appear: How Construction Defect Law Actually Works
- Buying and Selling a Home: A Comprehensive Guide to Contracts, Contingencies, Title, and Closing
- The Consumer Contract Cancellation Toolkit
- Force Majeure, Impossibility, and Excuse: A Comprehensive Guide to Contract Performance Under Disruption
- The Contract Risk Allocation Toolkit
- Electronic Signatures and Online Contract Formation: A Comprehensive Guide to ESIGN, UETA, and Clickwrap
- Bidding on a Federal Contract: A Compliance Checklist
- Classifying Workers: Employee or Independent Contractor — A Practical Checklist
- Starting and Running a Small Business: A Comprehensive Guide to Entity Choice, Licensing, Contracts, and Employees
- The Kitchen That Never Got Finished: Home Improvement Contracts and How They Go Wrong
- The Government Contracts Toolkit
- Bumped, Delayed, and Denied: What Airlines and Travel Companies Actually Owe You
- Construction Law: A Comprehensive Guide to Contracts, Delay Claims, and Defect Litigation
- Consumer Banking and Payments: A Comprehensive Guide to Accounts, Holds, Overdrafts, and Error Resolution
- The Payment Dispute, Wire Recall, and Fraud Recovery Toolkit
- Applying for Benefits and Appealing a Denial, Reduction, or Overpayment: A Practical Checklist
- Auditing a Referral Arrangement and Answering an Overpayment Demand: A Practical Checklist
- Resolving a Bank Account, Hold, or Payment Dispute: A Practical Checklist
- The Payment That Outlasts the Marriage: How Alimony Is Actually Decided
- Health Care Fraud and Abuse: A Comprehensive Guide to the Anti-Kickback Statute, Stark Law, and Overpayments
- Public Benefits: A Comprehensive Guide to SNAP, Cash Assistance, Eligibility, Overpayments, and Fair Hearings
- Making a Payment Bond Claim and Responding to a Surety Demand: A Practical Checklist
- Payments, Unauthorized Transfers, and Fraud: A Comprehensive Guide to Regulation E, Wires, Checks, and Chargebacks