This toolkit collects the working documents used to preserve, prosecute, and defend construction bond claims. It contains a project intake form capturing the two dates that control everything, a bond request letter, a tier analysis worksheet, a ninety-day notice template with a service protocol, a deadline calculator, a proof of claim index, a Miller Act complaint outline, an owner's performance bond default letter, a surety demand response protocol, an indemnity agreement negotiation checklist, a Little Miller Act comparison worksheet, and a subrogation priority reference. Each is drafted to be adapted to the project and jurisdiction. A related materials index maps each tool to the guides, articles, and checklists that explain it.
The Surety Bond, Miller Act, and Construction Claim Toolkit
Insurance > Surety Bonds and Construction Payment Security | Published 18 September 2025 - Updated 12 August 2026 | UpLaw - uplaw.us
Tool 1 belongs in every project file at mobilization. Tool 4 costs nine dollars and preserves the entire claim.
Tool 1 — Project Intake Form
Complete at mobilization, not when payment is late.
| Field | Entry |
|---|---|
| Project name and location | |
| Owner type: ☐ federal ☐ state/municipal ☐ private | |
| Prime contractor legal name | |
| Party we contracted with (exact legal name) | |
| Our tier: ☐ first ☐ second ☐ third ☐ uncertain | |
| Contract / purchase order number and amount | |
| Payment bond exists? ☐ yes ☐ no ☐ requested [date] | |
| Bond number / surety / penal sum | |
| Governing statute: ☐ 40 U.S.C. § 3133 ☐ [State] Little Miller Act ☐ common law bond ☐ lien only | |
| Attorney's fee clause in our subcontract? ☐ yes ☐ no | |
| Mobilization date | |
| ★ LAST DAY LABOR OR MATERIAL FURNISHED ★ | |
| ★ NOTICE DEADLINE (last work + 90, or state period) ★ | |
| ★ SUIT DEADLINE (last work + 1 year, or state period) ★ |
⚠ The two starred date fields are the entire claim. Companies that collect on bonds have them on the intake form; companies that rely on the relationship do not.
📌 There is no fee-shifting under the Miller Act — F.D. Rich Co. v. United States ex rel. Industrial Lumber Co., 417 U.S. 116. Negotiate the fee clause into the subcontract before signing.
Tool 2 — Bond Request Letter
[Date] · [Contracting Officer / Awarding Authority]
Re: Request for copy of payment bond and contract — [Project], Contract No. ______
The undersigned is furnishing [labor / material / both] for the prosecution of the work under the above contract, as a [subcontractor to / supplier to] [name].
Pursuant to 40 U.S.C. § 3133 [or: State Code § ______], we request a certified copy of the payment bond furnished for this contract, together with a copy of the contract and any modifications.
Our contract or purchase order number is ______, dated , in the amount of $.
[Signature · Company · Address · Phone]
Record from the bond: surety legal name and address · bond number · penal sum · obligee · principal's exact legal name · any notice provisions the bond itself imposes.
Verify federal surety qualification: 31 U.S.C. § 9304 (conditions) · 31 U.S.C. § 9305 (certificate of authority) · 31 U.S.C. § 9306 (obligations in the district) · 31 U.S.C. § 9309 (priority).
Confirm no alternative or waiver applies: 40 U.S.C. § 3132 · 40 U.S.C. § 3134.
Tool 3 — Tier Analysis Worksheet
Map the chain, in exact legal names:
Owner ______ └ Prime contractor ______ ← bond principal; bond required by 40 U.S.C. § 3131 └ ______ (subcontractor ☐ / materialman ☐) └ ______ (subcontractor ☐ / materialman ☐) └ US ______
| Our counterparty is | Our tier | Protected? | Notice required |
|---|---|---|---|
| The prime contractor | first | yes | no |
| A subcontractor | second | yes | yes — 90 days |
| A materialman or sub-subcontractor | third | generally no | n/a |
Characterizing each intermediate party — the question that decides the case:
☐ Did it perform a definable part of the prime contract? → subcontractor ☐ Did it merely sell goods? → materialman ☐ How substantial was its scope relative to the prime contract? ☐ Did the prime rely on it to perform, or merely to deliver? ☐ Was there a written subcontract, a schedule of values, retainage, and lien waivers? → subcontractor indicators
⚠ Clifford F. MacEvoy Co. v. United States ex rel. Calvin Tomkins Co., 322 U.S. 102 — a materialman supplying a materialman is outside the Act. J.W. Bateson Co. v. United States ex rel. Board of Trustees, 434 U.S. 586 — the tier limitation applies regardless of the claimant's identity, including benefit fund trustees.
📌 Watch for joint ventures and affiliates that obscure the chain. A nominal second-tier position sometimes turns out to be third.
Tool 4 — Ninety-Day Notice and Service Protocol
[Date] · Certified mail, return receipt requested, AND [courier with delivery verification]
[PRIME CONTRACTOR legal name and address — not the surety, not the owner]
Re: Notice of claim under 40 U.S.C. § 3133 — [Project], Contract No. ______
1. Claimant: [legal name, address] 2. Party to whom labor or material was furnished: [exact legal name] 3. Labor and material furnished: [describe] 4. Last date labor performed or material supplied: ______ 5. Amount claimed: $______, unpaid
More than ninety days have elapsed since the undersigned last furnished labor or material, and payment has not been made in full.
Our standard practice is to preserve payment bond rights on every public project. This notice is not intended as a dispute, and we remain available to resolve the balance.
[Signature · Title · Phone · Email] cc: [Surety] · [Contracting Officer]
Service protocol: ☐ Addressed to the prime contractor at its residence or place of business ☐ Sent by a means producing written third-party verification of delivery, or in a manner in which a United States marshal may serve summons ☐ Sent within ninety days of the last-work date ☐ Delivery confirmation retained permanently — it is an element of the claim
Content requirements — all four must appear: ☐ Amount claimed, with substantial accuracy ☐ Name of the party to whom the labor or material was furnished ☐ Project and contract identification ☐ Statement that payment has not been made
⚠ A pre-work waiver of bond rights is void. A waiver is enforceable only in writing, signed by the claimant, and executed after the labor or material was furnished.
Tool 5 — Deadline Calculator
| Input | Value |
|---|---|
| Last day labor performed or material supplied | ______ |
| Project type | ☐ federal ☐ state ☐ private |
| Our tier | ☐ first ☐ second ☐ third |
| Deadline | Federal | Fill in |
|---|---|---|
| Right to sue accrues | last work + 90 days unpaid | ______ |
| Notice to prime (second tier only) | last work + 90 days | ______ |
| Suit on the bond | last work + 1 year | ______ |
| State project — notice | per Little Miller Act (60/75/90/120) | ______ |
| State project — suit | per Little Miller Act (6 mo / 1 yr / 2 yr) | ______ |
| Mechanic's lien (private) | per state lien statute | ______ |
| Bond's own limitation (common law bond) | per the bond's text | ______ |
What counts as "last work": substantial work under the contract, including authorized change order work; delivery of material incorporated in or specially fabricated for the project.
⚠ What does NOT extend the clock: punch list · warranty callbacks · corrective work on defective installation · inspection visits · replacement parts for defective goods · work performed solely to extend the deadline.
Set two calendar entries at project closeout: day sixty (prepare notice) and month ten (prepare suit).
Tool 6 — Proof of Claim Index
| # | Item | Obtained | Notes |
|---|---|---|---|
| 1 | Payment bond (certified copy) | ☐ | penal sum, surety, principal |
| 2 | Prime contract and modifications | ☐ | |
| 3 | Our subcontract or purchase order | ☐ | check for fee clause |
| 4 | Agreement between our counterparty and the prime | ☐ | establishes tier |
| 5 | Signed delivery tickets / bills of lading | ☐ | establishes last work |
| 6 | Daily reports, sign-in logs, photographs | ☐ | |
| 7 | Invoices and account ledger | ☐ | |
| 8 | Payments received, with dates | ☐ | |
| 9 | Change orders and written authorizations | ☐ | |
| 10 | Correspondence — every promise to pay | ☐ | |
| 11 | Retainage withheld | ☐ | recoverable |
| 12 | Fringe benefit / trust fund records | ☐ | Sherman v. Carter, 353 U.S. 210 |
| 13 | Ninety-day notice + delivery verification | ☐ | element of the claim |
| 14 | Segregation of bonded vs. unbonded work | ☐ |
Recoverable: sums justly due; retainage; fringe benefit contributions; interest per the subcontract or applicable law. Fees only if the subcontract provides them — F.D. Rich Co., 417 U.S. 116.
Tool 7 — Miller Act Complaint Outline
UNITED STATES OF AMERICA for the use and benefit of [CLAIMANT] v. [PRIME CONTRACTOR] and [SURETY] United States District Court for the ______ District of ______
I. Jurisdiction and venue. 40 U.S.C. § 3133; the district in which the contract was performed; without regard to amount in controversy.
II. Parties. Claimant; prime contractor (principal); surety.
III. The contract and the bond. Award date; the payment bond furnished under 40 U.S.C. § 3131; bond number and penal sum.
IV. Claimant's tier. The contract chain, and that claimant had a direct contractual relationship with [the prime / a subcontractor], placing it within the Act. Clifford F. MacEvoy Co., 322 U.S. 102.
V. Labor and material furnished. Description; dates; the last day furnished.
VI. Nonpayment. Amount due; more than ninety days elapsed.
VII. Notice (second-tier claimants — plead affirmatively). Date sent; addressed to the prime; contents (amount with substantial accuracy; party supplied); manner of service; date of delivery verification.
VIII. Timeliness. Suit filed within one year of the last-work date.
IX. Claim on the payment bond. Sums justly due, including [retainage / fringe benefits / interest].
X. Prayer. Judgment against the surety and principal; interest; costs; fees pursuant to the subcontract [there is no statutory fee-shifting].
Plead notice and tier first — the surety will raise both. Federal law governs construction: F.D. Rich Co., 417 U.S. 116; Clearfield Trust Co. v. United States, 318 U.S. 363.
Anticipated defenses: wrong tier · late or defective notice · suit beyond one year · defective work, backcharges, prior payment · material furnished for a different contract.
Tool 8 — Owner's Performance Bond Default Letter
[Date] · Certified mail and email · [Surety, claims department] · cc: [Principal]
Re: Declaration of default and demand — [Project], Contract No. ______; Performance Bond No. ______
1. Notice of default. [Owner] previously notified [Principal] and the Surety of performance deficiencies by letters dated ______ [attach].
2. Declaration. [Principal] is hereby declared in default under the Contract, effective ______, for [state grounds with contract citations].
3. Termination. The Contract is terminated pursuant to Section ______, effective ______.
4. Demand. [Owner] demands that the Surety perform its obligations under the Performance Bond and elect among its options — financing the Principal, tendering a completion contractor, taking over and completing, or paying [Owner]'s damages up to the penal sum.
5. Contract balance. The remaining balance of $______ is being retained and has not been disbursed, and will be made available to the Surety in accordance with the Bond.
6. Access. [Owner] will make the site, drawings, and records available for the Surety's investigation and requests a response by ______.
[Signature]
⚠ Owner errors that discharge or reduce the surety's obligation: terminating without required notice · never formally declaring default · disbursing the contract balance · overpaying against the schedule of values · materially altering the contract without consent · failing to give the surety its election · delaying notice until costs escalate.
📌 The contract balance is the surety's collateral. Prairie State Bank v. United States, 164 U.S. 227 (subrogation relates back to the date of the bond); Henningsen v. United States Fidelity & Guaranty Co., 208 U.S. 404 (extends to a surety paying laborers and materialmen).
Tool 9 — Surety Demand Response Protocol
For the contractor whose surety has paid or demands collateral. Treat as a solvency event.
Step 1 — Read the general indemnity agreement. Locate and quote: ☐ Indemnity scope ☐ Personal indemnitors (who signed, including spouses) ☐ Collateral on demand ☐ Assignment of contract balances and receivables ☐ Right to settle ☐ Conclusive-evidence / voucher clause ☐ Access and takeover ☐ Waiver of defenses
Step 2 — Demand the surety's documentation, in writing:
"Please provide, for each claim paid or reserved: the claimant's identity and tier; the date and content of any ninety-day notice and proof of its service; the date suit was filed, if any; proof of actual payment; the invoices supporting the amount; and the calculation supporting the collateral demand."
Step 3 — Audit every claim the surety paid:
| Claimant | Tier | Notice date | Within 90 days of last work? | Suit within 1 yr? | Amount | Was the surety obligated? |
|---|---|---|---|---|---|---|
| ☐ | ☐ | ☐ |
⚠ A surety that paid a THIRD-TIER claimant, or one whose notice was untimely, paid a claim it did not owe. Clifford F. MacEvoy Co., 322 U.S. 102. This is the principal's real leverage.
Step 4 — Identify offsets: contract balances the surety collected · salvage · recoveries from others · amounts within the penal sum already satisfied.
Step 5 — Assess the collateral demand. Reasoned exposure calculation, or reflexive? Some jurisdictions require good faith.
Step 6 — Preserve the bad faith settlement theory where the principal disputed a claim in writing before payment.
Step 7 — Understand the posture honestly. The conclusive-evidence clause makes this uphill, and the principal's belief that a claim was defensible is generally not a defense.
Step 8 — If insolvency follows, know that the surety generally takes retainage ahead of the trustee — Pearlman v. Reliance Insurance Co., 371 U.S. 132 — subject to the government's prior setoff, United States v. Munsey Trust Co., 332 U.S. 234, with statutory priority at 31 U.S.C. § 9309.
Tool 10 — Indemnity Agreement Negotiation Checklist
Obtainable at inception for established contractors. Unobtainable afterward.
| # | Term | Ask for | Got it |
|---|---|---|---|
| 1 | Collateral on demand | Cap, or a reasoned exposure calculation rather than a bare demand | ☐ |
| 2 | Reimbursement trigger | Actual payment, not reserves | ☐ |
| 3 | Notice and cure | Written notice and an opportunity to resolve before any demand | ☐ |
| 4 | Spousal indemnity | Carve-out | ☐ |
| 5 | Personal indemnity | Sunset after a defined period of clean performance | ☐ |
| 6 | Conclusive-evidence clause | Inapplicable where the principal disputed the claim in writing before payment | ☐ |
| 7 | Duty of good faith | Express, in settling claims | ☐ |
| 8 | Definition of "loss" | Exclude costs incurred unreasonably | ☐ |
| 9 | Consultant and fee recovery | Reasonableness standard | ☐ |
| 10 | Assignment trigger | On default only, not on the surety's subjective belief | ☐ |
⚠ The sentence to say out loud before signing: "This is not insurance. If the surety pays a dollar, I owe it a dollar plus fees, and my house is collateral."
Tool 11 — Little Miller Act Comparison Worksheet
Complete once per state and keep it. Never carry federal habits into a state project.
| Item | Federal | [State] |
|---|---|---|
| Bond threshold | statutory | |
| Notice deadline | 90 days from last work | |
| Notice runs from | last labor/material | |
| Notice recipients | prime only | (many states add owner) |
| Notice contents | amount + party supplied | |
| Notice service method | third-party verified delivery | |
| Limitations period | 1 year from last work | |
| Tier coverage | first and second | (some states broader) |
| Attorney's fees | none — F.D. Rich | (many states allow) |
| Prompt payment act interest | — | |
| Trust fund statute | — | |
| Retainage limits | — |
Tool 12 — Subrogation and Priority Reference
Who gets the retained contract funds when the contractor fails:
| Rank | Claimant | Authority |
|---|---|---|
| 1 | The United States, by setoff for debts the contractor owes it | United States v. Munsey Trust Co., 332 U.S. 234 |
| 2 | The surety, by subrogation to the rights of those it paid and of the obligee | Pearlman v. Reliance Insurance Co., 371 U.S. 132 |
| 3 | Assignees and secured lenders taking after the bond date | subordinate under Prairie State Bank, 164 U.S. 227 |
| 4 | The bankruptcy trustee and unsecured creditors | funds were never property of the estate — Pearlman |
Key principles: the surety's equity relates back to the date of the bond (Prairie State Bank); it extends to a surety that paid laborers and materialmen, not only one that completed (Henningsen, 208 U.S. 404); and federal law governs (Clearfield Trust Co., 318 U.S. 363).
Surety practice: perfect the assignment under the indemnity agreement · notify the obligee immediately · assert subrogation expressly in any bankruptcy · object to turnover of contract funds.
Lender practice: a blanket lien on a contractor's receivables is likely subordinate as to bonded contract funds. Price accordingly.
Tool 13 — Related Materials Index
| If you need to | Read |
|---|---|
| Understand the whole field | the comprehensive guide |
| Explain suretyship to a client | the article |
| Work a live claim | the checklist |
| Handle a private project | Mechanics Liens · The Paper That Beats Everyone Else · Secured Transactions and Liens |
| Understand federal contracting | Selling to the Government |
| Collect a judgment | Judgment Enforcement and Debtor Exemptions · Filing, Trying, and Collecting a Small Claims Judgment · Small Claims and Self-Representation · Justice Without a Lawyer |
| Handle the contractor's insolvency | Chapter 11 Reorganization · Filing a Proof of Claim · Restructuring a Business or Filing a Business Bankruptcy |
| Handle the title and closing side | Title, Survey, and Closing Problems |
| Compare to a first-party insurance claim | Property Insurance Claims |
| Handle another possessory lien problem | Towing, Impoundment, and Vehicle Repair · Moving Companies and Self-Storage · The Moving, Storage, and Household Goods Claim Toolkit |
| Choose the entity | Business Taxation |
Tool 14 — Authority Quick Reference
Miller Act: 40 U.S.C. § 3131 (bond required) · § 3132 (alternatives) · § 3133 (the claim, notice, and limitations) · § 3134 (waiver) Surety qualification and priority: 31 U.S.C. § 9304 · § 9305 · § 9306 · § 9309 Tier and coverage: Clifford F. MacEvoy Co. v. United States ex rel. Calvin Tomkins Co., 322 U.S. 102 · J.W. Bateson Co. v. United States ex rel. Board of Trustees, 434 U.S. 586 Recovery: United States ex rel. Sherman v. Carter, 353 U.S. 210 (fringe benefits) · F.D. Rich Co. v. United States ex rel. Industrial Lumber Co., 417 U.S. 116 (no fee-shifting; federal law governs) Subrogation and priority: Prairie State Bank v. United States, 164 U.S. 227 · Henningsen v. United States Fidelity & Guaranty Co., 208 U.S. 404 · Pearlman v. Reliance Insurance Co., 371 U.S. 132 · United States v. Munsey Trust Co., 332 U.S. 234 Federal common law: Clearfield Trust Co. v. United States, 318 U.S. 363
Related Documents
- Surety Bonds and Construction Payment Security: A Comprehensive Guide to Payment Bonds, Performance Bonds, Miller Act Claims, and Indemnity
- The Promise Behind the Promise: How Surety Bonds Actually Work
- Making a Payment Bond Claim and Responding to a Surety Demand: A Practical Checklist
- Mechanics Liens and the Right to Get Paid for Work Performed
- The Paper That Beats Everyone Else: How Security Interests and Liens Decide Who Gets Paid
- Secured Transactions and Liens: A Comprehensive Guide to Article 9 Perfection, Priority, and Foreclosure
- Selling to the Government: How Federal Contracting Actually Works
- Judgment Enforcement and Debtor Exemptions: A Comprehensive Guide to Garnishment, Liens, and Levies
- Small Claims and Self-Representation: A Comprehensive Guide to Filing, Proving, and Collecting
- Filing, Trying, and Collecting a Small Claims Judgment: A Practical Checklist
- Title, Survey, and Closing Problems: A Comprehensive Guide to Defects, Insurance, and Cures
- Property Insurance Claims: A Comprehensive Guide to Coverage, Proof of Loss, Appraisal, and Bad Faith
- Chapter 11 Reorganization: A Comprehensive Guide for Debtors and Creditors
- Filing a Proof of Claim in a Bankruptcy Case: A Practical Checklist
- Restructuring a Business or Filing a Business Bankruptcy: A Practical Checklist
- Business Taxation: A Comprehensive Guide to Entity Choice and Federal Income Tax
- Moving Companies and Self-Storage: A Comprehensive Guide to Estimates, Carmack Claims, Liens, and Auctions
- The Moving, Storage, and Household Goods Claim Toolkit
- Towing, Impoundment, and Vehicle Repair: A Comprehensive Guide to Notice, Liens, Hearings, and Recovery
- Justice Without a Lawyer: What Small Claims Court Can and Cannot Fix