Checklist · Environmental
Obtaining a Permit and Responding to a Notice of Violation: A Practical Checklist
33 U.S.C. § 1342
- Type
- Checklist
- Jurisdiction
- National
- Date
- 2024-11-26
- Topic
- Environmental
This checklist runs the four operations in environmental compliance. Part A obtains a permit, from authorization mapping through issuance and appeal. Part B builds the compliance program — reading the permit, the calendar, and the applicability protocol that prevents the most expensive category of enforcement. Part C handles inspections. Part D responds to a notice of violation, hour by hour and then week by week, through penalty negotiation and consent decree terms. Separate parts cover self-disclosure, citizen suit notices, permit renewal and transfer, and transactional diligence. A final part lists the actions that convert a civil matter into a criminal one.
Obtaining a Permit and Responding to a Notice of Violation: A Practical Checklist
Environmental > Permitting and Compliance | Published 26 November 2024 - Updated 26 July 2026 | UpLaw - uplaw.us
Part A — Obtaining a Permit
A1. Map the Authorizations
- [ ] List every federal, state, and local authorization the project needs, with dependencies.
- [ ] Water: discharge permit under 33 U.S.C. § 1342; dredge and fill under 33 U.S.C. § 1344; stormwater coverage; spill prevention plan under 40 C.F.R. part 112.
- [ ] Air: preconstruction review under 42 U.S.C. § 7475; performance standards under 42 U.S.C. § 7411; operating permit under 42 U.S.C. § 7661a; state implementation plan requirements at 40 C.F.R. part 52 and 40 C.F.R. part 70.
- [ ] Waste: generator status; permit if applicable under 42 U.S.C. § 6925 and 40 C.F.R. part 270; waste identification under 40 C.F.R. part 260.
- [ ] Determine whether a federal permit triggers environmental review under 42 U.S.C. § 4321 and 42 U.S.C. § 4332 — if so, it is the critical path.
- [ ] Check species consultation obligations where a federal action is involved.
- [ ] Check drinking water implications under 42 U.S.C. § 300f for injection or public systems.
- [ ] Obtain a jurisdictional determination for any water feature, under Sackett v. Environmental Protection Agency, 598 U.S. 651 — and separately under state law, which may be broader.
- [ ] Schedule backward from the permit, not forward from the design.
A2. Prepare
- [ ] Hold a pre-application meeting and record what the agency identifies as its concerns.
- [ ] Commission the technical work: control technology determination and modeling for air; discharge characterization and receiving water analysis for water; design, closure, post-closure, and financial assurance for waste.
- [ ] Disclose fully. Disclosure is what makes the permit shield protective; omission is not, and can be an independent violation.
- [ ] Check the application for completeness against the agency's checklist. Incompleteness restarts the clock.
- [ ] Obtain required certifications and signatures, including engineering certifications.
A3. Public Process and Issuance
- [ ] Track the draft permit publication and comment period under 40 C.F.R. part 124.
- [ ] Read every comment and respond substantively — issues not raised are generally waived on later review.
- [ ] Attend the hearing if one is held.
- [ ] Review the final permit line by line before the appeal window closes.
- [ ] Appeal any condition you cannot live with, administratively then judicially, on the record and within the deadline. Unchallenged conditions bind for the term.
- [ ] Calendar the expiration and the renewal application deadline the day the permit issues.
Part B — The Compliance Program
B1. Read the Permit
- [ ] Cover page: permittee, facility, number, effective date, expiration date.
- [ ] Authorized activities — and by implication what is not authorized.
- [ ] Limits by parameter, with averaging periods. A daily maximum and a monthly average are separate obligations.
- [ ] Monitoring: parameter, frequency, sample type, method.
- [ ] Recordkeeping: what, and for how long.
- [ ] Reporting: what, to whom, on what form, by when — including immediate notification triggers measured in hours.
- [ ] Standard conditions: duty to comply, duty to mitigate, proper operation and maintenance, duty to provide information, inspection and entry, signatory requirements.
- [ ] Special conditions, compliance schedules, and required studies.
B2. Build One Calendar
Every entry needs a named owner and a named backup.
- [ ] Daily and weekly inspection rounds with a logbook.
- [ ] Monitoring and sampling by parameter and frequency.
- [ ] Quarterly reports.
- [ ] Annual compliance certifications, signed by a responsible official who has seen the data.
- [ ] Waste accumulation start dates and shipment deadlines by container.
- [ ] Manifest reconciliation and exception reporting.
- [ ] Tank testing and inspection intervals.
- [ ] Training refreshers with sign-in sheets.
- [ ] Plan reviews: pollution prevention, spill prevention, contingency.
- [ ] Permit expirations and renewal application deadlines, with a one-year reminder.
- [ ] Financial assurance renewals and fee payments.
B3. The Applicability Protocol
⭐ The single control that prevents the most expensive cases.
- [ ] Standing rule: no construction, modification, process change, or equipment replacement proceeds without a written applicability analysis.
- [ ] Compare projected actual emissions or discharges against the baseline.
- [ ] State the methodology and the data relied on.
- [ ] Identify any exclusion claimed and why it applies.
- [ ] Signed, dated, retained.
- [ ] Consider asking the agency in writing where the answer is genuinely unclear — a documented inquiry is powerful evidence of good faith.
Part C — Inspections
C1. Standing Protocol
- [ ] One named greeter, with a backup. Everyone else refers.
- [ ] Records organized, in one place, retrievable in minutes.
- [ ] Staff instructed: answer within your own knowledge, factually; say "I don't know" when you do not; do not speculate or characterize compliance.
- [ ] Counsel's number posted.
C2. During
- [ ] Accompany the inspector at all times.
- [ ] Take the same photographs the inspector takes.
- [ ] Take split samples whenever the inspector samples.
- [ ] Keep a contemporaneous log: areas entered, questions asked, documents requested, samples taken, times.
- [ ] Produce what is requested; volunteer nothing.
- [ ] Note staff statements verbatim where possible.
- [ ] Do not refuse entry — permits and statutes provide inspection authority, and refusal is itself a violation. Raise scope objections politely, with counsel.
C3. After
- [ ] Written debrief the same day, while memories are fresh.
- [ ] Fix immediately anything that can be fixed.
- [ ] Correct any inaccurate statement in writing, promptly — an uncorrected inaccuracy becomes an allegation under 18 U.S.C. § 1001.
- [ ] Respond in writing to the inspection report.
- [ ] ⚠️ Never alter a record before or after an inspection — 18 U.S.C. § 1519.
Part D — Notice of Violation
D1. Week One
- [ ] Record the date received and the response deadline.
- [ ] Issue a written preservation hold covering documents, monitoring data, maintenance logs, and email. Suspend routine destruction.
- [ ] Engage counsel; conduct the review at counsel's direction.
- [ ] Verify every allegation independently against the underlying data and against the permit's actual text.
- [ ] Determine whether any violation is continuing. If so, stop it now — penalties accrue daily under provisions including 33 U.S.C. § 1319.
- [ ] Assess criminal exposure before anyone speaks. Knowing violations are felonies; negligent violations of the water statute are misdemeanors.
- [ ] Instruct staff to route all agency contact to one person.
- [ ] Notify insurers per policy terms.
D2. The Response Letter
- [ ] On time, in writing.
- [ ] Accurate as to what is known; explicit about what is still under investigation.
- [ ] No characterizations that may later prove wrong.
- [ ] Describes corrective action already taken, with dates.
- [ ] Proposes a schedule for anything not yet complete.
- [ ] Requests a meeting.
- [ ] Remember: this letter is quoted in every subsequent document.
D3. Penalty Mitigation Package
- [ ] Economic benefit analysis — what was actually saved, computed conservatively. This is the practical floor.
- [ ] Gravity mitigation — absence of harm, absence of exceedance where the violation is administrative, small magnitude, short duration.
- [ ] Compliance history, if favorable.
- [ ] Good faith: pre-notice self-audit, prompt correction with dates, the written compliance program, training records, calendar completion rates.
- [ ] Ability to pay documentation if relevant.
- [ ] Supplemental environmental project proposal, where agency policy permits.
- [ ] A named accountable person and a credible schedule.
D4. Consent Decree Negotiation
Negotiate in this order.
- [ ] 1. The compliance schedule. Achievable milestones with realistic dates. This matters more than the penalty.
- [ ] 2. Stipulated penalties. They operate automatically for years.
- [ ] 3. Force majeure definition — what excuses a missed date.
- [ ] 4. Scope of injunctive work — one unit or the facility, and whether it binds future operations.
- [ ] 5. Termination provisions — what must be demonstrated, for how long. Insist on a clean exit.
- [ ] 6. Reporting burden, which is a real recurring cost.
- [ ] 7. The civil penalty.
- [ ] Confirm whether the resolution binds both state and federal authorities; a resolution with one may not resolve the other.
- [ ] Expect judicial decrees to be lodged publicly with a comment period.
Part E — Self-Disclosure
- [ ] Establish the facts completely before deciding.
- [ ] Confirm the discovery was voluntary — not from an inspection or a required monitoring event.
- [ ] Confirm prompt disclosure, correction, and prevention of recurrence.
- [ ] Understand that gravity-based penalties may be reduced or eliminated but economic benefit generally is not.
- [ ] Weigh: likelihood of independent discovery; whether the violation is ongoing; criminal exposure; sector enforcement attention; any pending transaction.
- [ ] ⚠️ Never disclose without counsel. A disclosure is an admission, and an incomplete one is worse than none.
- [ ] Check the state policy separately; conditions differ.
Part F — Citizen Suit Notice
- [ ] Calendar the sixty-day period from receipt under 33 U.S.C. § 1365 or the parallel provision.
- [ ] Verify every alleged violation against the underlying data.
- [ ] Check notice sufficiency — the standard, the person, the location, and the dates must be identified.
- [ ] Correct anything ongoing immediately and permanently, with documentation.
- [ ] Assess whether the government will commence and diligently prosecute its own action, which bars the citizen suit.
- [ ] Evaluate the ongoing-violation requirement under Gwaltney of Smithfield, Ltd. v. Chesapeake Bay Foundation, Inc., 484 U.S. 49.
- [ ] Remember mootness is narrow — under Friends of the Earth, Inc. v. Laidlaw Environmental Services (TOC), Inc., 528 U.S. 167, voluntary cessation moots nothing unless recurrence is clearly foreclosed.
- [ ] Assess standing under Lujan v. Defenders of Wildlife, 504 U.S. 555.
- [ ] Budget for fee exposure, which is what makes these cases viable for plaintiffs.
- [ ] ⭐ Use the sixty days to become compliant, not to prepare a defense.
Part G — Renewal and Modification
- [ ] Calendar the renewal application deadline — typically 180 days before expiration — with a one-year reminder.
- [ ] File on time. A timely application generally continues the existing permit until renewal issues; a late one can leave the facility operating unpermitted, converting routine operations into violations.
- [ ] Review the outgoing permit for conditions that no longer fit the operation, and propose changes with supporting data.
- [ ] Address any rule vacated or changed since issuance — the condition stands until the permit is modified.
- [ ] Disclose accurately in the renewal; the permit shield depends on it.
- [ ] Request a modification rather than deviating, whenever operations change.
- [ ] Track whether the modification is minor or major — the latter triggers public process.
Part H — Transactions
- [ ] Confirm whether each permit transfers: administratively on notice, with agency approval, or not at all. Do this before signing.
- [ ] Diligence list: every permit and expiration; notices of violation, orders, and consent decrees, which bind successors; five years of monitoring data read for exceedance patterns; the air modification history; waste generator status and manifests; tanks; financial assurance; pending applications; and the compliance calendar itself.
- [ ] Complete all appropriate inquiries before closing to preserve the innocent landowner, contiguous property, and bona fide prospective purchaser defenses to liability under 42 U.S.C. § 9607, with definitions at 42 U.S.C. § 9601 and response procedures at 40 C.F.R. part 300.
- [ ] Understand the continuing obligations the defenses impose after closing.
- [ ] Allocate: representations with survival periods; indemnities carved out of liability caps; escrow or holdback; environmental insurance; price adjustment.
- [ ] Plan for day one — an operating facility that cannot lawfully operate on closing day is a valuation error.
Part I — Actions That Convert Civil Into Criminal
- [ ] Altering, backdating, or destroying a record after a notice, an inspection, or a subpoena — 18 U.S.C. § 1519.
- [ ] Making a false statement to an inspector or in a report — 18 U.S.C. § 1001.
- [ ] Signing a compliance certification without seeing the underlying data.
- [ ] Adjusting data to resolve a discrepancy.
- [ ] Instructing staff to be unavailable or unhelpful.
- [ ] Continuing a known violation after being told of it.
- [ ] Bypassing treatment without the permit's required notice.
- [ ] Disposing of waste off-manifest.
- [ ] Concealing a spill or missing an immediate-notification deadline.
- [ ] Operating after a permit lapses because nobody filed the renewal.
Part J — Quarterly Five-Minute Review
- [ ] Every permit's expiration date confirmed; renewal reminders live.
- [ ] Calendar completion rate for the quarter — any misses, and why.
- [ ] Every calendar entry has a current owner and a backup who still works here.
- [ ] Any project in the quarter that proceeded without a written applicability analysis.
- [ ] Any exceedance reported late.
- [ ] Any inspection this quarter, and whether the debrief and corrections were documented.
- [ ] Training current.
- [ ] Financial assurance and fees current.
Part K — The Annual Self-Audit
Run this once a year, at counsel's direction where privilege matters. It is what converts a penalty negotiation.
K1. Scope and Setup
- [ ] Engagement letter from counsel describing the legal purpose.
- [ ] Scope: all media, all units, all authorizations.
- [ ] Assemble the permit binder, the calendar, and the last twelve months of monitoring and reporting.
- [ ] Identify the personnel who actually perform each obligation, by name.
K2. Test the Calendar Against Reality
- [ ] For each monitoring obligation: was every required sample taken, on time, by the required method?
- [ ] For each report: filed by the deadline, on the correct form, complete?
- [ ] For each immediate-notification event in the period: reported within the permit's window?
- [ ] For each annual certification: signed by a responsible official who reviewed the data?
- [ ] For waste: accumulation dates observed, containers labeled and dated, manifests reconciled, exception reports filed?
- [ ] For tanks and equipment: testing and inspections at the required intervals?
- [ ] For plans: reviewed and certified on schedule?
- [ ] For training: current, with records?
K3. Test the Limits
- [ ] Compare every reported value against the applicable limit and averaging period.
- [ ] Identify exceedances, and whether each was reported.
- [ ] Identify near-misses that indicate a process trending toward a violation.
- [ ] Verify the analytical methods used match those the permit requires.
- [ ] Verify the sampling locations match the permit's description.
K4. Test the Applicability Record
- [ ] List every project, modification, process change, and equipment replacement in the period.
- [ ] For each, is there a written applicability analysis? If not, that is the first finding.
- [ ] For each analysis, is the methodology stated and the data retained?
- [ ] Has any change occurred that would alter waste generator status?
K5. Report and Remediate
- [ ] Written memorandum: scope, method, findings, remediation with dates, open items with owners.
- [ ] Correct what can be corrected immediately.
- [ ] Decide the disclosure question deliberately, with counsel.
- [ ] Update the calendar and the protocol to prevent recurrence.
- [ ] Present findings to management on a stated cadence.
- [ ] Calendar next year's audit.
⭐ Two metrics to report every year: calendar completion rate, and the number of projects that proceeded without a written applicability analysis. Those two numbers predict enforcement exposure better than anything else a facility tracks.
Part L — Deadline Table
| Item | Typical timing | Consequence of missing it |
|---|---|---|
| Permit renewal application | Often 180 days before expiration | Operating without a permit; every discharge a violation |
| Immediate exceedance notification | Hours, per permit | Separate reporting violation |
| Written follow-up report | Commonly 5 days | Separate violation |
| Discharge monitoring report | Monthly or quarterly | Reporting violation; builds the enforcement record |
| Annual compliance certification | Annual | Violation; false certification is criminal |
| Waste accumulation limit | By generator status | Storage without a permit |
| Manifest exception report | Per regulation | Reporting violation |
| Notice of violation response | As stated in the notice | Waiver of the chance to shape the record |
| Citizen suit notice period | 60 days | The window to become compliant or trigger a government action |
| Permit appeal | Short, per program | Conditions become final for the term |
| Consent decree milestones | Per decree | Automatic stipulated penalties |
Part M — Roles and Ownership Sheet
Fill this in and post it. Ambiguity about ownership is the root cause of most administrative violations.
| Obligation | Primary owner | Backup | Frequency | Where recorded | Last verified |
|---|---|---|---|---|---|
| Sampling — [parameter] | |||||
| Discharge monitoring report | |||||
| Immediate exceedance notification | |||||
| Air monitoring and recordkeeping | |||||
| Annual compliance certification signatory | |||||
| Waste container labeling and dating | |||||
| Manifest reconciliation | |||||
| Tank testing | |||||
| Stormwater inspections | |||||
| Plan reviews and certifications | |||||
| Training delivery and records | |||||
| Permit renewal filings | |||||
| Fee and financial assurance payments | |||||
| Inspector greeting and escort | |||||
| Preservation hold authority | |||||
| Agency communications |
- [ ] Every row has a named person, not a department.
- [ ] Every row has a backup who currently works here.
- [ ] Reviewed when anyone in the table leaves or changes roles — the single most common cause of a missed obligation.
Related Documents
- The Permit Is the Product: How Environmental Compliance Actually Works
- Environmental Permitting and Compliance: A Comprehensive Guide to Air, Water, and Waste Authorizations
- The Environmental Permitting and Enforcement Response Toolkit
- Environmental Law: A Comprehensive Guide to CERCLA, RCRA, the Clean Air Act, and the Clean Water Act
- The Environmental Law Toolkit
- The Plume Under the Property: How Contamination Liability Actually Attaches
- Environmental Contamination and Cleanup: A Comprehensive Guide to Liability, Defenses, and Cost Recovery
- Investigating Contamination and Allocating Cleanup Liability: A Practical Checklist
- Phase I Environmental Site Assessment and All Appropriate Inquiries: A Practical Checklist
- Securing a Water Right, a Wetlands Permit, or a Conservation Easement: A Practical Checklist
- Water, Wetlands, and Conservation: A Comprehensive Guide to Rights, Permits, and Easements
- Securing Land Use Entitlements for a Development Project: A Practical Checklist
- Developing a Renewable Energy Project: A Practical Checklist
- Toxic Torts and Environmental Exposure: A Comprehensive Guide to Causation, Experts, and Damages