Opinion · Supreme Court of the United States

Robinson v. United States

Robinson v. United States, 261 U.S. 486 (1923)

Type
Opinion
Court
Supreme Court of the United States
Jurisdiction
Federal
Date
1923-04-09
Topic
general

How later courts describe this case

  • “a provision giving liquidated damages for each day’s delay” is appropriate, “and courts give it effect in accordance with its terms”
  • upholding damage award and stating “[h]ere the fault of the respective parties was not so clearly distributed in time, and it may have been difficult to determine, as a matter of fact, how much of the delay was attributable to each. But the Court of Claims has done so in this case.”
  • “In construction contracts a provision giving liquidated damages for each day’s delay is an appropriate means of inducing due performance, or of giving compensation, in case of failure to perform.”

Citator

UpLaw has not yet analyzed Robinson v. United States. The absence of a flag is not a finding that it is good law.

Cited by
40 opinions

Headnotes

  1. Contracts Law — Liquidated Damages A provision in a construction contract obliging the contractor to pay liquidated damages for each day's delay is a permissible means of inducing due performance and of affording compensation for failure to perform, is not contrary to public policy, and will be enforced according to its terms. 261 U.S. at 488
  2. Contracts Law — Liquidated Damages Where a public building contract provides for liquidated damages for each day's delay not caused by the Government, the fact that the Government caused part of the total delay does not bar recovery of liquidated damages for the days of delay found to be attributable wholly to the contractor's fault; the contractor's intent to pay at the specified rate for some days even while relieved of payment for others is clear from the contract's terms. 261 U.S. at 488-490
  3. Contracts Law — Suretyship Where defects in a building result partly from the character of materials expressly required by the contract and partly from the contractor's own fault in furnishing unseasoned or inferior materials or workmanship, the contractor is not relieved of his obligation under his guaranty to repair the defects merely because, after the contract was made, he pointed out the unsuitability of the specified materials and suggested a substitute. 261 U.S. at 489-491