Opinion · Supreme Court of the United States

Carnegie Steel Co. v. United States

240 U.S. 156

Type
Opinion
Court
Supreme Court of the United States
Jurisdiction
Federal
Date
1916-02-21
Topic
general

How later courts describe this case

  • delay caused by simple inability to perform on time is not excusable

Citator

UpLaw has not yet analyzed Carnegie Steel Co. v. United States. The absence of a flag is not a finding that it is good law.

Cited by
55 opinions

Headnotes

  1. Contracts Law — Impossibility Ability to perform is of the very essence of a contract to deliver goods, and where the thing agreed to be done is possible and lawful it must be done; difficulty or improbability of accomplishing the undertaking does not excuse the obligor, and it must be shown that the thing cannot by any means be effected before performance will be excused. 240 U.S. at 164
  2. Contracts Law — Excuse of Performance — Unforeseen Difficulties A party who by his contract charges himself with an obligation possible to be performed must make it good unless performance is rendered impossible by the act of God, the law, or the other party; unforeseen difficulties, however great, will not excuse him. 240 U.S. at 164
  3. Contracts Law — Liquidated Damages A contractor's delay arising from unforeseen difficulties in a then-new manufacturing art, though shared by the industry and not attributable to any act or neglect of the contractor and not preventable by it, is not a cause of the same kind as the extraneous excepted causes enumerated in a contract excusing delay — such as fires, storms, labor strikes, and action of the United States — because a delay resulting from absence of ability to perform is not a cause extraneous to the contract and independent of the parties' engagements and exertions. 240 U.S. at 164-165