Opinion · Supreme Court of the United States

United States v. Axman

United States v. Axman, 234 U.S. 36 (1914)

Type
Opinion
Court
Supreme Court of the United States
Jurisdiction
Federal
Date
1914-05-25
Topic
general

How later courts describe this case

  • finding the substantial changes to the contract led to a 192% increase in the reprocurement contract price
  • government resold dredging contract on terms it had denied to original contractor

Citator

UpLaw has not yet analyzed United States v. Axman. The absence of a flag is not a finding that it is good law.

Cited by
29 opinions

Headnotes

  1. Contracts Law — Reletting After Default Where a contract is relet following the original contractor's default, the original contractor is liable for the difference in cost only if the contract as relet is the same as the original contract; a relet contract that differs materially from the original cannot serve as the measure of recovery for breach of the original contract. 234 U.S. 36 (1914)
  2. Contracts Law — Material Terms — Place of Performance A specification requiring dredged material to be deposited at a designated location and impounded behind bulkheads is an essential and particular term of the contract, not a mere incidental provision; a contractor's obligation to dredge the channel is not performed unless the material is deposited as specified. 234 U.S. 36 (1914)
  3. Contracts Law — Reletting After Default — Material Variation A change in the location for depositing dredged material under a government contract is an important and material variation, not a minor change, where the original contract fixed the place of deposit as a specific requirement and did not reserve to the Government an absolute right of choice in that regard. 234 U.S. 36 (1914)
  4. Contracts Law — Reletting After Default — Distinguishing Reserved Right of Choice Where the original contract reserves to the Government an absolute right of choice as to the place of depositing spoil, a relet contract allowing deposit in deep water does not materially change the work the first contractor agreed to perform; absent such reserved right, a change in the place of deposit is a material variation. 234 U.S. 36 (1914) (distinguishing United States v. McMullen, 222 U.S. 460)