The Preliminary Notice, Lien Claim, and Bond Claim Deadline Toolkit

40 U.S.C. § 3133

Type
Toolkit
Jurisdiction
National
Date
2025-03-09
Topic
Professional Licensing

This toolkit supplies the working documents for construction payment practice. It opens with a project intake sheet and a three-deadline calendar — the two instruments that prevent most losses in this field. Middle instruments include a licensure verification log, a preliminary notice worksheet, a lien claim contents worksheet, a lien amount computation, and a waiver exchange register. The public-work instruments are a tier analysis, a bond claim notice worksheet, and a claim submission index. Later instruments cover retainage tracking, a notice of completion monitor, a demand to commence, a joint check agreement outline, trust fund segregation, a liquidating agreement outline, and an insolvency response sheet. Each instrument states what it is for and what failure it prevents.

The Preliminary Notice, Lien Claim, and Bond Claim Deadline Toolkit

Professional Licensing > Contractor Licensing, Payment, and Mechanics Liens | Published 9 March 2025 - Updated 24 March 2026 | UpLaw - uplaw.us

Instrument 1: Project intake sheet

Complete at mobilization, before any work is performed. Ten minutes, and it determines whether a remedy exists eight months later.

Field Entry
Project name and street address
County, and legal description obtained from
Property public or private
If public: federal, state, county, or municipal
Record owner, exact legal entity name
Construction lender and address
General contractor, exact legal entity name
Party the claimant contracted with
Claimant's tier position
Bond posted? Obligee, surety, penal sum, bond number
Governing state, and statute version pulled on
Claimant's license number, classification, expiration
Contracting entity's license verified on
Upstream parties' licenses verified on
Contract amount, and retainage percentage
Date of first furnishing
Pay-if-paid or pay-when-paid clause: which, and section
Notice-of-claim provision: period, and section
Statutory waiver form required?

What this prevents. Every failure mode in the field begins with an item on this sheet that nobody filled in.

Instrument 2: The three-deadline calendar

Populate the same day as Instrument 1. Set reminders at the deadline and at two-thirds of the way to it.

Deadline Trigger in this state Date computed Reminder set Completed
Preliminary notice Days from first furnishing
Notice re-service on ownership or lender change
Lien recording Completion / cessation / last furnishing / notice of completion
Service of recorded lien on owner
Foreclosure suit Days from recording
Bond notice (public work) Ninety days from last furnishing, federal
Bond suit (public work) One year from last furnishing, federal
Prompt payment demand
Retainage release
Contract notice-of-claim Days from the event

On the federal bond deadlines. 40 U.S.C. § 3133 sets the ninety-day notice and the one-year suit period, both running from last furnishing rather than from any breach.

On shortened lien periods. A recorded notice of completion or cessation frequently compresses the recording window dramatically. Monitor the county records on any slow-paying project (Instrument 12).

Instrument 3: Licensure verification log

Verification point Entity checked License no. Classification Status Verified on By Screenshot retained
At contracting
At 25% completion
At 50% completion
At 75% completion
At completion
After any entity change

Also record. Any corporate reorganization, administrative dissolution, change in the qualifying individual, or contract signed by an affiliate — each of which can render a competent contractor unlicensed.

What this prevents. Forfeiture of the entire claim, and in several states disgorgement of amounts already paid, on a project where the work was never in question.

Instrument 4: Preliminary notice worksheet

Element Entry
Statutory form prescribed? Cite
Required warning language included verbatim
Claimant name, address, and license number
Party the claimant contracted with
Description of labor, services, materials, or equipment
Estimated total price
Property description and address
Owner: name and address
Lender: name and address
Prime contractor: name and address
Service method permitted by statute
Date of first furnishing
Date served on each recipient
Proof of service retained where

Serve it even when not required. The exemption analysis is occasionally wrong and there is no penalty for an unnecessary notice.

Instrument 5: Lien claim contents worksheet

Element Entry Statutory cite
Claimant identity and address
Party with whom the claimant contracted
Description of labor and materials furnished
Amount unpaid
Property legal description
Record owner
Date of first furnishing
Date of last furnishing
Verification or notarization
Authorized signatory for the entity
County of recording
Date recorded, instrument number
Date served on owner

Instrument 6: Lien amount computation

Overstatement voids the lien entirely in several states. Compute deliberately.

Component Amount Lienable in this state?
Base contract performed to date
Approved change orders
Change orders performed but not approved
Materials delivered and installed
Materials delivered but not installed
Materials fabricated off site
Equipment rental
Delay damages
Interest
Attorney's fees
Retainage
Less payments received
Less amounts covered by waivers delivered
Lien amount claimed

The discipline. Where an item's lienability is uncertain, exclude it from the lien and claim it in the contract count. A lien is not the place to make an aggressive argument.

Instrument 7: Waiver exchange register

Payment app no. Period through Conditional waiver delivered Payment received Funds cleared on Unconditional waiver delivered Retainage covered?

The rule the register enforces. Unconditional waivers are delivered only after funds have cleared. The register makes a violation visible immediately rather than at trial.

For owners. Maintain the mirror image: waivers collected from the prime and from every party that served a preliminary notice, matched to cleared payments.

Instrument 8: Bond claim tier analysis

Question Answer
Does the claimant have a direct contract with the prime?
If not, with whom?
Is that party a subcontractor or a materialman?
Did that party perform a substantial and definable part of the prime contract's work?
Did it maintain a presence on site, employ labor, hold a scope?
Claimant's resulting tier
Notice required?

The governing test. Clifford F. MacEvoy Co. v. United States ex rel. Calvin Tomkins Co. draws the line functionally rather than by label, and J. W. Bateson Co. v. United States ex rel. Board of Trustees applies it further down the chain. The bond itself is required by 40 U.S.C. § 3131.

Instrument 9: Bond claim notice worksheet

Element Entry
Bond number, surety, penal sum, obligee
Prime contractor name and address
Party for whom the claimant performed
Description of labor and materials
Amount claimed, stated with substantial accuracy
Date of last furnishing
Ninetieth day from last furnishing
Date served on prime, and method
Additional recipients required by state statute
One-year suit deadline
District where the contract was performed
Fee entitlement: statutory basis, if any

On fees. F. D. Rich Co. v. United States ex rel. Industrial Lumber Co. applies the American Rule to the federal statute. Many state analogues shift fees; identify the basis before pricing the claim.

On state work. Pull the little Miller Act. Threshold, notice period, limitation period, tier reach, and recipients all differ.

Instrument 10: Prompt payment demand

Element Entry
Statutory basis (federal or state)
Approved application date and amount
Statutory payment period
Date payment became due
Undisputed amount
Disputed amount and stated basis for dispute
Statutory interest rate and accrual date
Fee-shifting provision
Suspension right: notice required, cure period
Date of demand, method of service

Federal construction. 31 U.S.C. § 3903 supplies the agency payment periods and interest penalty; 31 U.S.C. § 3905 supplies the downstream obligations, the interest running to subcontractors, and the certification the prime must make with each request.

The leverage. The suspension right is worth more than the interest on nearly every project. Use it where the statute permits and the notice has been given.

Instrument 11: Retainage tracker

Payment app Gross billed Retainage withheld Cumulative retainage Statutory cap Reduction trigger reached? Early release available? Released on

Also record. Whether the state requires escrow, whether interest accrues to the contractor, whether securities may be substituted, and the deadline for release after completion.

Instrument 12: Notice of completion monitor

For any project where payment is slow.

Item Entry
County recorder search performed on
Notice of completion recorded? Date
Notice of cessation recorded? Date
Shortened recording deadline resulting
New deadline calendared on

Why this exists. In several states an owner can compress a ninety-day lien window to thirty days by recording a document the claimant never receives. The only defense is to look.

Instrument 13: Demand to commence and lien release

For the owner. A demand requiring the claimant to file a foreclosure action within a shortened statutory period or release the lien. Record the statutory basis, the service date and method, and the resulting deadline.

For the claimant. Calendar the demand deadline the day it is received, and treat it as superseding the ordinary foreclosure period.

Release discipline. When a lien is satisfied or expires, record a release. An expired lien left on the record supports a slander of title claim and statutory removal costs.

Instrument 14: Joint check agreement outline

Term Content
Parties: owner or prime, subcontractor, supplier
Project and scope covered
Amounts and payment schedule
Endorsement mechanics
Allocation of each check between payees
Effect on the supplier's lien or bond rights
Whether the supplier's claim is limited to checks it should have received
Termination

The doctrine to address expressly. In many states, a supplier that accepts joint checks is limited in its later claim to the amount of the checks it should have received, whether or not it actually received them. Draft around it or accept it knowingly.

Instrument 15: Trust fund segregation record

Where the state has a construction trust fund statute.

Item Entry
Statutory cite and its scope
Project account established, institution and number
Funds received on this project, by date
Disbursements to project claimants, by date and payee
Disbursements to any other purpose, with justification
Officer responsible for disbursement decisions
Reconciliation performed on

Why the record matters. Diversion is a breach of trust, the officers who directed it may be personally liable, the obligation is frequently non-dischargeable as a defalcation, and the funds may be excluded from the estate — the last because Butner v. United States holds that state law defines property interests and 11 U.S.C. § 541 brings in only what the debtor actually held. Patterson v. Shumate confirms that nonbankruptcy restrictions are honored rather than displaced.

Instrument 16: Liquidating agreement outline

For a subcontractor claim against the federal government, which must travel through the prime.

Term Content
Prime's acknowledgment of liability to the sub
Limitation of that liability to amounts recovered from the government
Prime's agreement to prosecute the claim
Sub's obligation to fund and support the prosecution
Control of settlement
Allocation of recovery and of costs
Certification responsibility

The statutory route. 41 U.S.C. § 7103 requires written submission to the contracting officer with certification above the threshold, and a contracting officer's decision before any appeal. Without a liquidating agreement the sub has no route at all, because it lacks privity.

Instrument 17: Insolvency response sheet

Complete within seventy-two hours of learning that any party in the chain has failed.

Question Answer
Which party failed, and at what tier
Petition filed? Chapter, court, case number, date
State construction trust statute applicable?
Funds traceable to this project?
Officers who directed any diversion
Payments received by the claimant in the ninety days before the petition
Ordinary course evidence assembled
Lien perfected pre-petition?
Lien recording still permitted post-petition?
Relief from stay required for foreclosure?
Bond claim available and unaffected by the stay?
Retainage held by whom, and in what amount
Surety's subrogation position
Obligee's setoff rights

The controlling authorities. 11 U.S.C. § 362 for the stay and its limits; 11 U.S.C. § 547 for preference exposure and the ordinary course defense; Pearlman v. Reliance Insurance Co. for the surety's priority over the estate in retained funds; and United States v. Munsey Trust Co. for the obligee's setoff ahead of the surety.

On statutory change. Armstrong v. United States treats destruction of perfected materialmen's liens as a taking; Connolly v. Pension Benefit Guaranty Corp. permits ordinary prospective economic adjustment among private parties.

How the instruments fit together

Instruments 1 and 2 are completed at mobilization and prevent most of what goes wrong. Instrument 3 runs continuously and is the cheapest insurance in the field. Instruments 4 through 7 carry a private-work claim from notice through waiver discipline. Instruments 8 through 10 carry a public-work claim through the tier analysis, the bond notice, and the payment statutes. Instruments 11 through 14 manage the payment cycle and the owner's counter-tools. Instruments 15 through 17 handle failure.

Every one of them is a document created before it is needed. That is the whole design, and it is the reason the field rewards preparation over advocacy.

Instrument 18: Change order and claim notice register

The most common reason a meritorious extra-work claim fails is not the merits. It is that the contract required written notice within seven or ten days of the event and nobody gave it.

Event date Description Contract notice provision Notice due Notice given, method Direction to proceed received from Priced at Approved / disputed Included in lien claim?

The field problem this addresses. Extra work is directed verbally by a superintendent, performed immediately because the schedule demands it, and priced later. By the time it is priced, the notice period expired weeks earlier. Maintaining this register converts a verbal direction into a documented claim at the moment it arises, which is the only moment it can be done.

On lienability. Unapproved change orders are frequently non-lienable or are the amounts most vulnerable to an overstatement challenge. Track them separately in Instrument 6 and claim them in the contract count rather than in the lien where the state's law is unfavorable.

Instrument 19: Surety claim submission index

Item Included
Bond number and a copy of the bond
Subcontract or purchase order
All change orders, approved and disputed
Payment applications with approval records
Payment history and remaining balance
Daily reports, delivery tickets, and timesheets
Photographs and progress documentation
Correspondence establishing the amount owed
Ninety-day notice and proof of service
Statement of the claimant's tier position
Claimant's licensure documentation
Computation of the amount claimed

How sureties actually behave. A surety investigates rather than pays, and its first questions are whether the claimant is inside the protected tier under 40 U.S.C. § 3133, whether the notice was timely, and whether the amount is genuinely owed. A submission that answers those three questions in its first two pages resolves months faster than one that does not.