Engaging a Design Professional or Pursuing a Design Defect Claim: A Practical Checklist

40 U.S.C. § 1101

Type
Checklist
Jurisdiction
National
Date
2025-08-07
Topic
Construction

This checklist covers engaging a design professional, administering the project, and evaluating a design defect claim from either side. It begins with the owner's selection and agreement review, organized around the clauses that determine what a future claim will be worth, and the designer's parallel review of the terms that create uninsured exposure. It sequences the project administration records that decide disputes years later — the request-for-information log, the submittal actions, the field reports, and the written confirmations of verbal instructions. It provides a claim evaluation sequence that works the four threshold questions first, because repose, certificate-of-merit requirements, the economic loss rule, and the contract's damages limits dispose of more claims than any standard-of-care analysis. It closes with the defense sequence, the insurance notice steps that preserve coverage, and the document retention policy keyed to the repose period rather than the limitations period.

Engaging a Design Professional or Pursuing a Design Defect Claim: A Practical Checklist

Construction > Design Professional Liability and Standard of Care | Published 7 August 2025 - Updated 17 November 2025 | UpLaw - uplaw.us

Which sequence do you need?

☐ Hiring a designer — Parts 1 and 2. ☐ Being hired as a designer — Parts 2 and 3. ☐ Running the project — Part 4. ☐ Evaluating a claim — Part 5. ⚠️ Work its four threshold questions before anything else. ☐ Defending a claim — Part 6. ☐ Insurance and records — Part 7.

Part 1 — Selection (owner)

☐ Select on qualifications, not price. Public projects generally require it; the federal framework is 40 U.S.C. § 1101 through 40 U.S.C. § 1104, and most States have parallel statutes. Price competition on design selects for the least investigation and the thinnest review.

☐ Verify licensure in this State, for the individual in responsible charge and for the firm.

☐ Verify the firm may lawfully practice here — many States restrict design firm ownership to licensed professionals and require registration of the entity.

☐ Verify insurance: professional liability in force, the limit, the retroactive date, and whether the limit is eroded by defense costs.

☐ Ask for the claims history and for the firm's experience with this building type and scale.

☐ Confirm which consultants are the designer's and which you will retain separately. Every boundary you create is a scope gap somebody must own.

☐ Budget the existing-conditions investigation properly. Survey, geotechnical, hazardous materials, and as-built verification. This is the cheapest risk reduction available on any project.

Part 2 — The agreement

The clause that matters most:

☐ Standard of care — "consistent with the professional skill and care ordinarily provided by [architects/engineers] practicing in the same or similar locality under the same or similar circumstances." ☐ ⚠️ Do not accept, and do not propose: "highest standard," "free from errors or defects," "fit for the intended purpose," "shall comply with all applicable laws," or "best efforts." Each converts negligence into warranty, and professional liability policies exclude warranties — meaning an owner who wins on the clause may collect nothing.

Scope — define inclusions and exclusions:

☐ Phases included and excluded ☐ Disciplines included; who retains the others ☐ Existing conditions: investigation scope, and reliance on owner-furnished reports ☐ Geotechnical, environmental, survey, hazardous materials — usually owner-provided ☐ Cost estimating: whether provided, and expressly not guaranteed ☐ Construction observation: frequency, and expressly not exhaustive or continuous inspection ☐ Submittal review: general conformance with design intent only ☐ Site safety: expressly excluded; means, methods, sequences, procedures are the contractor's ☐ Deliverables and whether a model is contractual ☐ Iteration count and additional-services triggers

Risk allocation:

☐ Consequential damages waiver — mutual, listing lost profits, lost use, lost rent, financing costs ☐ Limitation of liability — capped at fee, at insurance limits, or a stated sum; check enforceability in this State ☐ Indemnity limited to the designer's own negligence. ⚠️ Broad "any and all claims" indemnity is contractual liability the policy excludes, and many States restrict it by anti-indemnity statute ☐ Certification language — qualified by knowledge, information, and belief; never unqualified ☐ Insurance requirements — types, limits, retroactive date, duration after completion ☐ Dispute resolution — mediation first, then arbitration or litigation ☐ Document ownership and license, and the effect of termination and nonpayment ☐ Termination and suspension rights and the fee consequences

Part 3 — Designer intake

☐ Confirm you are licensed in the project jurisdiction and that the firm may lawfully practice there. ☐ Confirm the individual in responsible charge and that sealing will follow actual responsible charge. ⚠️ Sealing work you did not supervise is among the most serious licensing violations and is largely uninsurable. ☐ Check your professional liability policy before signing: does it cover this project type, this scale, and any contractual obligations the agreement imposes? ☐ Confirm the retroactive date covers your prior work. ☐ Run the agreement past the carrier or broker if it contains any indemnity, warranty, certification, or safety language. ☐ Confirm the owner's insurance and consultant structure. ☐ Confirm existing-conditions responsibility — if you are relying on owner-furnished information, say so in writing and identify what you relied on. ☐ Price the investigation you think the project needs. If the owner declines it, get the declination in writing. ☐ Mirror your scope into every consultant agreement, and build an interface matrix assigning every boundary between disciplines. ☐ Confirm the fee covers the construction-phase obligations the agreement imposes.

Part 4 — Project administration

Set up on day one:

☐ A request-for-information log: number, date received, date responded, subject, response, and who responded. ⚠️ This log is the entire defense to a delay claim. A firm without it loses those claims. ☐ A submittal log with the review action and date. ☐ A field report template and a schedule of observation visits. ☐ A correspondence protocol — every verbal instruction confirmed in writing the same day, copied to owner and contractor. ☐ A document control system preserving each issuance, dated.

Throughout:

☐ Review submittals for general conformance with design intent only. Do not check dimensions or quantities; say so in the review stamp. But do not approve a submittal that plainly contradicts the design — the disclaimer will not save that. ☐ Respond to requests for information promptly and log every one. ☐ Make field observations at the contracted intervals and write a report for each, including what was observed and what was not. ☐ Report observed safety hazards in writing to the contractor and owner. Do not direct means or methods. The general duty rests on the employer under 29 U.S.C. § 654, with standards at 29 C.F.R. Part 1926. ⚠️ Directing a method, stopping work for safety, or assuming safety duties by contract creates exposure the disclaimer does not cover. ☐ Exercise rejection authority when you observe nonconforming work, and document it. Observing and saying nothing is where negligence findings come from. ☐ Certify payment based on observation, with the standard qualifications. ☐ Evaluate substitutions against the design intent and document the evaluation. ☐ Document the substantial completion determination — it triggers warranties, final payment, and in many States the repose clock.

Accessibility, throughout:

☐ Perform and document a code and accessibility review. The obligations at 42 U.S.C. § 12181 and 42 U.S.C. § 12183, with standards at 28 C.F.R. Part 36, and the multifamily requirements at 42 U.S.C. § 3604(f)(3)(C) with 24 C.F.R. Part 100, are independent of local plan review. ☐ ⚠️ Do not treat plan review approval as a defense. It is not one, and the remedy for a failure is remediation at construction cost.

Part 5 — Evaluating a claim

⚠️ Work these four before spending a dollar on experts. Three of them can end the case.

☐ 1. REPOSE. What is the substantial completion date? What is this State's repose period for improvements to real property? What triggers it here — substantial completion, occupancy, final payment, or last services? Does it differ for designers and contractors? Is it tolled by fraud, concealment, or continuing services? Does it bar contribution claims against parties brought in later? If repose has run, stop.

☐ 2. CERTIFICATE OF MERIT. Is one required? Who may sign — same discipline, licensed, currently practicing? By when? What must it contain — general attestation or specific departures? What happens on failure — dismissal with or without prejudice? Retain the expert before filing. A dismissal for a defective certificate often arrives after limitations has run.

☐ 3. ECONOMIC LOSS RULE. Is the claimant in privity with the designer? If not: does this State recognize a professional services exception, a foreseeable reliance exception, or negligent misrepresentation? Is there personal injury or damage to property other than the project itself? Research this before drafting, applying the framework of East River Steamship Corp. v. Transamerica Delaval Inc..

☐ 4. CONTRACT LIMITS. Consequential damages waiver — does it eliminate the largest number in the claim? Liability cap — at the fee, at insurance limits, or a stated sum, and is it enforceable here? Arbitration clause? Notice conditions?

Only then:

☐ Standard of care — identify each alleged departure specifically, and confirm a qualified expert will support each. ☐ Scope — was the designer retained to do the thing they did badly? This is frequently the strongest defense and the fastest check. ☐ Causation — did the departure cause this harm, or would it have occurred anyway? ☐ Damages, net of betterment — the incremental cost caused by the error, not the cost of the correct work. Compute the betterment credit early; it reframes the number before mediation. ☐ Comparative fault — owner-furnished information, value engineering, contractor deviation, later modification, maintenance failure. ☐ Other defendants — contractor, subcontractors, suppliers, testing agencies, and the effect of joint-and-several rules here.

For a contractor claiming against owner or designer:

☐ The implied warranty of the plans — were these design specifications (warranty attaches) or performance specifications (it does not)? ☐ Was the error patent such that an experienced contractor should have caught it? ☐ ⚠️ Did you give notice in the form and within the time the contract requires? More of these claims fail on notice than on substance. ☐ On federal work, the disputes route is 41 U.S.C. § 7103, with clauses at 48 C.F.R. Part 36 and bond remedies at 40 U.S.C. § 3131 and 40 U.S.C. § 3133.

Part 6 — Defending a claim

In the first week:

☐ Notice the carrier. ⚠️ Claims-made policies make late notice a genuine coverage defense, and most require notice of circumstances likely to become claims, not only of claims. ☐ Issue a litigation hold covering the agreement, all issuances of the documents, the request-for-information and submittal logs, field reports, correspondence, meeting minutes, the code and accessibility review, and cost estimates. ☐ Do not annotate, supplement, or "organize" the project file. The file as it stood is the evidence; anything added later is impeachment. ☐ Locate the insurance declarations pages showing the retroactive date for every relevant year.

In the first responsive pleading:

☐ Assert repose and limitations. ☐ Challenge the certificate of merit — signer qualification, timeliness, specificity. ☐ Move on the economic loss rule where the claimant is not in privity. ☐ Plead the damages waiver and liability cap. ☐ Plead comparative fault and identify other responsible parties.

Building the defense:

☐ Establish the scope first. The designer was not retained to perform the geotechnical investigation, to inspect continuously, or to guarantee cost — whichever applies. ☐ Identify owner-furnished information relied upon, with the transmittal proving what was furnished and when. ☐ Document contractor deviation from the issued documents. ☐ Compute betterment and be ready to present it at mediation. ☐ Retain a standard-of-care expert who will testify to customary practice at the time, with the information then available — not with hindsight. ☐ Check whether repose bars contribution against parties you would otherwise implead; in some States it does, which strands the remaining defendants and changes settlement strategy entirely.

Settlement posture:

☐ Settle early or settle last. The middle position is where a defendant pays for other parties' shares. ☐ Share the betterment and waiver analyses at mediation; they usually move the number more than liability argument does. ☐ Confirm whether joint-and-several liability applies here, which determines whether an empty chair helps or hurts.

Part 7 — Insurance and records

Insurance hygiene (designers):

☐ Maintain continuous claims-made coverage. A single gap leaves every past project unprotected. ☐ Preserve the retroactive date on every carrier change. Losing it forfeits coverage for everything before it. ☐ Report claims AND circumstances promptly, in the form the policy requires. ☐ Confirm the general liability professional services exclusion and the professional policy's coverage grant meet without a gap. ☐ Check the exclusions annually: express warranties, contractual liability beyond common law, cost estimates, means and methods and site safety, pollution and mold, claims by related entities, prior known circumstances. ☐ Buy tail coverage — an extended reporting period — on dissolution, retirement, sale, or non-renewal. It is expensive and it is not optional. ☐ Note that defense costs usually erode the limit, so budget accordingly.

Records to retain:

☐ The agreement and every amendment; all consultant agreements ☐ Owner-furnished information with transmittals ☐ Every dated issuance of the document set ☐ The request-for-information log and the submittal log with actions and dates ☐ All field reports and observation records ☐ Payment certifications ☐ Correspondence, including written confirmations of verbal instructions ☐ Meeting minutes ☐ Code and accessibility review ☐ Cost estimates with their disclaimers ☐ Insurance policies and declarations pages, including expired ones

⚠️ Set the retention period from the statute of repose, not the statute of limitations. A firm purging files on a seven-year schedule in a State with a twelve-year repose period has destroyed its defense to claims it can still receive. Retain declarations pages indefinitely — proving a retroactive date a decade later is otherwise impossible.

The short version

☐ Select on qualifications; verify licensure, entity registration, and the insurance retroactive date. ☐ Hold the ordinary standard-of-care clause. Warranty language moves the obligation outside the insurance. ☐ Define scope by exclusion as much as inclusion; say what you are not doing. ☐ Never sign broad indemnity or an unqualified certification. ☐ Invest in existing-conditions investigation; get any declination in writing. ☐ Log every request for information and response with dates. ☐ Confirm every verbal field instruction in writing the same day. ☐ Observe and report on safety; never direct. ☐ Treat plan review approval as no defense to accessibility obligations. ☐ On any claim: repose, certificate, economic loss, contract limits — in that order, before experts. ☐ Compute betterment before valuing the case. ☐ Notice the carrier immediately; preserve the retroactive date; buy the tail.

⚠️ The single most valuable habit in this entire checklist is the request-for-information log with dates. It costs nothing, it takes a minute a day, and it is the difference between defending a delay claim with a record and defending it with a recollection.

Appendix — Authority quick reference

Where it appears Authority
Economic loss rule East River Steamship Corp. v. Transamerica Delaval Inc.
Qualifications-based selection of design services 40 U.S.C. § 1101; § 1102; § 1103; § 1104
Federal construction contracting and disputes 48 C.F.R. Part 36; 41 U.S.C. § 7103
Payment and performance security on federal work 40 U.S.C. § 3131; 40 U.S.C. § 3133
Site safety allocation 29 U.S.C. § 654; 29 C.F.R. Part 1926
Accessibility — public accommodations and commercial facilities 42 U.S.C. § 12181; 42 U.S.C. § 12183; 28 C.F.R. Part 36
Accessibility — covered multifamily housing 42 U.S.C. § 3604; 24 C.F.R. Part 100
Architectural works, ownership, and the license 17 U.S.C. § 101; § 102; § 106; § 120; § 201; § 501
Work-for-hire and originality Community for Creative Non-Violence v. Reid; Feist Publications v. Rural Telephone Service Co.

Everything else in this checklist is state law — the standard of care's formulation, the economic loss variations, certificate-of-merit requirements, repose periods and their triggers, anti-indemnity statutes, the enforceability of liability caps, licensure and practice-entity rules, and design professional lien rights. Verify each in the governing jurisdiction before relying on any general statement here.

Related materials: the article explains why the doctrines are shaped this way, the comprehensive guide develops each in detail, and the toolkit supplies the contract language, the logs, the field report form, the certificate framework, and the betterment worksheet referenced above.

Six failures, and the step that catches each

The warranty clause nobody priced. An owner inserts "free from defects," the designer signs, and years later the owner wins a clause the designer's insurer will not pay. Caught by: Part 2's standard-of-care item, and by Part 3's instruction to run any warranty language past the carrier before signing.

The investigation nobody paid for. A renovation designed from record drawings that do not match the building. Caught by: Part 1's investigation budget and Part 3's written declination — the declination is what converts an owner's cost decision into an owner's risk.

The undated response record. A contractor's delay analysis attributes six weeks to slow requests-for-information responses, and the designer has email folders instead of a log. Caught by: Part 4's day-one log setup.

The verbal instruction. A change directed on site, never confirmed, later disputed by three participants with three recollections. Caught by: Part 4's same-day written confirmation protocol.

The purged file. A firm on a seven-year retention schedule receives a claim in year nine in a twelve-year repose State. Caught by: Part 7's rule to set retention from repose, not limitations.

The case filed without an expert. A meritorious claim dismissed on a defective certificate of merit, after the limitations period has run. Caught by: Part 5's second threshold question, worked before filing rather than after.

Every one of these is decided by a routine rather than by expertise, which is why they belong on a checklist. And five of the six are decided before anyone knows there will be a dispute — which is the recurring lesson of this entire field.