This toolkit supplies the instruments for handling contracts in a bankruptcy case from either side. The first group builds the record: the contract inventory, the executoriness worksheet, and the mark-to-market analysis that identifies assets and burdens. The second group covers assumption: the cure computation sheet and the adequate assurance package. The third group covers rejection and assignment: the motion outlines, the applicable law exception memorandum, and the rejection damages calculator. The fourth group equips the counterparty: the cure objection, the adequate assurance demand, and the claims to file. The final instruments cover the labor and retiree processes, the plan schedules, purchaser diligence, and the designation rights structure used in multi-location cases.
The Executoriness Analysis, Cure Computation, and Adequate Assurance Toolkit
Bankruptcy > Executory Contracts, Unexpired Leases, and Assumption | Published 25 January 2025 - Updated 13 March 2026 | UpLaw - uplaw.us
Instrument 1: the contract inventory template
Columns. Contract identifier; counterparty; type; effective date; term and renewals; annual cost; market comparison; defaults and amounts; credit support held by the counterparty; assignment restrictions; criticality to the reorganized business; executoriness conclusion.
Sources. The accounts payable system, the legal department's files, and each operating unit — each of which is incomplete, so all three are required.
Categories frequently missed. Purchase orders with remaining deliveries; software subscriptions; equipment leases; service and maintenance agreements; licenses embedded within larger arrangements; and side letters modifying master agreements.
Notice addresses, captured from the contracts rather than from the payables system, since service at the wrong address invalidates the process.
Instrument 2: the executoriness worksheet
Purpose. To answer the threshold question that determines whether 11 U.S.C. § 365 applies at all.
Column one — the debtor's remaining obligations, listed individually.
Column two — the counterparty's remaining obligations, listed individually.
Column three — materiality, stating for each whether failure to perform would constitute a material breach excusing the other party's performance.
Conclusion, with the contested categories flagged: negative covenants as the sole remaining obligation; contingent confidentiality and indemnity obligations; warranties after delivery and payment; unexercised options; and settlement agreements with continuing obligations.
Consequence noted. A non-executory contract cannot be assumed, rejected, or assigned over objection, and the counterparty's state law anti-assignment protections remain fully effective.
Equipment lease sub-analysis. True lease or disguised financing under state law as Butner v. United States directs, since a financing is a secured claim under 11 U.S.C. § 506 with adequate protection under 11 U.S.C. § 361.
Instrument 3: the cure computation sheet
Line items. Base amounts due; accrued charges by category; taxes, insurance, and reimbursable costs; default interest if the contract and applicable law permit; attorney's fees where the agreement provides.
Non-monetary defaults listed with a determination whether cure is required, noting that ipso facto defaults are excused and that certain non-monetary defaults impossible to cure are excused in real property leases.
Historical defaults, with any waiver or estoppel analysis under state law.
Reserves for amounts not yet ascertainable — percentage rent, year-end reconciliations, and pending disputes.
Fee support, noting that under Travelers Casualty & Surety Co. of America v. Pacific Gas & Electric Co. contractual fees are not disallowed merely because incurred litigating bankruptcy issues.
Aggregate, since the total frequently determines what the estate can afford to assume.
Instrument 4: the adequate assurance package
Financial section. Projections; the exit facility and its conditions; the pro forma capital structure; debt service coverage; and liquidity.
Operational section. Personnel, systems, licenses, and supplier relationships demonstrating that the performing entity can actually perform.
For an assignee. Balance sheet; operating history in the relevant business; guarantors; and existing credit facilities.
Credit support offered. Guarantee, letter of credit, deposit, or reserve, which is frequently how a marginal showing becomes an adequate one.
Shopping center supplement, meeting the enumerated requirements: source of rent; financial condition and operating performance comparable to the debtor when it became the tenant; similar percentage rent; compliance with radius, location, use, and exclusivity provisions; and no disruption of tenant mix or balance.
Timing note. Adequate assurance is assessed as of assumption or assignment, so a counterparty concerned about later deterioration must negotiate ongoing protections rather than rely on the finding.
Instrument 5: the assumption motion outline
Identification of the contract, counterparty, and notice address from the contract.
The three conditions addressed separately: cure or adequate assurance of prompt cure; compensation for pecuniary loss or adequate assurance of prompt compensation; and adequate assurance of future performance.
The cure amount from Instrument 3, with the payment timing proposed.
The adequate assurance showing from Instrument 4.
The business justification for assumption.
The consequence acknowledged, since an assumed contract becomes an administrative obligation with post-assumption breaches producing claims under 11 U.S.C. § 503 with priority under 11 U.S.C. § 507.
The proposed order, specifying the effective date, the cure amount and timing, reservations for later reconciliation, and any release.
Instrument 6: the rejection motion outline
Identification of the contract and counterparty.
The business judgment, stating the reasonable business basis — the contract is above market, the location is closing, the service is no longer needed, or the obligation exceeds the benefit.
The proposed effective date, noting that courts have permitted the motion date, the order date, or the surrender date, and that the choice affects the administrative claim for the interim period.
What rejection accomplishes, stated accurately: the estate is relieved of the obligation to perform, and the counterparty's claim becomes a prepetition unsecured claim under 11 U.S.C. § 502.
What it does not accomplish, noted for the client: under Mission Product Holdings, Inc. v. Tempnology, LLC, rejection is a breach rather than a rescission, so the counterparty retains whatever rights survive a breach.
Surrender obligations for leased premises, with the condition, timing, and abandonment of property addressed.
Instrument 7: the assignment analysis
Step one. Confirm the contract will be assumed, since assignment requires it.
Step two. Assemble adequate assurance of future performance by the assignee from Instrument 4.
Step three. Identify the restrictions and invoke the overrides — anti-assignment clauses including consent requirements, prohibitions, and provisions terminating or modifying on assignment; and ipso facto clauses conditioning the contract on insolvency, financial condition, the case, or a trustee's appointment.
Step four. Apply the applicable law exception, which bars assumption or assignment where applicable law excuses the counterparty from accepting performance from or rendering performance to an entity other than the debtor and the counterparty does not consent.
Step five. Determine the circuit's rule on the hypothetical versus actual test, since where the debtor wishes to assume but not assign, some courts bar assumption if assignment would hypothetically be barred.
Step six. Confirm the estate's release from liability for breaches occurring after the assignment.
Instrument 8: the applicable law exception memorandum
The contract type and the nonbankruptcy law governing it under Butner v. United States.
The rule outside bankruptcy on whether the counterparty may be compelled to accept performance from or render performance to a substitute party.
The categories where the exception plainly applies: personal service contracts.
The categories where courts divide: non-exclusive intellectual property licenses, where the general rule outside bankruptcy is non-assignability without consent.
The circuit's position on the hypothetical versus actual test, with the practical consequence stated: whether the debtor may keep a license it needs to reorganize.
The consent alternative, since the exception yields to the counterparty's consent, which makes negotiation the reliable route where the law is unfavorable.
Instrument 9: the lease deadline calendar
Order for relief date and the one hundred twenty day deadline for nonresidential real property leases.
The ninety day extension for cause, with the motion deadline calendared well before the initial period expires.
The outside limit, beyond which each lessor's written consent is required, with a plan for that negotiation.
Confirmation date, since the deadline runs to the earlier of the period or confirmation.
Performance obligations arising after the order for relief, budgeted, since the decision period is not free.
Liquidation case deadlines, sixty days after the order for relief for all contracts, subject to extension for cause.
Motions to compel an earlier decision, anticipated in a reorganization case where the counterparty is prejudiced by delay.
Instrument 10: the rejection damages calculator
Real property lease. Rent reserved for the greater of one year or fifteen percent, not exceeding three years, of the remaining term, plus unpaid rent already due. Note the scope dispute over whether the cap reaches unamortized tenant improvement allowances and brokerage commissions.
Mitigation, applied under state law in computing the underlying damages before the cap.
Employment contract. Compensation for one year following the earlier of the filing or the termination of performance, plus unpaid compensation already due.
Setoff, where mutual obligations exist.
Security deposit, applied against the claim with the residual returned to the estate.
Third-party credit support, which is outside the caps and outside the estate.
Administrative component, for value conferred between filing and rejection under 11 U.S.C. § 503 with priority under 11 U.S.C. § 507.
Claim timing, deemed to arise immediately before the filing, making it a prepetition general unsecured claim under 11 U.S.C. § 502.
Instrument 11: the counterparty objection package
Executoriness challenge, where the contract is not executory and therefore outside the provision.
Cure objection, filed by the deadline and stating every component with support, since a counterparty that does not object to a scheduled amount is generally bound.
Adequate assurance demand, specifying what is required and attaching a proposed guarantee or letter of credit, since a specific demand gives the court something to order.
Applicable law exception assertion, where nonbankruptcy law makes the identity of the performing party material.
Performance demand during the decision period for a nonresidential real property lease.
For a licensee, the retained rights assertion, under the statutory election for patents, copyrights, and trade secrets, or under the breach analysis of Mission Product Holdings, Inc. v. Tempnology, LLC for trademarks.
Claims filed — administrative under 11 U.S.C. § 503 and rejection damages under 11 U.S.C. § 502.
Instrument 12: the labor and retiree process checklist
Proposal to the authorized representative under 11 U.S.C. § 1113, based on the most complete and reliable information available, providing for necessary modifications assuring that all creditors, the debtor, and all affected parties are treated fairly and equitably.
Information provided to the representative, subject to protection of confidential material.
Conferences at reasonable times, in good faith, documented.
Findings sought: the proposal was made; the representative refused without good cause; the balance of the equities clearly favors rejection.
Interim relief, only on the separate showing that it is essential to the continuation of the business or to avoid irreparable damage.
The superseded standard noted, since National Labor Relations Board v. Bildisco & Bildisco permitted unilateral modification and the statutory process does not.
Retiree process under 11 U.S.C. § 1114, running in parallel.
Confirmation condition under 11 U.S.C. § 1129, calendared, since an unresolved labor issue blocks confirmation.
Priority claims under 11 U.S.C. § 507, protected from being skipped in a final distribution by Czyzewski v. Jevic Holding Corp..
Instrument 13: the plan schedule builder
Schedule of assumed contracts, with counterparty, contract description, and cure amount.
Schedule of rejected contracts, with counterparty and rejection effective date.
Contracts previously assumed or rejected, listed separately so the plan's treatment provision under 11 U.S.C. § 1123 covers everything.
Reconciliation to the claims register, so that rejection damages and administrative claims are anticipated.
Feasibility input, aggregating the assumed obligations, which are administrative in character and must be serviceable by the reorganized entity.
Objection deadlines and resolution status by contract.
Notice, served at the contract notice address, with proof retained.
Instrument 14: the designation rights term sheet
What is transferred. The right to designate which leases will be assumed and assigned, rather than the leases themselves.
Mechanics. Each designation triggers assumption and assignment under 11 U.S.C. § 365, with cure paid and adequate assurance provided as to the ultimate assignee.
Carrying cost allocation, since the estate must continue performing obligations arising after the order for relief while leases are held open.
Deadline discipline, since the designation period cannot outrun the statutory period as extended, and any further extension requires each lessor's written consent.
Landlord objections anticipated: the identity of the ultimate assignee, the adequate assurance showing, and the burden of extended uncertainty.
Cure timing, since landlords will resist deferral until designation and will seek current payment or escrow.
Estate release on each assignment.
The failure case, specifying what happens to leases not designated, which will be deemed rejected and must be surrendered, with the surrender obligations assigned to someone.
Instrument 15: the purchaser diligence list
Executoriness for each contract to be assumed.
Assignability against the applicable law exception, the failure point for licenses, personal service arrangements, franchises, and partnership interests.
Cure cost and its allocation in the purchase agreement.
Adequate assurance exposure, with the likely objectors identified.
Rejected contracts, not assumed to be resolved, since under Mission Product Holdings, Inc. v. Tempnology, LLC a rejected license may leave the licensee's rights intact.
Free and clear protections from the sale order under 11 U.S.C. § 363 rather than from rejection orders.
Transfer taxes under Florida Department of Revenue v. Piccadilly Cafeterias, Inc., which limits the stamp tax exemption to transfers under a confirmed plan.
Credit bid ceiling under RadLAX Gateway Hotel, LLC v. Amalgamated Bank, understood before investing in diligence.
Successor liability, addressed through the sale order's free and clear language and the plan's injunction under 11 U.S.C. § 1141, since contract assumptions do not determine what claims follow the assets.
Instrument 16: the contract-type screen
Supply agreements. Executory where deliveries and payments remain. Cure covers unpaid invoices. Rejection damages are measured by cover cost. Requirements contracts raise the question whether the estate's reduced volume is itself a breach.
Equipment leases. True lease or disguised financing under state law; a financing is a secured claim under 11 U.S.C. § 506 with adequate protection under 11 U.S.C. § 361 rather than a contract subject to 11 U.S.C. § 365.
Software and technology agreements. Executory where support, maintenance, and license obligations remain; the applicable law exception is the central assignment question; source code escrow arrangements raise their own executoriness issue.
Franchise agreements. Subject to state relationship statutes and to the applicable law exception where the franchisor's consent rights rest on nonbankruptcy law.
Insurance policies. Frequently not executory where premiums are fully paid, making the policy estate property under the general provisions rather than a contract subject to assumption.
Joint venture and partnership agreements. Subject to the applicable law exception where partnership law makes the identity of the partner material.
Settlement agreements. Executoriness turns on what remains, with the recurring question whether an exchanged release constituted the performance.
Purchase orders. Individually small and collectively enormous in a manufacturing case, handled through omnibus procedures with schedules whose accuracy is the principal practical risk.
Utility contracts, which interact with the separate provision governing utility service and adequate assurance of payment.
Instrument 17: the debtor-as-lessor analysis
Rejection does not evict. A lessee under a rejected lease may elect to remain in possession for the balance of the term including enforceable renewals, offsetting post-rejection nonperformance damages against rent but having no other claim for them.
Assumption requires curing the landlord's defaults — deferred maintenance, unfunded tenant improvement allowances, and service failures — which is frequently overlooked because parties think of cure as a tenant obligation.
Clearing the property requires a sale under 11 U.S.C. § 363 rather than rejection, and whether a leasehold can be stripped depends on state law under Butner v. United States.
Rents as cash collateral where the lender holds an assignment of rents, usable only with consent or authorization after adequate protection under 11 U.S.C. § 361 and 11 U.S.C. § 363.
Assignment of the lessor's position, which requires adequate assurance running to the tenants.
Real property purchasers in possession may remain and take title on completing payments; those not in possession have a lien for amounts paid.
The organizing principle, applied throughout: the estate cannot obtain by rejection anything the debtor could not have obtained by breach, which is what Mission Product Holdings, Inc. v. Tempnology, LLC holds.
Instrument 18: the procedural order template
Omnibus procedures. A schedule for serving cure notices; a deadline for objections; a provision that unopposed cure amounts become binding; and a form of notice.
Service. At the notice address stated in each contract rather than at the accounts payable address, with proof retained.
Schedules. Contract identifier, counterparty, description, and cure amount, verified before service, since accuracy is the principal risk in omnibus practice.
Reservations. For amounts not yet ascertainable, with a mechanism for later reconciliation.
Effective dates, specified in the order for both assumption and rejection.
Estate release on assignment, stated expressly.
Appeal note. An order resolving a contested assumption or rejection is generally appealable when entered rather than at the end of the case, consistent with the finality approach to discrete procedural units illustrated by Ritzen Group, Inc. v. Jackson Masonry, LLC.
Equitable authority limit, noted for anyone proposing a creative structure: Law v. Siegel forecloses using 11 U.S.C. § 105 to override the specific requirements of the provision.
Related Documents
- The Contract Nobody Has Finished Performing Is the One the Debtor Gets to Choose About: How Executory Contracts Actually Work
- Executory Contracts and Leases: A Comprehensive Guide to Assumption, Rejection, Assignment, Cure, and Special Contract Types
- Assuming, Rejecting, or Assigning a Contract in Bankruptcy: A Practical Checklist
- Everything Stops the Moment the Petition Is Filed, Including Things You Did Not Know Were Yours: How the Automatic Stay Actually Works
- The Automatic Stay: A Comprehensive Guide to Scope, Exceptions, Relief From Stay, Adequate Protection, and Damages for Violation
- Obtaining or Opposing Relief From the Automatic Stay: A Practical Checklist
- The Stay Scope Analysis, Adequate Protection Proof, and Stay Violation Damages Toolkit
- One Dissenting Class and the Whole Plan Has to Be Fair: How Chapter 11 Confirmation Actually Works
- Chapter 11 Confirmation: A Comprehensive Guide to Disclosure, Classification, Voting, Cramdown, Feasibility, and Releases
- Confirming or Objecting to a Chapter 11 Plan: A Practical Checklist
- The Classification Chart, Best Interests Test, and Cramdown Valuation Toolkit
- The Company Is Sold in Forty-Five Days and the Plan Comes Later: How Bankruptcy Sales Actually Work
- Bankruptcy Sales: A Comprehensive Guide to Section 363, Free and Clear Findings, Bidding Procedures, Credit Bidding, and Good Faith Protection
- Running or Bidding in a Bankruptcy Sale: A Practical Checklist
- The Bidding Procedures Motion, Free and Clear Analysis, and Sale Objection Toolkit
- The Company Failed Somewhere Else and Its Assets Are Here: How Cross-Border Insolvency Actually Works
- Cross-Border Insolvency: A Comprehensive Guide to Chapter 15 Recognition, Center of Main Interests, Relief, Cooperation, and Comity
- Seeking or Opposing Recognition of a Foreign Proceeding: A Practical Checklist
- The Center of Main Interests Analysis, Recognition Petition, and Discovery Relief Toolkit
- The Pallet That Never Arrived: How Freight and Cargo Claim Law Actually Works
- Freight, Cargo Claims, and Logistics: A Comprehensive Guide to Carmack, Bills of Lading, Broker Liability, and Warehouse Law
- Anatomy of a Lawful Layoff: WARN Notice, Disparate Impact, and the OWBPA Release
- Hell or High Water: Why an Equipment Lease Survives Equipment That Does Not Work
- The Airwaves Belong to the Public and the License Is a Lease: How Broadcast Regulation Actually Works
- The Lease That Outlives the Business: What a Small Business Signs and Cannot Undo
- The Price of Going Home: How Bail and Pretrial Release Actually Work
- The Release You Signed: How Settlement Agreements Fail and What Makes Them Hold
- Arresting a Vessel or Obtaining Its Release: A Practical Checklist
- Documenting a Farm Lease, Loan, or Neighbor Dispute: A Practical Checklist
- Locating a Detained Person and Seeking Release on Bond: A Practical Checklist
- Negotiating a Mineral Lease and Protecting the Surface: A Practical Checklist
- Negotiating and Exiting a Commercial Lease: A Practical Checklist
- Negotiating, Booking, or Terminating an Equipment Lease: A Practical Checklist