This checklist runs a contract portfolio through a bankruptcy case from inventory to plan schedules, and separately equips a counterparty to protect its position. The inventory track builds the portfolio and characterizes each agreement, since the entire framework applies only to executory contracts. The economics track identifies which contracts are assets and which are burdens and computes the cure exposure that frequently determines the outcome. The deadline track covers the timing rules and the hard limit on nonresidential real property leases. The assumption and assignment tracks cover the conditions each requires and the exception that defeats assignment. The counterparty track covers cure objections, adequate assurance demands, and the claims to file. The final tracks cover labor and retiree processes, plan schedules, and purchaser diligence.
Assuming, Rejecting, or Assigning a Contract in Bankruptcy: A Practical Checklist
Bankruptcy > Executory Contracts, Unexpired Leases, and Assumption | Published 1 February 2025 - Updated 24 March 2026 | UpLaw - uplaw.us
Track one: build the inventory
Collect from every source — the accounts payable system, the legal department's files, and each operating unit — since every source is incomplete.
Include what the business does not call a contract: purchase orders with remaining deliveries, subscriptions, equipment leases, service agreements, and licenses embedded within larger arrangements.
Record for each: counterparty, term, renewal rights, annual cost, defaults, and any credit support the counterparty holds.
Flag the contracts the reorganized business cannot operate without.
Flag the contracts with assignment restrictions, since those are where the applicable law exception will be argued.
Track two: characterize each agreement
Apply the executoriness test: obligations remaining on both sides so far unperformed that the failure of either to complete performance would constitute a material breach excusing the other's performance.
List the remaining obligations of each party rather than concluding, since the analysis is contested at the margins.
Treat as contested covenants not to compete where only a negative obligation remains; confidentiality and indemnity obligations; warranties after delivery and payment; unexercised options; and settlement agreements with continuing obligations.
Understand the consequence. A non-executory contract cannot be assumed, rejected, or assigned over objection under 11 U.S.C. § 365, and the counterparty's state law anti-assignment protections remain fully effective.
For equipment arrangements, determine true lease or disguised financing under state law as Butner v. United States directs, since a financing is a secured claim analyzed under 11 U.S.C. § 506 with adequate protection under 11 U.S.C. § 361 rather than a contract.
Track three: economics and cure
Mark each contract to market, identifying below-market contracts as assets whose value may be captured by assignment and above-market contracts as rejection candidates.
Compute the cure amount for each defaulted contract the business needs: base amounts, accrued charges, default interest if the contract and applicable law permit, and attorney's fees where the agreement provides.
Aggregate the cure exposure, since liquidity frequently determines what can be assumed regardless of strategic value.
Identify non-monetary defaults and whether they must be cured, noting that ipso facto defaults are excused and that certain non-monetary defaults impossible to cure are excused in real property leases.
Reserve for unascertainable amounts such as percentage rent and year-end reconciliations.
Confirm fee recoverability in light of Travelers Casualty & Surety Co. of America v. Pacific Gas & Electric Co., under which contractual fees are not disallowed merely because incurred litigating bankruptcy issues.
Track four: deadlines
Liquidation cases. Deemed rejected if not assumed within sixty days after the order for relief, subject to extension for cause.
Reorganization cases. Any time before confirmation, subject to a motion to compel an earlier decision.
Nonresidential real property leases. One hundred twenty days after the order for relief or confirmation, whichever is earlier; extendable ninety days for cause; any further extension requires the lessor's written consent.
Calendar the outside limit and plan for the consent negotiation, since it occurs at the moment of maximum pressure.
Budget the performance obligation, since the debtor must perform obligations arising after the order for relief under a nonresidential real property lease until assumption or rejection.
Track five: assumption
Satisfy the three conditions: cure or adequate assurance of prompt cure; compensation for pecuniary loss or adequate assurance of prompt compensation; and adequate assurance of future performance.
Assemble the adequate assurance showing. Financial evidence — projections, exit facility, pro forma capital structure, debt service coverage — and operational evidence that the performing entity can actually perform.
For a shopping center lease, meet the enumerated requirements: source of rent; financial condition and operating performance comparable to the debtor when it became the tenant; similar percentage rent; compliance with radius, location, use, and exclusivity provisions; and no disruption of tenant mix.
Take the contract whole, since assumption is all or nothing and favorable provisions cannot be selected.
Understand the consequence, since an assumed contract becomes an administrative obligation with a post-assumption breach producing a claim under 11 U.S.C. § 503 entitled to priority under 11 U.S.C. § 507.
Track six: rejection
Establish the business judgment, which is a deferential standard requiring a reasonable business basis.
Specify the effective date, since courts have permitted the motion date, the order date, or the surrender date, and the choice affects the administrative claim for the interim period.
Understand what rejection does. Under Mission Product Holdings, Inc. v. Tempnology, LLC, rejection is a breach rather than a rescission, so the counterparty retains whatever rights survive a breach under applicable law.
Understand what it does not do. It does not clear title. Extinguishing a counterparty's rights requires a sale free and clear under 11 U.S.C. § 363, a plan provision, or a negotiated resolution.
Anticipate the claim, which arises immediately before the filing as a prepetition general unsecured claim under 11 U.S.C. § 502, subject to the applicable cap.
Anticipate the administrative claim for value conferred between filing and rejection.
Track seven: assignment
Confirm assumption first, since assignment requires it.
Provide adequate assurance of future performance by the assignee, whether or not there has been a default.
Invoke the overrides. Anti-assignment clauses — including consent requirements, prohibitions, and provisions terminating or modifying on assignment — are unenforceable, as are ipso facto clauses conditioning the contract on insolvency, financial condition, the case, or a trustee's appointment.
Test the applicable law exception, which bars assumption or assignment where applicable law excuses the counterparty from accepting performance from or rendering performance to an entity other than the debtor and the counterparty does not consent.
Determine the circuit's rule on the hypothetical versus actual test, since where the debtor wishes to assume but not assign, some courts bar assumption if assignment would hypothetically be barred.
Confirm the estate's release, since the estate is relieved of liability for breaches occurring after the assignment.
Track eight: the counterparty's protections
Test executoriness first, since a non-executory contract is outside the provision.
Object to the cure amount promptly and completely, since a counterparty that does not object to a scheduled amount is generally bound.
Demand adequate assurance in writing, specifying what is required and attaching a proposed guarantee or letter of credit, since a specific demand gives the court something to order.
For a nonresidential landlord, calendar the deadline and price consent to any further extension.
Insist on performance during the decision period.
For a licensor, do not rely on rejection to terminate, since Mission Product Holdings, Inc. v. Tempnology, LLC forecloses that.
For a licensee, assert the retained rights, under the statutory election where the license covers patents, copyrights, or trade secrets, or under the breach analysis for trademarks.
Assert the applicable law exception where nonbankruptcy law makes the identity of the performing party material.
Preserve credit support, since draws on letters of credit and guarantees are outside the caps and outside the estate.
File both claims — the administrative claim under 11 U.S.C. § 503 and the rejection damages claim under 11 U.S.C. § 502 with the cap computed.
Track nine: rejection damages
Compute the real property cap: rent reserved for the greater of one year or fifteen percent, not exceeding three years, of the remaining term, plus unpaid rent already due.
Address the scope dispute over whether the cap reaches only rent or extends to unamortized tenant improvement allowances and brokerage commissions.
Apply state law mitigation in computing the underlying damages before the cap.
Compute the employment cap: compensation for one year following the earlier of the filing or the termination of performance, plus unpaid compensation already due.
Assert setoff where mutual obligations exist.
Apply security deposits and return any residual to the estate.
Draw on third-party credit support, which is outside the caps and outside the estate.
Track ten: labor and retiree obligations
Start early, since the processes take months and are confirmation conditions under 11 U.S.C. § 1129.
For a collective bargaining agreement, follow 11 U.S.C. § 1113: make a proposal based on the most complete and reliable information available, providing for necessary modifications assuring that all creditors, the debtor, and all affected parties are treated fairly and equitably; provide the relevant information; meet at reasonable times and confer in good faith.
Obtain the required findings: the proposal was made, the representative refused without good cause, and the balance of the equities clearly favors rejection.
Recognize that the ordinary standard does not apply, since National Labor Relations Board v. Bildisco & Bildisco was superseded by the statutory process and unilateral modification is no longer available.
Seek interim relief only on the separate showing that it is essential to the continuation of the business or to avoid irreparable damage.
For retiree benefits, follow 11 U.S.C. § 1114, which imposes a parallel process.
Track priority wage and benefit claims under 11 U.S.C. § 507, protected from being skipped in a final distribution by Czyzewski v. Jevic Holding Corp..
Track eleven: plan and sale integration
Build the plan schedules required by 11 U.S.C. § 1123, listing assumed contracts with cure amounts and rejected contracts with dates.
Reconcile against the claims register, so rejection damages and administrative claims are anticipated.
Confirm feasibility, since assumed contracts are administrative obligations that the reorganized entity must service.
For a sale, fix cure amounts and allocate them in the purchase agreement, and establish adequate assurance for the purchaser.
Address the designation period and who funds performance while contracts are held open.
Rely on the sale order for free and clear protections, not on rejection, since rejection does not clear title.
Address transfer taxes, since Florida Department of Revenue v. Piccadilly Cafeterias, Inc. limits the stamp tax exemption to transfers under a confirmed plan.
Confirm the credit bid position under RadLAX Gateway Hotel, LLC v. Amalgamated Bank, since it affects who the purchaser will be and whose adequate assurance counterparties must evaluate.
Do not rely on equitable authority to bridge a gap, since Law v. Siegel forecloses using 11 U.S.C. § 105 to override the specific requirements of the provision.
Track twelve: procedure
Draft the motion identifying the contract, the counterparty, the cure amount, and any proposed assignee.
Establish omnibus procedures in a large case: a schedule for serving cure notices, a deadline for objections, and a provision that unopposed cure amounts become binding.
Verify the schedules, since in omnibus practice the accuracy of the contract and cure schedules is the principal practical risk for both sides.
Prepare for the hearing on contested cure amounts and adequate assurance disputes.
Draft the order to specify the effective date, the cure amount and payment timing, any reservation for later reconciliation, and the estate's release on assignment.
Calendar the appeal, since an order resolving a contested assumption or rejection is generally appealable when entered rather than at the end of the case, consistent with the approach to discrete procedural units illustrated by Ritzen Group, Inc. v. Jackson Masonry, LLC.
Confirm service on the counterparty at the notice address in the contract, not merely at the address in the accounts payable system.
Track thirteen: contract-type screens
Supply agreements. Executory where deliveries and payments remain; cure covers unpaid invoices; rejection damages measured by cover cost; requirements contracts raise the question whether reduced volume is itself a breach.
Equipment leases. True lease or disguised financing, determined under state law.
Software and technology agreements. The applicable law exception is the central assignment question, and source code escrow arrangements raise their own executoriness issue.
Franchise agreements. Subject to state relationship statutes and to the applicable law exception where the franchisor's consent rights rest on nonbankruptcy law.
Insurance policies. Frequently not executory where premiums are fully paid, making the policy estate property rather than a contract subject to assumption.
Joint venture and partnership agreements. Subject to the applicable law exception where partnership law makes the identity of the partner material.
Settlement agreements. Executoriness turns on what remains, with the recurring question whether an exchanged release was the performance.
Utility contracts, which interact with the separate provision on utility service and adequate assurance of payment.
Track fourteen: where the debtor is the lessor or licensor
Rejection does not evict. A lessee under a rejected lease may elect to remain in possession for the balance of the term including enforceable renewals, offsetting damages from post-rejection nonperformance against rent.
Assumption requires curing the landlord's own defaults — deferred maintenance, unfunded tenant improvement allowances, and service failures — which is frequently overlooked.
Clearing the property requires a sale under 11 U.S.C. § 363, not rejection, and whether a leasehold can be stripped in such a sale depends on state law under Butner v. United States.
Rents are usually cash collateral where the lender holds an assignment of rents, usable only with consent or authorization after adequate protection under 11 U.S.C. § 361 and 11 U.S.C. § 363.
Real property purchasers in possession may remain and receive title on completing payments; those not in possession have a lien for amounts paid.
The organizing principle. The estate cannot obtain by rejection anything the debtor could not have obtained by breach, which is what Mission Product Holdings, Inc. v. Tempnology, LLC holds and what governs every situation in this track.
Track fifteen: purchaser diligence
Confirm executoriness for each contract to be assumed, since a non-executory contract cannot be assigned over the counterparty's objection and must be dealt with by consent.
Confirm assignability against the applicable law exception, which is the failure point for licenses, personal service arrangements, franchises, and partnership interests.
Compute the cure cost and negotiate its allocation, since it is cash payable at closing.
Assess adequate assurance exposure, identifying counterparties likely to object and what will satisfy them.
Do not assume rejected contracts are resolved, since under Mission Product Holdings, Inc. v. Tempnology, LLC a rejected license does not necessarily terminate the licensee's rights, and a purchaser of the underlying intellectual property may find those rights persist.
Rely on the sale order for free and clear protections, not on rejection orders.
Address the designation period, including who funds performance while contracts are held open.
Address transfer taxes under Florida Department of Revenue v. Piccadilly Cafeterias, Inc..
Address successor liability through the sale order's free and clear language and the plan's injunction, since the contract assumptions do not determine what claims follow the assets.
Track sixteen: closing questions
Has every agreement been inventoried, including those the business does not call contracts?
Has executoriness been determined in writing for each material agreement?
Has the aggregate cure exposure been computed, and can the estate fund it?
Have the deadlines been calendared, particularly the outside limit on nonresidential real property leases that requires the lessor's written consent?
Is the adequate assurance package assembled for every contract to be assumed or assigned?
Has the applicable law exception been analyzed for every below-market contract whose value depends on assignment?
Has the circuit's rule on the hypothetical versus actual test been confirmed?
Have the labor and retiree processes under 11 U.S.C. § 1113 and 11 U.S.C. § 1114 been started, given that compliance is a confirmation condition?
Do the plan schedules under 11 U.S.C. § 1123 reconcile with the claims register?
Can the reorganized entity service the assumed obligations, for the feasibility finding?
Has anyone confirmed that rejection will actually accomplish what the business expects, given that it is a breach rather than a rescission?
Track seventeen: the designation rights structure
Understand what is being sold. In a retail or multi-location case the debtor frequently sells the right to designate which leases will be assumed and assigned, transferring the option itself rather than the leases.
Confirm the mechanics. Each designation is exercised by the purchaser, and at that point the estate assumes and assigns the lease under 11 U.S.C. § 365, with cure paid and adequate assurance provided as to the ultimate assignee.
Allocate the carrying cost, since the estate must continue performing obligations arising after the order for relief under nonresidential real property leases while they are held open, and the purchase agreement must say who funds that.
Calendar against the statutory deadline, since the designation period cannot outrun the one hundred twenty day period as extended, and any extension beyond requires each lessor's written consent.
Address landlord objections, which typically concern the identity of the ultimate assignee, the adequate assurance showing, and the burden of an extended period of uncertainty.
Address the cure timing, since landlords will resist a structure under which cure is deferred until designation and will seek current payment or escrow.
Preserve the estate's release, so that on each assignment the estate is relieved of liability for subsequent breaches.
Document the failure case, specifying what happens to leases not designated by the deadline, since they will be deemed rejected and must be surrendered, and the surrender obligations must be assigned to someone.
Related Documents
- The Contract Nobody Has Finished Performing Is the One the Debtor Gets to Choose About: How Executory Contracts Actually Work
- Executory Contracts and Leases: A Comprehensive Guide to Assumption, Rejection, Assignment, Cure, and Special Contract Types
- The Executoriness Analysis, Cure Computation, and Adequate Assurance Toolkit
- Everything Stops the Moment the Petition Is Filed, Including Things You Did Not Know Were Yours: How the Automatic Stay Actually Works
- The Automatic Stay: A Comprehensive Guide to Scope, Exceptions, Relief From Stay, Adequate Protection, and Damages for Violation
- Obtaining or Opposing Relief From the Automatic Stay: A Practical Checklist
- The Stay Scope Analysis, Adequate Protection Proof, and Stay Violation Damages Toolkit
- One Dissenting Class and the Whole Plan Has to Be Fair: How Chapter 11 Confirmation Actually Works
- Chapter 11 Confirmation: A Comprehensive Guide to Disclosure, Classification, Voting, Cramdown, Feasibility, and Releases
- Confirming or Objecting to a Chapter 11 Plan: A Practical Checklist
- The Classification Chart, Best Interests Test, and Cramdown Valuation Toolkit
- The Company Is Sold in Forty-Five Days and the Plan Comes Later: How Bankruptcy Sales Actually Work
- Bankruptcy Sales: A Comprehensive Guide to Section 363, Free and Clear Findings, Bidding Procedures, Credit Bidding, and Good Faith Protection
- Running or Bidding in a Bankruptcy Sale: A Practical Checklist
- The Bidding Procedures Motion, Free and Clear Analysis, and Sale Objection Toolkit
- The Company Failed Somewhere Else and Its Assets Are Here: How Cross-Border Insolvency Actually Works
- Cross-Border Insolvency: A Comprehensive Guide to Chapter 15 Recognition, Center of Main Interests, Relief, Cooperation, and Comity
- Seeking or Opposing Recognition of a Foreign Proceeding: A Practical Checklist
- The Center of Main Interests Analysis, Recognition Petition, and Discovery Relief Toolkit
- The Pallet That Never Arrived: How Freight and Cargo Claim Law Actually Works
- Freight, Cargo Claims, and Logistics: A Comprehensive Guide to Carmack, Bills of Lading, Broker Liability, and Warehouse Law
- Anatomy of a Lawful Layoff: WARN Notice, Disparate Impact, and the OWBPA Release
- Hell or High Water: Why an Equipment Lease Survives Equipment That Does Not Work
- The Airwaves Belong to the Public and the License Is a Lease: How Broadcast Regulation Actually Works
- The Lease That Outlives the Business: What a Small Business Signs and Cannot Undo
- The Price of Going Home: How Bail and Pretrial Release Actually Work
- The Release You Signed: How Settlement Agreements Fail and What Makes Them Hold
- Arresting a Vessel or Obtaining Its Release: A Practical Checklist
- Documenting a Farm Lease, Loan, or Neighbor Dispute: A Practical Checklist
- Locating a Detained Person and Seeking Release on Bond: A Practical Checklist
- Negotiating a Mineral Lease and Protecting the Surface: A Practical Checklist
- Negotiating and Exiting a Commercial Lease: A Practical Checklist
- Negotiating, Booking, or Terminating an Equipment Lease: A Practical Checklist