Opinion · Supreme Court of the United States

Wise v. United States

249 U.S. 361

Type
Opinion
Court
Supreme Court of the United States
Jurisdiction
Federal
Date
1919-03-31
Topic
general

How later courts describe this case

  • granting summary judgment to the government on plaintiffs claim for reduction in withholding of liquidated damages
  • noting “[t]here is nothing . . . in the record to indicate that the parties did not take into consideration, when estimating the amount of damage which would be caused by delay,” the possibility that the particular delay might occur
  • Liquidated damages may be enforceable when the damages are uncertain in nature or amount or are difficult of ascertainment.

Citator

UpLaw has not yet analyzed Wise v. United States. The absence of a flag is not a finding that it is good law.

Cited by
116 opinions

Headnotes

  1. Contracts Law — Liquidated Damages Whether a stipulated sum is to be treated as liquidated damages or as a penalty is determined by construing the agreement to ascertain the intention of the parties when they inserted the stipulation, just as their intention is sought in other respects; where that intention is clearly ascertainable from the writing, the provision will be given effect as freely as any other, where the damages are uncertain in nature or amount or difficult of ascertainment, or where the amount stipulated is not so extravagant or disproportionate to the amount of property loss as to show that compensation was not the object aimed at or to imply fraud, mistake, circumvention, or oppression. 249 U.S. at 364–365
  2. Contracts Law — Liquidated Damages Persons competent and free to contract may agree upon a provision for liquidated damages as fully as upon any other subject, and their agreement, when fairly and understandingly entered into with a view to just compensation for the anticipated loss, will be enforced. 249 U.S. at 365
  3. Contracts Law — Liquidated Damages The modern rule is to look with candor, if not with favor, upon provisions for liquidated damages deliberately entered into between parties having equality of opportunity to understand and insist upon their rights, because such provisions promote prompt performance and adjust in advance, amicably, matters whose settlement through courts would often involve difficulty, uncertainty, delay, and expense. 249 U.S. at 365–366
  4. Contracts Law — Liquidated Damages The fact that a single sum is stipulated as liquidated damages without regard to whether the completion of one or both of two buildings is delayed is not a sufficient reason for regarding the stipulation as a penalty, rather than as a genuine pre-estimate of loss. 249 U.S. at 364
  5. Contracts Law — Liquidated Damages Whether a party should be relieved from a plain stipulation for liquidated damages on the ground that a penalty was really intended depends upon the facts of the case, not upon a conjectural situation that might have arisen under the contract. 249 U.S. at 364