J. E. Hathaway & Co. v. United States
J. E. Hathaway & Co. v. United States, 249 U.S. 460 (1919)
- Type
- Opinion
- Court
- Supreme Court of the United States
- Jurisdiction
- Federal
- Date
- 1919-04-14
- Topic
- general
How later courts describe this case
- “[t]here is no reason why parties competent to contract may not agree that certain elements of damage difficult to estimate shall be covered by a provision for liquidated damages”
Citator
UpLaw has not yet analyzed J. E. Hathaway & Co. v. United States. The absence of a flag is not a finding that it is good law.
- Cited by
- 18 opinions
HATHAWAY CO.v. UNITED STATES,249 U.S. 460(1919)
39 S.Ct. 346
J.E. HATHAWAY COMPANYv. UNITED STATES.
APPEAL FROM THE COURT OF CLAIMS.
No. 255.
Argued March 19, 20, 1919.
Decided April 14, 1919.
THE case is stated in the opinion.
Here was a month taken, at the best season of the year for working, simply to obtain record evidence of the authority of the attorney in fact of the surety company to sign the contract. The delay was wholly on the part of the Government. Whether styled "reasonable" or "unreasonable," it was a delay for which the contractor was in no degree responsible. That the delay in signing the contract on the part of the Government was reasonable is, it is submitted, not a finding of fact but a conclusion of law.United Statesv.Pugh,99 U.S. 265;Sun Insurance Co. v.Ocean Insurance Co.,107 U.S. 485,502,503. Such a conclusion embodied in the findings of fact is not binding in this court.
When the contract was signed by the contractor and the bond executed by a surety company, the contractor had done everything which he could do to enter into a legally binding contract with the Government. To supply the slight defect a telegram should have been sent to the contractor.
The injustice of holding this contractor to a date of completion offered by him on April 29, when he was notPage 462notified of the completion of the contract as a binding obligation of the Government until June 13, is apparent. As soon as the contractor made his bid April 29, 1910, he was bound.United Statesv.Porto Rico S.S. Co.,239 U.S. 88. He was not notified that the contract was awarded to him until May 11, twelve days thereafter. There is no explanation of this delay and no apparent reason for it.District of Columbiav.Camden IronWorks,181 U.S. 453, is directly in point. See alsoAmericanDredging Co. v.United States, 49 Ct. Clms. 350;Ittnerv.United States, 43 Ct. Clms. 336;Little Falls Knitting MillCo. v.United States, 44 Ct. Clms. 1;Callahan ConstructionCo. v.United States, 47 Ct. Clms. 229, 235, 236;Laidlaw-Dunn-Gordon Co. v.United States, 47 Ct. Clms. 271;Missouri Valley Bridge Iron Co., 19 Comp. Dec. 712.Mr. Assistant Attorney General Friersonfor the United States.
The Court of Claims found: "There was no unreasonable delay on the part of the Government in approving the contract. "This finding, like one of reasonable value,Talbertv.UnitedStates,155 U.S. 45,46, is a finding of an ultimate fact by which this court is bound, unless it appears that the finding was made without supporting evidence,Cramp Sons Co. v.UnitedStates,239 U.S. 221,232;Stonev.United States,164 U.S. 380;United Statesv.Clark,96 U.S. 37, or is inconsistent with other facts found,United Statesv.Berdan Fire-ArmsCo.,156 U.S. 552,573. There is no such lack of supporting evidence or inconsistency here. We have consequently no occasion to determine whether, as was held inAmerican Dredging Co. v.United States, 49 Ct. Clms. 350, unreasonable delay on the part of the Government in approving a contract for an accepted bid can entitle the contractor to a corresponding extension of time, where a definite date is fixed by the contract for completion of the work. CompareMonroev.United States,184 U.S. 524. The case ofDistrict of ColumbiaPage 464v.Camden Iron Works,181 U.S. 453,461, strongly relied upon by claimants, is clearly distinguishable. There the contract, as interpreted by the court, provided that the work should be completed, not (as here) by a date fixed, but within a certain number of days; and the number of days was to be measured, not from the date of the contract but from "the date of the execution of the contract. "What was there decided is merely that under such circumstances it may be "shown that a deed, bond or other instrument was in fact made, executed and delivered at a date subsequent to that stated on its face."Second. Claimants contend also that the Court of Claims erred in allowing, in addition to the sum of $100 a day as liquidated damages, the sum of $182 for the expense of superintendence and inspection. But the contract expressly provided that time should be deemed of the essence and that in case of failure to complete within the time specified "the contractor shall pay, in addition to the liquidated damages hereinbefore specified, all expenses for inspection and superintendence." There is no reason why parties competent to contract may not agree that certain elements of damages difficult to estimate shall be covered by a provision for liquidated damages and that other elements shall be ascertained in the usual manner. Provisions of a contract clearly expressed do not cease to be binding upon the parties, because they relate to the measure of damages.Wisev.United States, ante, 361.Third. Claimants further contend that the credit of time allowed by the Government on account of the extra work should have been greater. On this matter no issue appears to have been raised below; and it is obviously not open for review here.
The judgment of the Court of Claims isAffirmed.Page 465