Opinion · Supreme Court of the United States

William Cramp & Sons Ship & Engine Building Co. v. United States

William Cramp & Sons Ship & Engine Bldg. Co. v. United States, 239 U.S. 221 (1915)

Type
Opinion
Court
Supreme Court of the United States
Jurisdiction
Federal
Date
1915-11-29
Topic
general

How later courts describe this case

  • “[T]he failure of the officers of the claimant company to apprehend the legal effect thereof was not the fault of the United States or its officers, and was not the subject of reformation.”
  • well established principles of equity jurisprudence requires reformation where mutual mistake is shown

Citator

UpLaw has not yet analyzed William Cramp & Sons Ship & Engine Building Co. v. United States. The absence of a flag is not a finding that it is good law.

Cited by
30 opinions

Headnotes

  1. General — Court of Claims — Findings of Fact — Conclusiveness Findings of fact made by the Court of Claims upon matters within its authority are conclusive and binding upon the Supreme Court, unless Congress otherwise provides, and where there is ample testimony to support those findings, no question of law is presented for independent review. 239 U.S. 221 (Cramp v. United States)
  2. Civil Procedure — Court of Claims — Referral by Special Act Where Congress by a special act refers a case to the Court of Claims with a right of appeal to the Supreme Court, that appeal, unless the special act otherwise provides, is governed by the rules applicable to cases arising under the general jurisdiction of the Court of Claims, and the findings of fact are treated as conclusive.
  3. Contracts Law — Reformation A release will not be reformed on the ground of mistake where there was no mutual mistake between the parties, the instrument expressed the true intent and purpose of the government, and the claimant's failure to apprehend the legal effect of the release was a mistake of law, not the fault of the government or its officers.
  4. Contracts Law — Mistake A complete release executed under a contract covers all claims arising out of the performance of the contract, including claims for damages caused by government delay in furnishing materials, even though the claimant's representative may not have understood the legal effect of the release at the time of execution.
  5. General — Court of Claims — Equitable Jurisdiction — Reformation of Contract The Court of Claims has jurisdiction, in cases within its general jurisdiction, to reform a contract for the purpose of determining whether a claim, if established, is valid against the United States.