Opinion · Supreme Court of the United States

William Cramp & Sons Ship & Engine Building Co. v. United States

William Cramp & Sons Ship & Engine Bldg. Co. v. United States, 216 U.S. 494 (1910)

Type
Opinion
Court
Supreme Court of the United States
Jurisdiction
Federal
Date
1910-02-28
Topic
general

Mr. Justice Brewer delivered the opinion of the court. On September 24, 1896, the appellant entered into a contract with the United States for the building of an ironclad, afterwards known as the “Alabama.” The contract was authorized by act of Congress of June 10, 1896, c. 399, 29 Stat. 361,378. Under this act and that of August 3,1886, c. 849, 24 Stat. 215, to which it refers, the Secretary of the Navy was charged with the duty of supervising the contract on behalf of the UnitedjStates. After the completion of the vessel and the payment of the stipulated amount there was something asserted to be due to the building company as unliquidated damages on account of extra work caused by the United States, for which it brought suit in the Court of Claims.

Citator

UpLaw has not yet analyzed William Cramp & Sons Ship & Engine Building Co. v. United States. The absence of a flag is not a finding that it is good law.

Cited by
17 opinions

Headnotes

  1. Administrative Law — Authority of Executive Officers Executive officers of the Government are not authorized to entertain and settle claims for unliquidated damages; such claims require the application of judgment and discretion and are not "accounts" subject to adjustment and payment by treasury or departmental accounting officers. 216 U.S. at 501–503
  2. Contracts Law — Authority to Modify Terms Acknowledging Change Where a provision in a government contract has been treated by both parties as impracticable and therefore waived, the Secretary of the Navy, charged with supervising performance of the contract, has power to change the terms of the release required by the contract, so as to leave the contractor's claims for unliquidated damages to be presented to the Court of Claims. 216 U.S. at 501–502, 505
  3. Contracts Law — Releases A release executed in accordance with the terms of a government contract extinguishes all claims of the contractor growing out of the contract; but where the release contains a proviso excluding claims of a kind the Secretary of the Navy had no jurisdiction to entertain, the proviso leaves the contractor's claims for unliquidated damages arising under the contract open for determination in the courts. 216 U.S. at 501, 505
  4. General — Court of Claims — Jurisdiction under the Tucker Act Under the Tucker Act, the Court of Claims has jurisdiction to hear and determine claims for unliquidated damages, liquidated or unliquidated, in cases not sounding in tort, including a claim for unliquidated damages under a contract for building a war vessel that is excepted from a release by the Secretary of the Navy's proviso. 216 U.S. at 505