Opinion · Supreme Court of the United States

Day v. United States

38 S. Ct. 57

Type
Opinion
Court
Supreme Court of the United States
Jurisdiction
Federal
Date
1917-11-26
Topic
general

river levy construction contractor held liable for increased cost of levy due to delay caused by river flooding | river levy construction contractor held liable for increased cost of levy due to delay caused by river flooding | “[W]hen the scope of the undertaking is fixed, that is merely another way of saying that the contractor takes the risk of the obstacles to that extent.”

Citator

Cited by
54 opinions