This guide is a systematic reference on energy infrastructure siting. Part 1 covers the interstate natural gas certificate framework and what an applicant must show. Part 2 covers federal environmental review and the alternatives analysis. Part 3 covers the delegated state authorities that survive preemption — water quality certification, wetlands permitting, and species consultation. Part 4 covers condemnation, possession, and compensation. Part 5 covers electric transmission siting under state law and the limited federal backstop. Part 6 covers participation, rehearing, and judicial review, with a final part on where each question is decided.

Energy Infrastructure Siting: A Comprehensive Guide to Certificates, Environmental Review, Eminent Domain, and State Preemption

Utilities and Energy > Pipeline and Transmission Siting, Certificates, and Eminent Domain | Published 20 September 2024 - Updated 2 February 2026 | UpLaw - uplaw.us

Orientation

Two frameworks govern, and they are structurally opposite.

Interstate natural gas Electric transmission
Siting authority Federal, under 15 U.S.C. § 717f State, with a limited federal backstop at 16 U.S.C. § 824p
Eminent domain Conferred by the federal certificate Conferred by state law
Local land use control Largely preempted Frequently survives
Multi-state projects One federal proceeding Approval required in each state
Where need is decided Certificate proceeding State commission
Where routing is decided Certificate proceeding and environmental review State proceeding, sometimes local
Practical difficulty of building Moderate High