Checklist · Energy

Evaluating, Signing, or Unwinding a Residential Solar Agreement: A Practical Checklist

26 U.S.C. § 25

Type
Checklist
Jurisdiction
National
Date
2023-11-06
Topic
Energy

This checklist covers a residential solar transaction from the sales visit through cancellation, dispute, or transfer on sale. Part 1 is what to do before signing anything, and it is the part that prevents almost every problem in this field. Part 2 verifies the two facts that decide the economics: the utility tariff and the household's tax capacity. Part 3 reads the agreement clause by clause. Part 4 covers cancellation and its very short windows. Part 5 assembles the complete document set. Parts 6 and 7 handle installation and interconnection problems and production shortfalls. Part 8 covers escalation and complaint forums, and Part 9 the claims and their deadlines. Part 10 addresses selling a home with panels, and Part 11 supplies a quality-control review.

Evaluating, Signing, or Unwinding a Residential Solar Agreement: A Practical Checklist

Energy > Residential Solar and Home Energy | Published 6 November 2023 - Updated 21 May 2026 | UpLaw - uplaw.us

How to Use This Checklist

Part 1 costs an hour and prevents nearly everything else. Part 4 has deadlines measured in days. Doctrine is in the comprehensive guide; the narrative introduction is what a residential solar contract actually commits you to; the letters are in the toolkit.

⚠ Never sign the same day. No legitimate incentive expires tonight.

Part 1 — Before You Sign

☐ Identify the structure: cash purchase, loan, lease, or power purchase agreement. If a third party owns the system, you are a customer, not an owner.

☐ Find the total of payments over the full term — not the monthly payment.

☐ Get two independent cash quotes for a system of the same size and components.

☐ Compare the cash price to the financed price. The difference is the dealer fee, and it is the true cost of the financing.

☐ Calculate the escalator forward. A 2.9 percent annual increase roughly doubles the payment by year twenty-five.

☐ Ask who receives the tax credit. Only an owner claims 26 U.S.C. § 25D.

☐ Ask whether the payment schedule has two tiers, and what triggers the higher one.

☐ Ask for the shade study and the production model, in writing.

☐ Ask for the assumed utility rate escalation and the assumed export compensation rate used in the savings projection.

☐ Ask what security will be recorded: UCC fixture filing, mortgage, or PACE assessment.

☐ Ask who owns the renewable energy credits.

☐ Verify the installer's license and bond with the state board and print the verification.

☐ Take the documents home and read them without anyone present.

Part 2 — Verify Two Facts With Third Parties

☐ Call the utility. Confirm the current net metering or net billing tariff; the export compensation rate; the applicable rate schedule and whether time-of-use applies; any fixed, minimum, or demand charges; the grandfathering period and the date that fixes it; and the interconnection timeline.

☐ Call a tax preparer. Confirm the household's federal tax liability for the last two years, that the credit under 26 U.S.C. § 25D is nonrefundable, and how many years it would take to absorb the credit.

☐ If the household cannot use the credit, the two-tier loan structure is unaffordable and the transaction should be restructured or declined.

☐ Document both conversations in writing to yourself, with dates and names.

Part 3 — Reading the Agreement

☐ Term and end-of-term options: purchase, renew, or remove, and at whose cost.

☐ Escalator rate and the year-twenty-five payment.

☐ Production guarantee: guaranteed output, measurement method, shortfall threshold, remedy, notice and claim deadlines, and exclusions.

☐ Maintenance and outage: who repairs, response time, and whether payments abate.

☐ Inverter replacement responsibility and expected cost within the term.

☐ Roof: penetration standards, leak responsibility, workmanship warranty duration, and removal and reinstallation cost for re-roofing.

☐ Insurance and casualty: who insures, whose policy responds, and what happens to payments after a loss.

☐ Assignment by the provider and transfer by you, including credit qualification, fees, and processing time.

☐ Default and remedies, including acceleration and credit reporting.

☐ Security interest and whether any filing will be recorded against the property.

☐ Dispute resolution: arbitration, class waiver, opt-out window, and small claims carve-out.

☐ Conditions precedent: utility approval, permitting, credit approval, and shade study — and your right to terminate if they fail.

☐ Integration clause, which is what defeats reliance on the sales presentation. Ask that the proposal be attached and incorporated.

Part 4 — Cancellation, and Its Deadlines

☐ Three business days to cancel a door-to-door sale under 16 C.F.R. part 429. Confirm you received the completed cancellation form; if not, the period is generally extended.

☐ Check the state home solicitation statute, which is frequently longer and may extend further for older consumers.

☐ Check for TILA rescission. If a security interest was taken in your principal dwelling, 15 U.S.C. § 1635 gives three business days after the later of consummation, delivery of material disclosures, or delivery of the rescission notice — extended to three years if those were not delivered.

☐ Cancel in writing, by a method that proves delivery.

☐ Send copies to the installer and the finance company.

☐ Demand that work stop immediately and that no equipment be delivered or installed.

☐ Demand return of any deposit within the statutory period.

☐ Demand termination of any UCC filing and confirmation of the termination.

☐ Do not allow removal of installed equipment without a written agreement addressing the loan.

☐ Keep everything, including envelopes and delivery confirmations.

Part 5 — Assemble the Complete Document Set

Request each of these in writing from the installer, the finance company, the utility, and the building department.

☐ The proposal or design document with the savings projection and its assumptions.

☐ The shade study and production model.

☐ The sales or installation contract with the system size and components.

☐ Every financing document, including the retail installment contract, lease, or power purchase agreement.

☐ The TILA disclosure under 15 U.S.C. § 1638 and 12 C.F.R. part 1026.

☐ The credit application and any documents signed electronically, with the audit trail.

☐ The notice of right to cancel required by 16 C.F.R. part 429, and any rescission notice under 15 U.S.C. § 1635.

☐ The consumer credit contract containing the Holder Rule notice, 16 C.F.R. part 433.

☐ Any UCC-1 financing statement or fixture filing, from the recorder or the secretary of state.

☐ Any PACE assessment documents and the tax bill showing it.

☐ The interconnection application and agreement with the utility.

☐ Permits and inspection records from the building department.

☐ All warranty documents: panels, inverter, and workmanship.

☐ Monitoring account credentials and exported production history.

☐ All communications, including text messages and voicemails.

⭐ What the provider cannot produce is often the case. A missing shade study, a missing cancellation form, and undelivered copies are each independently actionable.

Part 6 — Installation and Interconnection Problems

☐ Photograph the installation, including roof penetrations, flashing, conduit, and the electrical panel.

☐ Compare what was installed to what was contracted: panel count, model, inverter type, and system size in kilowatts.

☐ Confirm permits were pulled and inspections passed. Unpermitted work is a code enforcement problem as well as a contract problem; see Obtaining a Permit and Responding to a Notice of Violation: A Practical Checklist.

☐ Track the interconnection timeline and put delays in writing to both installer and utility.

☐ If you are paying on a system that is not producing, write to the finance company invoking the Holder Rule and demanding suspension.

☐ Document any roof leak immediately with photographs and a roofer's written assessment, and notify the installer and your insurer.

☐ Preserve the failed components if anything is replaced.

Part 7 — Production Shortfalls

☐ Export the production data from the monitoring portal, monthly, for the whole period.

☐ Compare to the guaranteed output and to the sales projection separately; they are different numbers.

☐ Check the guarantee's threshold and notice deadline before doing anything else.

☐ Submit the claim in writing within the deadline, with the data attached.

☐ Identify the cause: shading, soiling, inverter failure, panel failure, undersized system, curtailment, or a metering error.

☐ Compare the actual tariff to the projected tariff. A shortfall in savings with normal production is a tariff problem, not an equipment problem, and it is a misrepresentation claim rather than a warranty claim.

☐ Request a site visit and a written diagnostic report.

☐ Escalate to the manufacturer if the component warranty applies.

Part 8 — Escalation and Complaints

☐ Write to the provider, to a named executive, with dates, documents, and a specific demand and deadline.

☐ Write to the finance company invoking the notice at 16 C.F.R. part 433.

☐ File with the contractor licensing board, which can compel performance and order restitution.

☐ File with the state attorney general and consumer protection agency.

☐ File with the public utility commission for interconnection, metering, tariff, or retail supplier issues.

☐ File with the federal consumer financial regulator for the credit transaction.

☐ Check the arbitration clause for an opt-out window and a small claims carve-out before filing suit.

☐ Consider small claims where the amount fits; see Filing and Trying a Small Claims Case: A Practical Checklist.

☐ Do not simply stop paying without invoking a right in writing.

Part 9 — Claims and Deadlines

☐ State unfair and deceptive practices act — the engine, with statutory or treble damages and fee shifting.

☐ Misrepresentation and fraud, with the savings projection and its assumptions as the core evidence.

☐ Breach of contract and breach of warranty.

☐ TILA disclosure violations under 15 U.S.C. § 1638, with civil liability at 15 U.S.C. § 1640 and assignee liability at 15 U.S.C. § 1641.

☐ TILA rescission under 15 U.S.C. § 1635.

☐ Cooling-off and home solicitation violations under 16 C.F.R. part 429 and state law.

☐ Telemarketing violations under 16 C.F.R. part 310 where the sale began by phone.

☐ Holder Rule claims against the assignee under 16 C.F.R. part 433.

☐ Licensing statute claims, which in some states void the contract.

☐ Elder abuse statutes where applicable, with enhanced remedies.

☐ Negligence for installation and roof damage.

☐ Calculate every limitations period, noting that a defective rescission notice may preserve a three-year right. See Calculating and Preserving a Limitations Deadline: A Practical Checklist.

Part 10 — Selling a Home With Panels

☐ On listing day, pull the agreement and identify the structure.

☐ Call the provider in writing for the transfer requirements, the credit criteria, the fee, the processing time, and any buyout figure.

☐ Order a title search and a UCC search, and identify any fixture filing or PACE assessment.

☐ Determine whether a PACE assessment must be paid off for the buyer's financing.

☐ Disclose the agreement and its terms to buyers as state law requires.

☐ Provide the buyer with the full document set, including production history.

☐ Allocate responsibility in the purchase contract for payoff, transfer fees, and the risk that a buyer fails to qualify.

☐ Build a contingency and a timeline into the contract, because provider processing is measured in weeks.

☐ Obtain a recorded termination of any filing at closing and verify it in the index.

Part 11 — Quality Control

☐ Was the structure identified in writing?

☐ Was the total of payments compared against two independent cash quotes?

☐ Was the tariff verified with the utility and the tax capacity with a preparer?

☐ Was the escalator calculated to year twenty-five?

☐ Were complete copies of every signed document delivered and retained?

☐ Was the cancellation form received, and was the deadline calendared?

☐ Is the security instrument identified and its type confirmed?

☐ Is the production guarantee's threshold, notice deadline, and remedy recorded?

☐ Are the roof provisions and removal cost known?

☐ Are the transfer conditions known before the house is listed?

☐ Were all complaint forums used, and is proof of filing retained?

☐ Are all limitations periods calendared?

Part 12 — The Numbers Worksheet

Fill this in before signing, and again if a dispute develops. It converts a sales presentation into a comparison.

☐ System size: ____ kW DC · Estimated annual production: ____ kWh · Source of the estimate: ____

☐ Cash price quoted by this seller: $______

☐ Independent cash quote 1: $______ · Quote 2: $______ · Median market price per watt: $______

☐ Financed price / amount financed: $______ · Implied dealer fee: $______

☐ Annual percentage rate disclosed: ______ percent · Finance charge: $______ · Total of payments: $______

☐ Payment, months 1-18: $______ · Payment thereafter without the credit paydown: $______

☐ Federal tax liability, prior year: $______ · Two years prior: $______ · Credit available under 26 U.S.C. § 25D: $______ · Years to absorb: ______

☐ Escalator: ______ percent · Year-10 payment: $______ · Year-25 payment: $______

☐ Current utility rate: $______ per kWh · Assumed annual escalation in the projection: ______ percent

☐ Export compensation rate confirmed with the utility: $______ per kWh · Rate used in the projection: $______

☐ Fixed monthly charges that solar will not offset: $______

☐ Projected annual savings: $______ · Recalculated annual savings using confirmed tariff: $______

☐ Inverter replacement, estimated year and cost: ______ · $______

☐ Roof age and remaining life: ______ years · Removal and reinstallation cost: $______

☐ Twenty-five-year total cost: $______ · Twenty-five-year recalculated savings: $______ · Net: $______

⭐ The comparison that matters. Twenty-five-year total cost against twenty-five-year recalculated savings, using the tariff the utility confirmed rather than the one in the presentation.

Part 13 — If You Believe You Were Defrauded

☐ Write the chronology first, from first contact to today, with names, dates, and what was said.

☐ Identify the specific representations and who made them, and find any written or recorded version.

☐ Collect the tax return showing the credit could not be used, if that was the representation.

☐ Collect the tariff confirmation from the utility, if the savings projection was the representation.

☐ Collect the independent quotes, if the price or the dealer fee was the issue.

☐ Send the Holder Rule letter to the finance company quoting the notice in the contract itself, 16 C.F.R. part 433, and demanding suspension of payments and a cure.

☐ File with the licensing board and the attorney general the same week.

☐ Consult counsel about the state deceptive practices act, which typically supplies multiplied damages and fee shifting, and about elder abuse statutes if applicable.

☐ Check whether the signature is genuine. If the loan was originated without authorization, dispute it in writing, file a police report, and place a fraud alert.

☐ Preserve everything and delete nothing.

☐ Do not sign a release of claims against the finance company in exchange for a repair the installer may never perform.

Part 14 — A One-Page Sequence

  1. Do not sign the same day.
  2. Identify the structure and find the total of payments.
  3. Get two independent cash quotes.
  4. Call the utility about the tariff; call a preparer about the tax credit.
  5. Calculate the escalator to year twenty-five.
  6. Read the production guarantee, the roof provisions, and the transfer conditions.
  7. If you sign, confirm you received complete copies and the cancellation form.
  8. Calendar the cancellation deadline the same day.
  9. Photograph the installation and confirm permits and inspections.
  10. Export the production data monthly.
  11. If something fails, write to the finance company invoking the Holder Rule.
  12. Before listing the house, call the provider about transfer, and search for filings.

Part 15 — Special Situations

Older homeowners.

☐ Ask whether the state home solicitation statute provides an extended cancellation period for consumers over a stated age.

☐ Preserve the elder abuse claim, which in most states supplies enhanced damages, a longer limitations period, and fee shifting.

☐ Involve a trusted family member or agent under a power of attorney in the review, before signing.

☐ Report suspected exploitation to adult protective services; see Detecting, Reporting, and Unwinding Elder Financial Exploitation: A Practical Checklist.

Sales conducted in another language.

☐ Determine the language of the negotiation and the language of the documents.

☐ Check whether the state requires delivery of a translated contract, and whether violation voids the agreement or extends cancellation rights.

☐ Preserve any recording or written communication in the negotiation language.

Homeowners association or historic district property.

☐ Check the covenants and any state solar access statute limiting restrictions.

☐ Confirm whether architectural review or a certificate of appropriateness was required and obtained. See Challenging or Enforcing an HOA Rule, Fine, or Assessment: A Practical Checklist.

Manufactured or mobile homes.

☐ Determine whether the home and the land are separately owned.

☐ Check the lot lease for restrictions and the roof structure for capacity. See Buying, Selling, or Defending a Manufactured Home Tenancy: A Practical Checklist.

Financial distress.

☐ Determine whether the obligation is unsecured, secured by a fixture filing, or a PACE assessment collected with property taxes, because each is treated differently.

☐ Coordinate with any foreclosure or bankruptcy analysis before defaulting; see Preparing and Filing a Consumer Bankruptcy Case: A Practical Checklist.

Retail energy supplier contracts.

☐ Compare the offered rate to the utility default rate, and find the date the teaser converts.

☐ Find the early termination fee and the cancellation right.

☐ Complain to the public utility commission, which regulates suppliers in restructured markets.

Battery storage added later.

☐ Read the warranty for cycle limits, capacity retention, and degradation.

☐ Determine whether enrollment in a utility program permits a third party to discharge the battery, and on what terms.

Part 16 — Questions to Ask the Salesperson, and What the Answers Mean

Ask these in order, write down the answers, and read them back before signing. Every one of them is answerable in a sentence by someone who is being straightforward.

☐ "Do I own the system, or does someone else?" If the answer is anything other than a plain "you own it," the tax credit belongs to someone else and the transfer of the house will require a third party's approval.

☐ "What is the total of all payments over the whole term?" A salesperson who redirects to the monthly figure is avoiding the number that matters.

☐ "What would this system cost if I paid cash today?" The difference from the financed price is the dealer fee.

☐ "What annual increase in my utility rate does your savings estimate assume?" Anything above the historical average in your service territory is an assumption, not a fact.

☐ "What export rate does your estimate assume, and did you confirm it with the utility this month?"

☐ "Am I grandfathered into the current tariff, and until when?"

☐ "How much is my payment in year twenty-five?"

☐ "What happens to my payment if I cannot use the whole tax credit in the first eighteen months?"

☐ "Who pays to take the panels off and put them back when I replace the roof?"

☐ "What will be recorded against my property, and can I see a sample?"

☐ "What happens if I sell the house and the buyer does not qualify?"

☐ "Will you leave these documents with me overnight?" A refusal answers every other question.

⚠ Record the answers. Where recording is lawful in your state, or in a follow-up email confirming the conversation, these answers become the misrepresentation evidence if the transaction goes wrong. A short email — "Confirming our conversation today: you told me that ____" — costs nothing and is the most useful document most homeowners never create.