Bidding, Protesting, and Performing a Government Contract: A Practical Checklist

15 U.S.C. § 632

Type
Checklist
Jurisdiction
National
Date
2025-07-26
Topic
Business

This checklist follows a federal contract from market entry to closeout, with the deadlines that end cases marked at each stage. The first sequence covers registration, size and status determination, and the affiliation questions that decide set-aside eligibility. The second covers reading and responding to a solicitation, including the compliance matrix, the evaluation-factor analysis, and the pre-proposal protest window for solicitation defects. The third covers what to do in the days after award or loss, including the debriefing request and the protest timeliness rules that control the automatic stay. The fourth covers performance: change notices, delay documentation, requests for equitable adjustment, certified claims, and appeals. The fifth covers terminations of both kinds and the response to a cure notice. The sixth covers compliance events — an internal billing problem, a civil investigative demand, a subpoena, or a suspension notice. Each item is written so a non-specialist can act on it the same day.

Bidding, Protesting, and Performing a Government Contract: A Practical Checklist

Business > Government Contracting | Published 26 July 2025 - Updated 11 July 2026 | UpLaw - uplaw.us

⚠ Federal contracting punishes lateness more than it punishes almost anything else. Nearly every irreversible loss in this field is a missed deadline, not a lost argument. Deadlines in this checklist are marked ⚠ and should be calendared the day the triggering event occurs.


Sequence A — Market entry

A1. Registration and identity

☐ Obtain a unique entity identifier and complete registration in the government's contractor registration system. ☐ Complete the representations and certifications, and ⚠ read each one before certifying. ☐ Identify the industry codes that describe your work, and the size standard for each. ☐ Determine your size under 15 U.S.C. § 632 — employees or average annual receipts, including affiliates. ☐ Set a calendar reminder to update registration annually; a lapsed registration makes you ineligible for award.

A2. Size and affiliation analysis

☐ List every entity under common ownership or control. ☐ List every entity sharing officers, directors, or managing members. ☐ ⚠ Identify economic dependence — any customer providing the bulk of revenue. ☐ Identify family relationships creating an identity of interest. ☐ Evaluate the newly organized concern question if principals came from a larger firm. ☐ For each teaming arrangement, evaluate the ostensible subcontractor rule: who performs the primary and vital requirements, who supplies management, who supplies the workforce, whose past performance is cited. ☐ Confirm compliance with the limitation on subcontracting for any set-aside you intend to pursue.

A3. Program eligibility

☐ 8(a) business development — 15 U.S.C. § 637 ☐ HUBZone — 15 U.S.C. § 657a, including the employee residency requirement ☐ Service-disabled veteran-owned — 15 U.S.C. § 657f ☐ Women-owned small business — 15 U.S.C. § 637 ☐ General set-aside authority — 15 U.S.C. § 644; implementation at 48 C.F.R. part 19; policy at 15 U.S.C. § 631 ☐ ⚠ Do not certify to a status you cannot document. 15 U.S.C. § 645 and 18 U.S.C. § 1001 both apply.

A4. Systems and infrastructure

☐ Determine whether your accounting system can support cost-reimbursement work under 48 C.F.R. part 16; if not, restrict yourself to fixed-price and commercial items. ☐ Review the cost principles at 48 C.F.R. part 31 and segregate unallowable costs from the beginning. ☐ Establish a timekeeping practice that will survive an audit. ☐ Establish a document retention and litigation hold procedure. ☐ Establish an internal reporting channel and a written investigation practice. ☐ ⭐ Subcontract before you prime. One contract as a subcontractor teaches more than a year of reading.


Sequence B — Reading and answering a solicitation

B1. First pass — is this winnable?

☐ Identify the acquisition method: sealed bidding under 48 C.F.R. part 14, negotiated procurement under 48 C.F.R. part 15, commercial items under 48 C.F.R. part 12, or simplified acquisition under 48 C.F.R. part 13. ☐ Identify the contract type and who bears the risk — 48 C.F.R. part 16. ☐ Identify whether the procurement is set aside, and confirm your eligibility. ☐ ⭐ Find the sentence stating the relative importance of price to non-price factors, and read it twice. It determines your entire bid strategy. ☐ Identify mandatory minimum qualifications; if you cannot meet one, stop. ☐ Identify the incumbent, the period of performance, and any option years. ☐ Assess whether the requirement was written around a specific competitor's capability. ☐ Estimate your realistic probability of award before spending proposal budget.

B2. Compliance matrix

☐ Build a matrix listing every requirement in the instructions, the evaluation criteria, and the statement of work, with the proposal location that answers it. ☐ Verify page limits, font, margin, and file format requirements. ☐ Verify volume structure and what may not be cross-referenced between volumes. ☐ Verify submission method and the exact deadline, including time zone. ☐ ⚠ A late proposal is generally unreadable regardless of the reason. Submit early. ☐ Confirm every required certification, representation, and form is included and signed. ☐ Confirm every "shall" in the statement of work is addressed somewhere.

B3. Clauses

☐ Locate the clauses incorporated by reference — 48 C.F.R. part 52 — and read them, not just their numbers. ☐ Note the changes clause and its notice period — 48 C.F.R. part 43. ☐ Note the termination clauses — 48 C.F.R. part 49. ☐ Note the disputes clause — 48 C.F.R. part 33. ☐ Note payment and financing terms — 48 C.F.R. part 32; prompt payment at 41 U.S.C. § 3903. ☐ Note labor standards and wage determinations — 48 C.F.R. part 22, 41 U.S.C. § 3701, 41 U.S.C. § 3702. ☐ Note domestic preference requirements — 41 U.S.C. § 8702, 41 U.S.C. § 8703. ☐ Note whether funding is incremental — 31 U.S.C. § 1341, 31 U.S.C. § 1501.

B4. Questions and pre-proposal protests

☐ Submit written questions by the stated deadline; answers are issued to all offerors by amendment. ☐ Identify any ambiguity, unduly restrictive specification, or improper sole-source justification under 41 U.S.C. § 3304. ☐ ⚠ A protest of a solicitation defect must be filed BEFORE the deadline for receipt of proposals. Competing without objecting waives the ground. Authority: 31 U.S.C. § 3552, procedures at 48 C.F.R. part 33. ☐ Verify the competition requirements were satisfied — 41 U.S.C. § 3301, 41 U.S.C. § 3306; exclusions at 41 U.S.C. § 3303; design-build at 41 U.S.C. § 3305; simplified authority at 41 U.S.C. § 3307. ☐ Disclose and mitigate any organizational conflict of interest — 48 C.F.R. part 3 — before award, not after.

B5. Pricing

☐ Price to the evaluation scheme, not to habit. ☐ Confirm all labor categories map to the applicable wage determination. ☐ Segregate unallowable costs — 48 C.F.R. part 31. ☐ Verify the price is realistic if a realism analysis will be performed; an unrealistically low price can be a technical risk finding. ☐ ⚠ Check the arithmetic twice. Sealed-bid mistake correction requires clear and convincing evidence and is not reliable relief.


Sequence C — Immediately after award or loss

C1. If you lost

☐ ⚠ Request a debriefing in writing, the same day, and keep the timestamp. ☐ Attend the debriefing and take verbatim notes; submit written questions if the process allows. ☐ Confirm in writing the date the debriefing closed. ☐ Analyze against the stated evaluation criteria: did the agency credit something the RFP did not identify? Treat comparable features differently? Fail to raise a significant weakness in discussions? Fail to document the tradeoff? ☐ Assess prejudice: would you have had a substantial chance of award if the error were corrected? ☐ ⚠ Protest within ten days of knowing the basis — or within ten days of the debriefing where one was required and timely requested. 31 U.S.C. § 3553. ☐ ⭐ Confirm the filing date that triggers the automatic stay. A protest without a stay is usually academic. ☐ If a size or status issue exists, file a size protest with the contracting officer within the very short SBA window. ☐ Choose the forum: GAO for speed and the stay — 31 U.S.C. § 3551, 31 U.S.C. § 3554; Court of Federal Claims for injunctive relief and appeal rights — 28 U.S.C. § 1491. Remedies are not exclusive — 31 U.S.C. § 3556.

C2. If you won

☐ Read the awarded contract against your proposal; identify every discrepancy and raise it now. ☐ Confirm the identity and warrant of the contracting officer. ☐ Identify the COR and confirm, in writing, that the COR has no authority to change the contract. ☐ Calendar every deliverable, report, and option decision date. ☐ Calendar the funded amount and set a threshold alert. ☐ Confirm insurance, bonding, and any facility or personnel clearance requirements. ☐ Flow required clauses down to subcontractors. ☐ Confirm subcontractor small business status representations in writing. ☐ Establish the contract file: correspondence, meeting minutes, daily reports, photographs, and time records. ☐ ⭐ Set a standing practice: confirm every significant conversation with the government in a short email the same day.


Sequence D — Performance and money

D1. When the work changes

☐ Identify the direction: who gave it, in what form, on what date. ☐ ⚠ If it did not come from the contracting officer, get written confirmation from the contracting officer before performing. ☐ Determine whether the change is within the general scope (an equitable adjustment) or beyond it (a cardinal change, potentially a breach). ☐ ⚠ Send written notice within the period the changes clause specifies — 48 C.F.R. part 43. ☐ Describe the change, its date, its source, and its anticipated cost and schedule impact. ☐ Reserve the right to an equitable adjustment expressly. ☐ Begin segregated cost accounting for the changed work on day one. ☐ Photograph and log conditions before, during, and after.

D2. Documenting delay and disruption

☐ Maintain a contemporaneous daily log: crew, weather, activities, interruptions, and who directed what. ☐ Maintain the as-planned schedule and the as-built schedule. ☐ Identify each delay event, its cause, its duration, and whether it is on the critical path. ☐ Distinguish excusable delay (beyond the contractor's control and without its fault) from compensable delay (caused by the government). ☐ Identify concurrent delays and analyze them; concurrency defeats compensability in most analyses. ☐ Preserve government-caused impacts: late approvals, denied access, unavailable government-furnished property, changed conditions, and interference. ☐ ⭐ The contemporaneous record beats the retrospective expert analysis every time.

D3. Request for equitable adjustment

☐ Confirm entitlement: a change attributable to the government, causing added cost, with notice given. ☐ Quantify with actual costs where available; use a modified total cost approach only as a last resort and be prepared to justify it. ☐ Include: labor, materials, equipment, subcontractor impacts, extended overhead, and profit. ☐ Support each element with records, not estimates. ☐ ⭐ Note that REA preparation costs may be allowable as contract administration; claim prosecution costs are not. ☐ Submit as an REA first and negotiate before converting to a claim.

D4. Certified claim

☐ Confirm you are within six years of accrual — 41 U.S.C. § 7103. ☐ State a sum certain. ⚠ This is jurisdictional. ☐ Include the certification if the amount exceeds the statutory threshold: good faith; accurate and complete supporting data; the amount accurately reflects the adjustment believed owed; the certifier is authorized. ☐ Request a contracting officer's final decision expressly. ☐ Calendar the date the CO received it — ⭐ interest runs from receipt. ☐ Calendar the date by which a final decision is due. ☐ Applicable framework: 41 U.S.C. § 7101, 41 U.S.C. § 7102, 41 U.S.C. § 7105, 41 U.S.C. § 7106, 41 U.S.C. § 7107.

D5. Appealing a final decision

☐ ⚠ 90 days to a board of contract appeals, or 12 months to the Court of Federal Claims — 41 U.S.C. § 7104, 28 U.S.C. § 1491. ☐ Calendar both deadlines the day the decision arrives, in two systems. ☐ Consider the accelerated or small claims procedure for smaller amounts — 41 U.S.C. § 7106. ☐ ⚠ A government claim (defective pricing, overpayment, liquidated damages) starts the same clock against you. Do not treat a final decision demanding money as correspondence.

D6. Past performance

☐ Read every proposed performance evaluation under 48 C.F.R. part 42. ☐ Respond within the stated comment window, factually and specifically. ☐ Escalate any material inaccuracy to the reviewing official. ☐ ⭐ A negative rating left unrebutted follows the company into every future competition.


Sequence E — Terminations

E1. Cure notice or show cause notice

☐ ⚠ Calendar the response deadline the day it arrives — commonly ten days. ☐ Address each alleged failure specifically. ☐ Assert every excusable cause with documentation: government acts, acts of God, epidemics, strikes, embargoes, unusually severe weather. ☐ Identify every government act that caused or contributed to the problem. ☐ Provide a concrete corrective plan with dates, staffing, and milestones. ☐ Reserve rights to an equitable adjustment for government-caused impacts. ☐ ⚠ Do not concede fault in an effort to appear cooperative.

E2. If terminated for default

☐ Preserve the entire record immediately. ☐ Analyze conversion grounds: government-caused delay; ⭐ waiver of the delivery date by permitting continued performance; defective or absent cure notice; no actual default; abuse of discretion. ☐ Submit a claim contesting the termination and appeal the final decision within the deadline. ☐ Quantify exposure to excess reprocurement costs and unliquidated progress payments. ☐ Address the past performance consequences under 48 C.F.R. part 42. ☐ Assess responsibility and debarment exposure under 48 C.F.R. part 9.

E3. If terminated for convenience

☐ Stop work as directed and issue stop-work notices to subcontractors. ☐ Preserve and inventory materials, work in process, and special tooling. ☐ Settle subcontractor terminations and document each settlement. ☐ Prepare the settlement proposal — costs incurred, reasonable profit on work performed, settlement expenses. ☐ ⚠ Anticipated profit on unperformed work is not recoverable. ☐ ⚠ File the settlement proposal within one year of the termination notice, or seek an extension in writing — 48 C.F.R. part 49.


Sequence F — Compliance events

F1. You discover a billing or certification problem

☐ ⚠ Stop the practice immediately. ☐ Issue a litigation hold; ⚠ no one deletes or "cleans up" anything — 18 U.S.C. § 1519. ☐ Retain counsel before interviewing anyone. ☐ Quantify the exposure: how many invoices, over what period, in what amount. ☐ Analyze materiality under Escobar, 579 U.S. 176, and scienter under Schutte, 598 U.S. 739 — ⭐ the question is what the company actually believed at the time. ☐ Assess exposure under 31 U.S.C. § 3729: treble damages plus per-claim penalties. ☐ Assess criminal exposure under 18 U.S.C. § 287, 18 U.S.C. § 286, 18 U.S.C. § 1001, 18 U.S.C. § 1031, and 18 U.S.C. § 371. ☐ Evaluate voluntary disclosure; it is a recognized mitigating factor under 48 C.F.R. part 9. ☐ Consider the administrative remedy path at 31 U.S.C. § 3801, 31 U.S.C. § 3802, 31 U.S.C. § 3803.

F2. A civil investigative demand or subpoena arrives

☐ Preserve everything, in writing, the same day. ☐ Identify the issuing authority — 31 U.S.C. § 3733 authorizes CIDs. ☐ Note that a sealed qui tam may underlie it — 31 U.S.C. § 3730; limitations and burden at 31 U.S.C. § 3731; venue at 31 U.S.C. § 3732. ☐ Do not contact potential relators or witnesses about the investigation without counsel. ☐ Do not retaliate; retaliation is separately actionable under 31 U.S.C. § 3730 and 10 U.S.C. § 2409. See reporting misconduct and preserving a retaliation claim and whistleblower and retaliation claims. ☐ Note that the government may seek dismissal even after declining — Polansky, 599 U.S. 419.

F3. A suspension or proposed debarment notice arrives

☐ ⚠ Calendar the response deadline immediately — it is typically 30 days. ☐ Determine the scope: which entities and individuals are covered. ☐ Notify customers, lenders, sureties, and teaming partners as your agreements require. ☐ Assemble the present responsibility showing: corrective action taken, individuals disciplined or removed, restitution paid, compliance program installed and independently assessed, internal controls changed. ☐ Consider an administrative agreement with independent monitoring. ☐ Governing framework: 48 C.F.R. part 9; ethics rules at 48 C.F.R. part 3. ☐ ⭐ Every document you file should answer one question: why is this a company the government can safely do business with today?


The deadline table

Event Deadline If missed
Solicitation defect protest Before proposals are due ⚠ Waived permanently
Debriefing request Within the stated window after notice Loses the favorable protest clock
Post-debriefing protest 10 days ⚠ Loses the automatic stay
Other protest grounds 10 days from knowledge Dismissed
Size or status protest ~5 business days Dismissed
Change notice under the changes clause As stated, often 30 days Prejudice defense
Cure notice response As stated, often 10 days Default termination
CDA claim 6 years from accrual Barred
Board appeal ⚠ 90 days Barred
Court of Federal Claims appeal ⚠ 12 months Barred
Convenience settlement proposal 1 year Unilateral determination
Past performance comment As stated Rating stands
Debarment response ~30 days Decided on the government's record

Related resources

Background and doctrine: government contracting. Plain-language overview: selling to the government. Forms and letters: the government contracting and bid protest toolkit.

Adjacent: starting and running a small business, forming and launching a small business, contracts, drafting, reviewing, and enforcing a contract, the contract drafting and breach response toolkit, the employee who said something, and the whistleblower protection and retaliation claim toolkit.

⭐ One habit covers most of this checklist: write it down, send it the same day, and keep the copy. Federal contracting disputes are decided on the contemporaneous record, and the party with the file wins.


Appendix: three worked situations

Situation one — "We lost, and the debriefing said our past performance was 'Satisfactory' on a contract where our rating was 'Very Good.'"

☐ Pull the actual performance report from the government system and print it with its date. ☐ Compare it to what the agency said it relied on. ☐ Determine whether the RFP required past performance to be evaluated from that system. ☐ If the agency used stale or incorrect data, that is an unreasonable evaluation, not a difference of opinion — a real protest ground. ☐ ⚠ File within ten days of the debriefing. Do not spend three weeks gathering more evidence; the agency report will produce it.

Situation two — "The government keeps asking for extra deliverables and says it's all within scope."

☐ Compare each request against the statement of work, line by line. ☐ For each item not required, send a short notice: what was requested, by whom, on what date, and that the contractor considers it a change. ☐ Ask the CO to either withdraw the request or issue a modification. ☐ Perform under protest if directed by the CO, with a written reservation. ☐ Track the cost separately from day one. ☐ ⭐ Ten short letters over six months are worth more than a 200-page claim at closeout.

Situation three — "Our subcontractor is doing most of the work on a set-aside."

☐ Compute the percentage of the contract performed by your own employees against the limitation on subcontracting. ☐ Compare the proposal's key personnel and past performance sources against who actually controls the work. ☐ If you are out of compliance, fix it now — reassign work, hire, or notify the CO. ☐ ⚠ Understand the exposure if you do not: loss of the contract, a size protest, potential False Claims Act liability under 31 U.S.C. § 3729, and debarment under 48 C.F.R. part 9. ☐ Document the corrective action contemporaneously; it is the difference between a mistake and a misrepresentation.