Opinion · Supreme Court of the United States

Lujan v. G & G Fire Sprinklers, Inc.

Lujan v. G & G Fire Sprinklers, Inc., 532 U.S. 189 (2001)

Type
Opinion
Court
Supreme Court of the United States
Jurisdiction
Federal
Date
2001-04-17
Topic
litigation

How later courts describe this case

  • holding that due process is not deprived when California law affords plaintiff sufficient opportunity to pursue the claim in state court
  • holding that a California law which provided sufficient opportunity to pursue payment in state court did not violate due process
  • holding that availability of post-deprivation breach-of-contract claim satisfied government contractor’s right to due process
  • holding that where a state provides a remedy through a breach of contract, there is no due process violation when a contract is not paid by the state
  • holding that an ordinary breach of contract suit was enough process due to resolve a state’s alleged failure to comply with contract terms that resulted in depriving plaintiffs of payments
  • providing that post-deprivation adjudication was sufficient process for a state contractor allegedly deprived of payments
  • explaining that as long as the state “makes ordinary judicial process available to respondent for resolving its contractual dispute, that process is due process”
  • holding, in a different context, that, if a party's only relevant property interest is a claim of entitlement to bring an action, the provision of a forum for hearing that action is all that is required to vindicate that property interest

Citator

UpLaw has not yet analyzed Lujan v. G & G Fire Sprinklers, Inc.. The absence of a flag is not a finding that it is good law.

Authority status
pending
Cited by
146 opinions
Distinguished
1 times

Headnotes

  1. Constitutional Law — Procedural Due Process Where a state law is challenged on due process grounds, the court asks whether the State has deprived the claimant of a protected property interest and whether the State's procedures comport with due process. In contrast to cases in which the claimant was denied a right by virtue of which he was presently entitled either to exercise ownership dominion over real or personal property or to pursue a gainful occupation, a claimant who has only a claim that it complied with its contract and is therefore entitled to payment has not been denied any present entitlement, and that interest can be fully protected by an ordinary breach-of-contract suit. 532 U.S. at 195-197
  2. Constitutional Law — Procedural Due Process Due process is not a technical conception with a fixed content unrelated to time, place, and circumstances, and the very nature of due process negates any concept of inflexible procedures universally applicable to every imaginable situation; accordingly, if a State makes ordinary judicial process available to a claimant for resolving its contractual dispute, that process is due process. 532 U.S. at 196 (quoting Cafeteria & Restaurant Workers v. McElroy, 367 U.S. 886, 895 (1961))
  3. Constitutional Law — Procedural Due Process A subcontractor's claim for payment withheld under a state labor code is not deprived of due process where the statutory scheme permits the contractor to assign to the subcontractor the right to sue the awarding body on the contract for alleged breach in not making payment, thereby providing a means by which the subcontractor may bring a breach-of-contract claim to recover the withheld wages and penalties. 532 U.S. at 197-198
  4. Constitutional Law — Procedural Due Process The retention of disputed funds pending the outcome of a breach-of-contract suit, even one lasting several years, does not deprive a claimant of its claim for payment under the contract; lawsuits are not known for expeditiously resolving claims, and the standard practice in breach-of-contract suits is to award damages, if appropriate, only at the conclusion of the case. 532 U.S. at 198
  5. Constitutional Law — Procedural Due Process A statutory provision making suit on the contract against the awarding body the exclusive remedy of the contractor or his assignees is, by its terms, exclusive only as to the contractor and his assignees and not as to a subcontractor who does not receive assignment; a subcontractor may therefore pursue its claim for payment by bringing a standard breach-of-contract suit against the contractor under state common law. 532 U.S. at 198-199
  6. Constitutional Law — Presumption of Constitutionality — Burden of Proof A party challenging a statutory withholding scheme on due process grounds bears the burden of demonstrating its unconstitutionality, and where the party has not shown that available avenues of state-court relief are closed to it, the statutory provisions do not deprive it of property without due process of law. 532 U.S. at 199