41 U.S.C. § 4707 — Remission of liquidated damages

41 U.S.C. § 4707

Type
Statute
Source
United States Code
Jurisdiction
Federal
Date
2026-10-22

When a contract made on behalf of the Federal Government by the head of a Federal agency, or by an authorized officer of the agency, includes a provision for liquidated damages for delay, the Secretary of the Treasury on recommendation of the head of the agency may remit any part of the damages as the Secretary of the Treasury believes is just and equitable.

Citator

41 U.S.C. § 4707 — Remission of liquidated damages is in force in the current edition of the Code, and nothing recorded condemns it.

When a contract made on behalf of the Federal Government by the head of a Federal agency, or by an authorized officer of the agency, includes a provision for liquidated damages for delay, the Secretary of the Treasury on recommendation of the head of the agency may remit any part of the damages as the Secretary of the Treasury believes is just and equitable.