Working instruments for every side of an electric vehicle charging matter. The resident set includes a right-to-charge application template, a deemed-approval notice, and a capacity documentation request. The association set includes a charging policy outline, a review log, and a cost allocation grid. The host set includes a demand charge model, an interconnection tracker, a network agreement term sheet, and an accessibility design checklist. The operations set includes a price posting audit, a session and outage log, and a driver incident record. An authority quick reference completes it.
The Electric Vehicle Charging, Right-to-Charge, and Site Host Toolkit
Energy > Electric Vehicles and Charging Infrastructure | Published 2 September 2025 - Updated 20 August 2026 | UpLaw - uplaw.us
How this toolkit is built
Fourteen instruments. Bracketed text is for completion.
Three rules organize the set: a complete application starts the clock and an incomplete one does not; load management answers most capacity objections; and the demand charge, not the energy price, decides whether a commercial site works.
Tool 1 — Right-to-Charge Application
To: [Association / Landlord], [address] · From: [owner/tenant], Unit [ ] · Date: [ ]
Re: Application to install an electric vehicle charging station in [space identifier]
Pursuant to [state statute], I request approval to install a charging station in my [assigned parking space / space under my exclusive control].
1. Space. [Identifier, location, level.]
2. Equipment. [Make, model, listing laboratory certification, dimensions, color.] Specification sheet attached as Exhibit A.
3. Electrical. Proposed circuit: [ ] amps at [ ] volts. The installation will include a load management device limiting draw to [ ] amps, specification attached as Exhibit B.
4. Installation plan. Route from [point of connection] to the space, [concealed/surface] conduit, mounting method. Drawings attached as Exhibit C.
5. Contractor. [Name], license no. [ ], insurance certificate attached as Exhibit D.
6. Permits. Application will be made to [authority] for an electrical permit; inspection will be completed before energization.
7. Metering and billing. [Method proposed.]
8. Insurance. Certificate of liability insurance in the amount of $[ ], naming the Association as an additional insured, attached as Exhibit E.
9. Costs. I agree to pay all costs of installation, operation, maintenance, repair, removal, and electricity consumed, and to repair any damage to common elements. These obligations shall run with the unit and bind my successors.
10. Request. Approval within the period provided by [statute]. Please also provide the Association's current electrical load calculation.
Delivered by [method] on [date]. Receipt requested.
📌 Attach everything. The statutory clock starts on a complete application, and an association's best defense is that the application was incomplete.
Tool 2 — Deemed-Approval Notice
[Date] · To: [Association], [address]
Re: Application of [owner], Unit [ ], dated [date] — approval by operation of law
On [date] I submitted a complete application to install an electric vehicle charging station in [space], together with all supporting documentation. A copy of the delivery record is enclosed.
[State statute] requires the Association to approve or deny a complete application in writing, with reasons, within [period]. That period expired on [date]. No written decision has been issued.
The application is therefore approved by operation of law. I will proceed with permitting and installation, and I will comply with each condition the statute imposes: licensed contractor, permits and inspection, insurance naming the Association as an additional insured, payment of all costs, and repair of any damage.
I will provide the permit and inspection records and an updated insurance certificate when issued. If you believe the application was incomplete, please identify the missing item in writing within seven days.
[Signature]
⚠️ Send this by a method that proves delivery, and keep proof of the original application's delivery date. Those two dates are the entire argument.
Tool 3 — Capacity Documentation Request
[Date] · To: [Association]
Re: Request for electrical capacity information
In connection with my charging application, please provide:
- The building's electrical service size and the utility account information;
- The most recent load calculation and the date it was performed, together with the name of the engineer;
- The connected load and any documented spare capacity;
- Any engineering study concerning charging capacity;
- Whether the Association has installed or evaluated a load management system;
- Whether the Association has inquired about the utility's make-ready program;
- Any prior charging applications, and their disposition;
- Any capacity reserved for future installations, and the basis for the reservation.
If the Association denies my application on capacity grounds, please identify the specific document supporting the denial.
Note: my application proposes a load-managed installation capped at [ ] amps, which is designed to fit within existing capacity.
📌 This request usually resolves the dispute. Either the documentation exists and the parties can engineer around it, or it does not and the denial cannot stand.
Tool 4 — Association Charging Policy Outline
☐ 1. Purpose and statutory reference ☐ 2. Definitions — charging station, assigned space, common element, load management, service capacity ☐ 3. Application — form, required attachments, and what makes it complete ☐ 4. Review — timeline matching the statute, responsible officer, written decision with reasons, and an express statement that failure to act constitutes approval ☐ 5. Standards — listed equipment, licensed electrician, permits and inspection, concealed conduit where practicable, amperage cap absent a capacity study, load management required ☐ 6. Capacity — maintain a current load calculation and make it available to applicants ☐ 7. Cost allocation — itemized (see Tool 5) ☐ 8. Metering and billing — method, frequency, and meter maintenance ☐ 9. Insurance — amount, additional insured status, certificate delivery and renewal ☐ 10. Maintenance, repair, removal — running with the unit and binding successors ☐ 11. Shared charging — time limits, idle fees, reservations, pricing, enforcement authority, accessible station ☐ 12. Records — unit file documentation and recording where permitted ☐ 13. Annual review of capacity, utilization, and the policy itself
Tool 5 — Cost Allocation Grid
| # | Component | Owner | Common expense | Utility make-ready | Notes |
|---|---|---|---|---|---|
| 1 | The charging station itself | ☐ | |||
| 2 | Wiring from the point of connection to the space | ☐ | |||
| 3 | Dedicated breaker | ☐ | |||
| 4 | Sub-panel serving multiple future spaces | ☐ | ☐ | ||
| 5 | Conduit and raceway benefiting multiple units | ☐ | ☐ | ||
| 6 | Main service upgrade | ☐ | ☐ | ||
| 7 | Transformer and utility-side work | ☐ | |||
| 8 | Load management system | ☐ | |||
| 9 | Metering equipment | ☐ | ☐ | Depends on method | |
| 10 | Electricity consumed | ☐ | By meter or submeter | ||
| 11 | Maintenance of the owner's station | ☐ | |||
| 12 | Maintenance of shared infrastructure | ☐ | |||
| 13 | Permits for the owner's installation | ☐ | |||
| 14 | Engineering and load calculation | ☐ | Association's obligation to maintain | ||
| 15 | Removal and restoration | ☐ | Runs with the unit |
⚠️ Rows 4 through 8 are where disputes live. Requiring the first applicant to fund shared infrastructure is generally unreasonable and is frequently a breach of the duty to allocate common expenses fairly.
Tool 6 — Association Review Log
| # | Applicant | Unit | Date received | Complete? | Date completed | Statutory deadline | Decision | Date decided | Written reasons? |
|---|---|---|---|---|---|---|---|---|---|
| 1 | ☐ | ⚠️ | ☐ approve ☐ deny | ☐ |
☐ Record the completeness determination the day the application arrives, in writing to the applicant ☐ Calendar the statutory deadline immediately and assign a named officer ☐ Issue every decision in writing, with reasons, before the deadline ☐ File the insurance certificate and diary its renewal ☐ Record the approval in the unit file ☐ Update the running total of installed amperage against the load calculation
📌 This log is the association's defense. Its absence is the applicant's case.
Tool 7 — Demand Charge Model
Run before signing any equipment, network, or construction agreement.
Rate schedule: [ ] · Energy charge: $[ ]/kWh · Demand charge: $[ ]/kW · Interval: [ ] minutes · Ratchet? ☐ Yes — [ ] months
Line Input 10% util. 25% util. 50% util. A Chargers × rated kW B Peak simultaneous draw (kW) C Monthly demand charge = B × rate D Sessions per month E kWh delivered per month F Energy charge = E × rate G Customer and fixed charges H Total monthly cost = C + F + G I Cost per session = H ÷ D J Cost per kWh delivered = H ÷ E K Realistic price per kWh chargeable L Margin = (K − J) × E ☐ Break-even utilization: [ ]% — is it achievable at this location? ☐ Charging-specific tariff available? ☐ Demand charge holiday or phase-in? ☐ Make-ready program? ☐ Load management cap to hold line B below [ ] kW ☐ On-site storage evaluated? Standby charges if added?
⚠️ A ratchet provision means one peak sets a floor for months. Model it explicitly.
Tool 8 — Interconnection Tracker
| # | Step | Owner | Date submitted | Expected | Actual | Notes |
|---|---|---|---|---|---|---|
| 1 | Pre-application meeting with utility | |||||
| 2 | Load and equipment specification finalized | |||||
| 3 | Interconnection application filed | ⚠️ critical path | ||||
| 4 | Feasibility study | |||||
| 5 | System impact study | |||||
| 6 | Facilities study and cost estimate | |||||
| 7 | Cost allocation agreed — refundable portion? | |||||
| 8 | Easements negotiated and recorded | |||||
| 9 | Make-ready program application | |||||
| 10 | Metering configuration confirmed | |||||
| 11 | Construction agreement executed | |||||
| 12 | Utility-side construction | |||||
| 13 | Customer-side construction and trenching | |||||
| 14 | Inspection and energization |
☐ File step 3 before the building permit application ☐ Sequence trenching once for the full build-out, even if chargers are phased ☐ Note the jurisdictional frame: retail is state, wholesale and transmission are federal under 16 U.S.C. § 824, with rates at 16 U.S.C. § 824d and 16 U.S.C. § 824e; see FERC v. Electric Power Supply Association, 577 U.S. 260 and Hughes v. Talen Energy Marketing, LLC, 578 U.S. 150 before any grid-services participation ☐ Check what the commission decided in its charging proceeding under 16 U.S.C. § 2621, with the framework at 16 U.S.C. § 2601 and procedures at 16 U.S.C. § 2622; cogeneration and small power production is at 16 U.S.C. § 824a-3
Tool 9 — Network Agreement Term Sheet
| # | Term | Position sought | Agreed |
|---|---|---|---|
| 1 | Equipment ownership | ||
| 2 | Electricity cost — who bears the demand charge | Network, or host with a cap | |
| 3 | Removal and restoration, with bond or escrow | Required | |
| 4 | Term, renewal, exclusivity | Non-exclusive; short initial term | |
| 5 | Uptime commitment and remedy | Both, with credits | |
| 6 | Maintenance scope and response times | Hours, with escalation | |
| 7 | Pricing control and idle fees | Host input | |
| 8 | Revenue share and reporting | With audit rights | |
| 9 | Data ownership and permitted use | Host retains site data | |
| 10 | Insurance and indemnity, including electrical events | ||
| 11 | Assignment on sale; recording; subordination | Survives sale | |
| 12 | Funding conditions and who bears compliance | Network | |
| 13 | Signage, branding, site standards | ||
| 14 | Obsolescence and connector upgrades | Allocated | |
| 15 | Equipment warranty pass-through — 15 U.S.C. § 2301, 15 U.S.C. § 2310 |
📌 Rows 2 and 3 decide whether the deal is good.
Tool 10 — Accessibility Design Checklist
Design it in. Retrofitting a charging space costs several times what building it correctly costs.
| # | Element | Standard | Complies |
|---|---|---|---|
| 1 | Accessible route from the space to the entrance | Continuous, unobstructed | ☐ |
| 2 | Access aisle width sufficient to deploy a ramp or lift | ☐ | |
| 3 | Aisle free of bollards, wheel stops, and equipment | ☐ | |
| 4 | Screen and display within reach ranges | ☐ | |
| 5 | Connector within reach ranges and manageable weight | ☐ | |
| 6 | Payment device within reach ranges | ☐ | |
| 7 | Operable parts usable with one hand, no tight grasping, pinching, or twisting | ☐ | |
| 8 | Cable routing does not cross the access aisle or the route | ☐ | |
| 9 | Surface stable, firm, slip-resistant; slope compliant | ☐ | |
| 10 | Adequate lighting | ☐ | |
| 11 | Signage and wayfinding | ☐ | |
| 12 | At least one accessible station where multiple are installed | ☐ |
☐ Public accommodations: 42 U.S.C. § 12182; new construction and alterations at 42 U.S.C. § 12183; regulations at 28 C.F.R. Part 36 ☐ Public entities: 42 U.S.C. § 12132; regulations at 28 C.F.R. Part 35 ☐ Residential modification requests: 42 U.S.C. § 3604; complaint process at 42 U.S.C. § 3610 ☐ Corridor projects: 23 U.S.C. § 151; design standards at 23 U.S.C. § 109 ☐ Re-check after any restriping, resurfacing, or equipment change
Tool 11 — Price Posting and Metering Audit
☐ 1. What is the permitted pricing unit in this state — per kilowatt-hour, per session, or per minute? ☐ 2. Is the operator exempt from public utility status for reselling to charge vehicles? Cite the authority. ☐ 3. Does the exemption cover submetering and markups? ☐ 4. Is the meter certified under the state's weights and measures program? ☐ 5. Is the price posted before the session begins, in the unit actually charged? ☐ 6. Are tiered rates by power level disclosed clearly? ☐ 7. Are idle fees disclosed, with the grace period stated? ☐ 8. Are session, connection, and network fees disclosed separately? ☐ 9. Is the hold amount disclosed, with the release timeline? ☐ 10. Do subscription terms comply with the state's automatic renewal statute? ☐ 11. Are network coverage, speed, and reliability claims substantiated? See 15 U.S.C. § 45 and Advertising and Marketing Law ☐ 12. Is tax treatment correct — sales tax, utility tax, or neither? ☐ 13. If federally funded, are the price transparency, payment access, connector, uptime, and reporting conditions met?
⚠️ Weights and measures is the enforcement channel for items 4 through 8 — the same agency that regulates gasoline pumps, and it responds far faster than a court.
Tool 12 — Session and Outage Log (Operator)
| Date | Station ID | Sessions | kWh delivered | Failed sessions | Outage start | Outage end | Cause | Resolution | Complaints |
|---|---|---|---|---|---|---|---|---|---|
☐ Retain for at least [period]; these records are the defense to a reliability complaint and the proof of compliance with any funding condition ☐ Track failed sessions separately from outages — the driver experience differs and so does the exposure ☐ Track payment holds placed and released, with timing ☐ Review the complaint log monthly for patterns ☐ Where equipment failure causes damage, preserve the unit and the logs — see Product Liability
Tool 13 — Driver Incident Record
Complete at the station, before leaving.
Date and time: [ ] · Network: [ ] · Station ID: [ ] · Location: [ ]
What the app showed (screenshot): ☐ available ☐ in use ☐ out of service What the station showed (photograph): [ ] Posted price (photograph): [ ] per [unit] · Idle fee disclosed? ☐ Session started? ☐ · Session ID: [ ] · kWh delivered: [ ] Failure mode: ☐ would not start ☐ stopped mid-session ☐ no power delivered ☐ payment declined ☐ connector damaged ☐ blocked ☐ other Amount charged: $[ ] · Hold placed: $[ ] · Hold released? ☐ date [ ] Support contacted: [ ] · Ticket number: [ ] · Response: [ ] Alternative station used: [ ] · Additional cost and delay: [ ]
Then, in order: payment channel dispute → state weights and measures complaint → state consumer protection complaint under 15 U.S.C. § 45 and the state analogue → if federally funded, the administering state agency.
Tool 14 — Authority Quick Reference
Utility jurisdiction: 16 U.S.C. § 824 · § 824d · § 824e · § 824a-3 — retail sales are state business Cases: FERC v. Electric Power Supply Assn., 577 U.S. 260 · Hughes v. Talen Energy Marketing, 578 U.S. 150 PURPA standards: 16 U.S.C. § 2601 · § 2621 (includes charging program standards — consideration is procedural) · § 2622 Corridors and design: 23 U.S.C. § 151 · 23 U.S.C. § 109 Incentives and fleets: 26 U.S.C. § 30C · 26 U.S.C. § 30D · 42 U.S.C. § 13212 · 42 U.S.C. § 17012 Accessibility: 42 U.S.C. § 12182 · § 12183 · § 12132 · 28 C.F.R. Part 36 · 28 C.F.R. Part 35 Housing: 42 U.S.C. § 3604 · 42 U.S.C. § 3610 Consumer and warranty: 15 U.S.C. § 45 · 15 U.S.C. § 2301 · § 2302 · § 2310 Vehicles and equipment: 42 U.S.C. § 7521 · 42 U.S.C. § 7543 · 49 U.S.C. § 30111 · 42 U.S.C. § 6295 State law supplies: right-to-charge statutes · utility-status exemptions and the permitted pricing unit · weights and measures rules · tariffs and demand charges · automatic renewal statutes · unfair and deceptive practices claims. Check the state every time.
Related Documents
- The Outlet That Became Infrastructure: How Electric Vehicle Charging Law Actually Works
- Electric Vehicles and Charging Infrastructure: A Comprehensive Guide to Right-to-Charge Laws, Utility Rules, Siting, and Consumer Protection
- Installing a Charger and Resolving a Charging Dispute: A Practical Checklist
- Energy Law: A Comprehensive Guide to Regulation, Markets, and Project Development
- The Energy and Utilities Toolkit
- Residential Solar and Home Energy: A Comprehensive Guide to Contracts, Financing, Net Metering, and Disputes
- The Residential Solar and Home Energy Contract Toolkit
- Developing a Renewable Energy Project: A Practical Checklist
- Homeowners and Condominium Associations: A Comprehensive Guide to Governance, Assessments, and Enforcement
- Landlord and Tenant Law: A Comprehensive Guide to Leases, Habitability, Deposits, and Eviction
- The Landlord-Tenant and Eviction Defense Toolkit
- Land Use and Zoning Law: A Comprehensive Guide
- Disputing a Utility Bill and Preventing or Reversing a Shutoff: A Practical Checklist
- The Notice Before the Dark: How Utility Shutoffs Are Actually Stopped
- Consumer Protection Law: A Comprehensive Guide to the FDCPA, FCRA, TCPA, and State UDAP Statutes
- The Consumer Protection and Credit Toolkit
- Advertising and Marketing Law: A Comprehensive Guide to Substantiation, Endorsements, and Disclosures
- Fair Housing: A Comprehensive Guide to Protected Classes, Modifications, and Enforcement
- Documenting and Pursuing a Disability Access Complaint: A Practical Checklist
- The Ramp That Was Never Built: How Disability Access Law Actually Works
- Hiring a Contractor and Resolving a Construction Dispute: A Practical Checklist
- Product Liability: A Comprehensive Guide to Defects, Warnings, Causation, and Defenses