Statute · California Civil Code
Cal. Civ. Code § 8814 — Retention Payment
Cal. Civ. Code § 8814
- Type
- Statute
- Source
- California Civil Code
- Jurisdiction
- California
- Date
- 2011-01-01
- Current through
- Nov 2, 2026 (California Legislative Counsel)
(a) If a direct contractor has withheld a retention from one or more subcontractors, the direct contractor shall, within 10 days after receiving all or part of a retention payment, pay to each subcontractor from whom retention has been withheld that subcontractor’s share of the payment.
Citator
Cal. Civ. Code § 8814 — Retention Payment is in force in the current edition of the Code, and nothing recorded condemns it.
(a) If a direct contractor has withheld a retention from one or more subcontractors, the direct contractor shall, within 10 days after receiving all or part of a retention payment, pay to each subcontractor from whom retention has been withheld that subcontractor’s share of the payment.
(b) If a retention received by the direct contractor is specifically designated for a particular subcontractor, the direct contractor shall pay the retention payment to the designated subcontractor, if consistent with the terms of the subcontract.
(c) If a good faith dispute exists between the direct contractor and a subcontractor, the direct contractor may withhold from the retention to the subcontractor an amount not in excess of 150 percent of the estimated value of the disputed amount.