A direct contractor may not enforce a lien unless the contractor records a claim of lien after the contractor completes the direct contract, and before the earlier of the following times:
Citator
Cal. Civ. Code § 8412 — Conditions to Enforcing a Lien is in force in the current edition of the Code, and nothing recorded condemns it.
A direct contractor may not enforce a lien unless the contractor records a claim of lien after the contractor completes the direct contract, and before the earlier of the following times:
(a) Ninety days after completion of the work of improvement.
(b) Sixty days after the owner records a notice of completion or cessation.