Opinion · Supreme Court of the United States

Williamson County Regional Planning Commission v. Hamilton Bank of Johnson City

Williamson County Reg’l Plan. Comm’n v. Hamilton Bank of Johnson City, 473 U.S. 172 (1985)

Type
Opinion
Court
Supreme Court of the United States
Jurisdiction
Federal
Date
1985-06-28
Topic
litigation

holding that a takings claim was not ripe because the developer did not seek a variance | holding that constitutional challenge brought' under 42 U.S.C. § 1983 to. application of zoning ordinance was not ripe until the aggrieved party applied for a variance | holding that federal takings claim is not reviewable in federal court until plaintiff has sought compensation from state and been denied | holding that an as-applied takings claim against a municipality’s enforcement of a zoning ordinance is not ripe until (1 | holding that a takings claim was not ripe because plaintiff had failed to exhaust its state law remedies | holding that takings claims in federal court are not ripe absent exhaus tion when states provide adequate procedures for obtaining just compensation | holding that an inverse condemnation claim is not ripe until landowner has pursued appropriate procedures to obtain just compensation for taking | holding that a taking claim is not ripe until the administrative agency has arrived at a final decision | holding that a takings claim ripens after final determination by the initial decisionmaker | holding that claims for compensation under the Fifth Amendment takings clause are not ripe until (1) the relevant governmental unit has reached a final decision as to what will be done with the property and (2 | holding that the agency must have “arrived at a final, definitive position regarding how it will apply the regulations at issue to the particular land in question.” | holding that a party’s section 1983 takings claim is not ripe “until it has used the procedure [provided by the state] and been denied just compensation” | holding that a party’s section 1983 takings claim is not ripe “until it has used the procedure [provided by the state] and been denied just compensation” | concluding that due process claim under Fourteenth Amendment was not ripe because the requisite variance had not been sought to establish a “final decision,” and utilizing the same rationale in analyzing the ripeness of the takings claim and the due process claim | recognizing that "a property owner has not suffered a violation of the Just Compensation Clause until the owner has unsuccessfully attempted to obtain just compensation . . ." | ruling that “challenges to a government denial are different in kind from a takings claim, and do not bear upon whether the takings claim is ripe for adjudication” | holding that taking claim was not ripe because developer did not seek a variance from the determination of the planning commission to apply recently enacted density requirements reducing the development potential of the land | holding that the plaintiff failed to present a ripe takings claim where it had neither followed the procedure for obtaining a variance nor provided “specific information about the variances it would require” | holding that a takings claim ripens after final determination by the initial decisionmaker | holding that because party seeking relief under the Taking Clause had “not yet obtained a final decision regarding the application of the zoning ordinance ... to its property ... [its] claim [wa]s not ripe.” | holding that a property-related claim is not ripe “until the government entity charged with implementing the regulations has reached a final decision regarding the application of the regulations to the property at issue” | holding that if state provides an adequate procedure for seeking just compensation, property owner cannot claim a violation of Just Compensation Clause until he has used the procedure and been denied just compensation | holding that if state provides an adequate procedure for seeking just compensation, property owner cannot claim a violation of Just Compensation Clause until he has used the procedure and been denied just compensation | holding that a regulatory taking is ripe when “the administrative agency has arrived at a final, definitive position regarding how it will apply the regulations at issue

Citator

Authority status
negative
Cited by
2352 opinions
Negative treatment
2 citing opinions
Distinguished
2 times