Opinion · Supreme Court of the United States
United States v. Utah, Nevada & California Stage Co.
199 U.S. 414
- Type
- Opinion
- Court
- Supreme Court of the United States
- Jurisdiction
- Federal
- Date
- 1905-11-27
- Topic
- general
. Mr. Justice Day, after making the foregoing statement, ■ delivered the opinion of the court. It is the contention of the Government that, under the authority of the Postmaster General to require new or additional mail messengers or transfer service, without additional compensation, the contractor might be required to perform the additional service made necessary by the establishment of the Industrial Building branch under the authority of the act of Congress of March 3, 1893, .27 Stat. 732, authorizing the renting of the building to be used for general post office purposes in the city of New York. The findings of fact establish that this Industrial Building branch was more than three miles distant from the general post office, and was intended to anri did transact nearly all of the business north of Fourteenth street.
Citator
UpLaw has not yet analyzed United States v. Utah, Nevada & California Stage Co.. The absence of a flag is not a finding that it is good law.
- Cited by
- 81 opinions
Headnotes
- Contracts Law — Interpretation The same principles of right and justice that govern contracts between private individuals control the construction and enforcement of contracts between the Government and private parties. 199 U.S. at 420
- Contracts Law — Mail Service Contracts — "New or Additional Service" Clause A contract clause authorizing the Postmaster General to order "new or additional service" of the same character without additional compensation does not extend to vast, unanticipated additional work, such as service necessitated by the establishment of an entirely new postal facility not contemplated by either party at the time of contracting; there is a limit to the service that may be required without additional compensation, lest the Government be empowered to ruin a contractor by wholly unanticipated demands that no caution or prudence could have foreseen. 199 U.S. at 419–420
- Contracts Law — Interpretation Because the phrase "new or additional service" is not one of exact meaning that defines the precise extent of the contractor's obligation, it is subject to a reasonable construction, and in giving it that construction the court must examine the entire contract and consider the relation of the parties and the circumstances under which it was signed. 199 U.S. at 420
- Contracts Law — Misrepresentation in Government Advertisement — Bidder's Reliance Where a Government advertisement for proposals positively and unequivocally states a fact peculiarly within the Government's knowledge, such as the number of stations to be served, the contractor may presume the Government's statement is correct, and a general clause requiring bidders to inform themselves and disclaiming liability for mistakes does not compel an independent investigation of a fact the Government has placed beyond doubt; the contractor is therefore entitled to extra compensation for performing double the specified service. 199 U.S. at 421–422
- Contracts Law — Mail Service Contracts — Scope of Delivery Obligation A mail service contract obligating the contractor to deliver the mail "into the post offices, mail stations and cars" reasonably requires the contractor, without additional compensation, to carry the mails up and down steps at elevated railroad stations, since delivery at the foot of the steps would not be sufficient to place the mail in the cars. 199 U.S. at 422
"The elementary canon of interpretation is, not that particular words may be isolatedly considered, but that the whole contract must be brought into view and interpreted with reference to the nature of the obligations between the parties, and the intention which they have manifested in forming them.Boardmanv.Reed, 6 Pet. 328;Canal Co. v.Hill, 15 Wall. 94."
And, upon the same subject, Mr. Justice Bradley, in the case ofCanal Co. v.Hill, 15 Wall. 94, 99, said:
"We should look carefully to the substance of the original agreement . . . . as contradistinguished from its mere form, in order that we may give it a fair and just construction, and ascertain the substantial intent of the parties, which is the fundamental rule in the construction of all agreements."
We cannot believe it possible that the parties to this contract contemplated the establishment of a new postal departmentPage 424in the city of New York, not then authorized by any act of Congress, which should so greatly increase the service, requiring more than 300,000 miles of additional transfer service and nearly $10,000 of additional expense for ferrying during the time covered in the suit. The Government, in its advertisement, had stated the probable additional annual mileage at 6,718.40 miles. This may be presumed to have been a fair and impartial estimate, made for the benefit of those with whom the Government was about to contract, notwithstanding they were warned that it was not conclusive, There is nothing in the record to show that it was not a reasonable estimate in the light of the facts then known. In this case, after the contract was entered into, this enormous new service, clearly not intended by either of the parties to be rendered, was required. In this instance we think the limit of reasonable requirement under the new and additional service clause was exceeded and the service required cannot be held to be within the terms of the contract. We find no error in the Court of Claims reaching this conclusion.
2. The second question involved is as to the right of the contractor to recover because the Government's advertisement for proposals, instead of stating the number of elevated stations to be served at four, which was, in fact, the number, gave the number of stations at two, thus doubling the number of trips necessary. It is true that the advertisement required the bidders to inform themselves as to the facts, and stated that additional compensation would not be allowed for mistakes; but, in the present instance, the Government in its advertisement had positively stated the number of stations at two. The contractor had a right to presume that the Government knew how many stations were to be served; it was a fact peculiarly within the knowledge of the Government agents and upon which, in the advertisement, it spoke with certainty. We do not think, when the statement was thus unequivocal, and the document was prepared for the guidance of bidders for Government service, that the general statement that the contractor must investigatePage 425for himself, and of non-responsibility for mistakes, would require an independent investigation of a fact which the Government had left in no doubt. We think the Court of Claims correctly allowed this item.
3. As to the compensation for the so-called "foot service," for carrying the mails up and down the steps at the elevated railroad stations, the delivery of the mail at the foot of the steps would not have been sufficient, and the contractor agreed to deliver the mail into the post offices, mail stations and cars. The statement of facts shows that the preceding contractor had delivered the mail on the platform of the stations at the door of the cars. We think the contract was not exclusively for wagon service, but, reasonably construed, required the delivery of the mail into the elevated stations in such wise as to be placed in the cars, and consequently required it to be carried upstairs without extra allowance of pay. We find no error in disallowing this claim for extra compensation.
The judgment of the Court of Claims isAffirmed.