Mr. Justice McKenna delivered the opinion of the .court. April 14,1919, the Court of Claims rendered a judgment against the United States in favor of L. P. & J. A.

Citator

UpLaw has not yet analyzed United States v. Smith. The absence of a flag is not a finding that it is good law.

Cited by
54 opinions

Headnotes

  1. Federal Government Contracts — Extra Work Outside Contract Specifications Where a government contract for channel excavation specifies the material to be removed as clay, sand, gravel, and boulders in unknown proportions, the excavation of a materially different substance (there, a limestone bed) not covered by the contract is work outside the contract, entitling the contractors to recover its cost notwithstanding the officer's contrary classification of the material with those named in the specifications. 256 U.S. at 15
  2. Federal Government Contracts — Finality and Instructions Clauses — Inapplicability to Uncontracted Work Contract clauses making the engineer officer's decisions as to the quality and quantity of work final, requiring the contractors to observe his instructions, and barring claims for modifications not agreed to or expressly required in writing do not bar recovery for work outside the contract, where the officer arbitrarily classified uncontracted material as within the specifications, ignored the contractors' protests and request for a new price, and compelled performance under threats of default and recoupment. 256 U.S. at 15
  3. Federal Government Contracts — Constructive Coercion — Futility of Appeal Where the conduct of the engineer officer in charge, though perhaps without malice or bad faith, was such that soliciting an appeal or any change by him would be useless and left only submission with its consequences, the contractors are not required to invoke the contractual appeal procedure before recovering for work exacted outside the contract. 256 U.S. at 15
  4. Federal Government Contracts — Damages — Delay by Government Officer Contractors with the United States are entitled to recover for loss caused by delays of the engineer in charge in locating the places where they were to work. 256 U.S. at 17