Opinion · Supreme Court of the United States

United States v. Smith

94 U.S. 214

Type
Opinion
Court
Supreme Court of the United States
Jurisdiction
Federal
Date
1877-03-13
Topic
general

Me. Chief Justice Waite delivered the opinion of the court. The only questions presented in this case relate to the liability of the United States for damages growing out of the suspension of the work under the contract sued upon. In effect, the contract bound Smith to furnish the materials and erect the buildings, the labor being performed by the soldiers at the fort, except to the extent that skilled workmen were necessary. There was no time specified within Avhich the work must be done, neither was there any poAver reserved by the United States to direct its suspension.

Citator

UpLaw has not yet analyzed United States v. Smith. The absence of a flag is not a finding that it is good law.

Cited by
109 opinions

Headnotes

  1. Contracts Law — Implied Time for Performance Where a contract specifies no time for performance and reserves no power in the United States to direct its suspension, the law implies that the work must be done within a reasonable time and that the United States will not unnecessarily interfere to prevent it.
  2. Contracts Law — Liability of the United States for Interference The United States is liable for damages resulting from an improper interference with the work of a contractor, and the principles governing inquiries into the conduct of individuals with respect to their contracts apply equally where the United States is a party. Clark's Case, 6 Wall. 546; Smoot's Case, 15 Wall. 47
  3. Contracts Law — Damages Where the United States stops work by its order and refuses the contractor's request to be released unless permitted to proceed, the interference is improper as between individuals, and the United States is liable for the loss necessarily consequent upon the suspension.
  4. Remedies — Measure of Recovery Against the United States Damages are measured by the sum necessary to place the contractor in the same condition he would have been in had he been allowed to proceed without interference, excluding any loss or injury to materials that he might have prevented by the exercise of reasonable care and prudence.
  5. General — Court of Claims — Conclusiveness of Findings of Fact Under the rules governing appeals from the Court of Claims, that court's finding of facts established by the evidence is in the nature of a special verdict and is conclusive on appeal unless impeached for some error of law appearing in the record. Rule 1, § 2
  6. General — Court of Claims — Limits on Recovery The United States can be required to compensate a contractor for damages actually sustained by reason of their default in performing their undertakings to him, but more than compensation for damages actually sustained can never be awarded against the United States in the Court of Claims.
  7. General — Practice — Specification of the Elements of Damages No rule of law or practice requires a court or jury to specify the elements of the calculation by which it arrives at its final result in estimating damages; a party may properly request a finding as to whether a particular item of claim or damage was included in the estimate and in what amount, but not the mere items of calculation for the purpose of testing the sufficiency of the evidence.
  8. General — Court of Claims — Role in Estimating Damages In the estimation of damages the Court of Claims occupies the position of a jury under like circumstances: damages must be proved, the court may no more guess than a jury, but, like a jury, it must make its estimates from the proofs submitted, and the result of the best judgment of the triers is all that the parties have a right to expect.
Me. Chief Justice Waite

delivered the opinion of the court.

The only questions presented in this case relate to the liability of the United States for damages growing out of the suspension of the work under the contract sued upon. In effect, the contract bound Smith to furnish the materials and erect the buildings, the labor being performed by the soldiers at the fort, except to the extent that skilled workmen were necessary. There was no time specified within Avhich the work must be done, neither was there any poAver reserved by the United States to direct its suspension. Under such circumstances, the law implies that the Avork should be done within a reasonable time, and that the United States Avould not unnecessarily interfere to prevent,this.

In Clark’s Case, 6 Wall. 546, it was decided that the United States were liable for damages resulting from an improper interference with the work of a contractor; and in Smoot’s Case, 15 id. 47, that the principles Avhich govern inquiries as to the conduct of individuals, in respect to their contracts, are equally applicable Avhere the United States are a party. The same rules Avere applied in the case of the Amoskeag Company, 17 id. 592. Here the work was stopped by order of the United States. Smith asked to be released from his contract, unless he could go on. This was refused until the expiration of sixty *218 days, when he was allowed to resume. As between individuals, certainly, this would be considered an improper interference, and damages would be awarded to the extent of the loss which was the necessary consequence of the suspension. The United States must answer according to the same' rule. In this respect, we cannot consider this case different in principle from that of Clark, supra.

The Court of Claims has found the amount of the damages to have been $5,000 ; that is .to say, that sum, in its opinion, from the evidence before it, was necessary to place Smith in the same condition he would have been in if he had been allowed to proceed without interference, and not allowing any thing for loss or injury to his materials, which he might have prevented by the exercise of reasonable care and prudence.

This rule of damages, as an abstract proposition, is clearly right. Unless, therefore, there appears in the record some error growing out of the estimation of the amount, the judgment below should be affirmed.

• By our rules in reference to appeals from the Court of Claims, rule 1, sect. 2, that court sends here its finding of facts as “ established by the evidence, in the nature of a special verdict.” The evidence is not sent up. This finding is conclusive, unless impeached for some error in law appearing in the record. Here, in effect, the error complained of is, that the court refused to state the items of its account of damages. This we have not required; and while, under the practice we have established, liberal provision should be made for the review of questions of law, it seems to us that in this case the claim of the United States goes beyond any thing we ought to grant. The court might with propriety have been asked to state in a finding whether a particular item of claim or of damage was included in its estimate, and, if so, what amount. To such a finding exception might in proper form be taken, and then we could be called upon to decide whether such an item was legally the subject of compensation in an action for damages. The United States can be required to make compensation to a contractor for damages which he has actually sustained by their default in the performance of their undertakings to him; but this is the extent of their liability in the Court of Claims. More than *219 compensation for damages actually sustained can never be swarded against the United States.

In this case the United States asked the court to find (1) the amount of damage done to the building ,on account of exposure to the winter storms in its unfinished condition; (2) the amount resulting from the retention of the skilled labor, &c.; and (8) tbe deterioration in tbe value of materials. All these were legitimate subjects of inquiry by tbe court in making up its final estimate; but we know of no rule of law or practice which requires a court or jury to specify tbe elements of the calculation by which it arrives at its final result. In tbis case tbe court was not asked to say whether it included tbis or that supposed element of compensation in its judgment; but tbe only effort seems to have been to ascertain tbe items of calculation so as to determine whether tbe proof supported them. Tbe whole contest evidently was as to tbe sufficiency of tbe evidence, not as to tbe liability of the United States if tbe facts as claimed were established by tbe proof.

In tbe estimation of damages tbe Court of Claims occupies tbe position of a jury under like circumstances. Damages must be proved. Tbe court is not permitted to guess any more than a jury, but, like a jury, it must make its estimates from tbe proofs submitted. Tbe result of tbe best judgment of tbe triers is all that tbe parties have any right to expect.

As tbe record presents tbe case, we see no error in tbe court below. Judgment affirmed.