Opinion · Supreme Court of the United States

United States v. Blair Ex Rel. Roanoke Marble & Granite Co.

321 U.S. 730

Type
Opinion
Court
Supreme Court of the United States
Jurisdiction
Federal
Date
1944-05-08
Topic
general

How later courts describe this case

  • holding that parties could not choose to disregard similar provisions, “accumulate large damages and then sue for recovery”; noting that similar administrative procedures were designed to “adjudicate disputes and to avoid large damage claims”
  • holding that a subcontractor cannot sue the government directly on a government contract because of the absence of an agreement between the government and subcontractor, but the prime contractor may sue to recover a subcontractors' costs
  • distinguishing Department of Transp. v. Claussen Paving Co., 246 Ga. 807, 273 S.E.2d 161, 164 (1980
  • allowing contractor to assert subcontractor claims because of implied “right to recover extra costs and services .. . regardless of whether such costs were incurred or such services were performed personally or through a subcontractor”
  • “[the general contractor’s] contract *** is thus sufficient to sustain an action for extra costs wrongfully demanded under [the] contract”
  • government contractor may assert against the government pass-through damages of subcontractor

Citator

UpLaw has not yet analyzed United States v. Blair Ex Rel. Roanoke Marble & Granite Co.. The absence of a flag is not a finding that it is good law.

Authority status
pending
Cited by
226 opinions

Headnotes

  1. Federal Government Contracts — Implied Duties A Government construction contract that obligates each contractor to complete its work within a stipulated time imposes no duty on the Government to take affirmative steps to prevent one contractor from unreasonably delaying or interfering with another contractor's attempt to finish ahead of schedule; the Government is therefore not liable in damages for such delay. This is so even where the contractor subsequently gives notice of his intention to complete the work early, since such notice cannot create a new obligation requiring the Government to compel accelerated performance from another contractor. 321 U.S. at 733
  2. Federal Government Contracts — Disputes Clause — Exhaustion of Administrative Remedies Under a contract clause providing that all disputes concerning questions arising under the contract shall be decided by the contracting officer subject to written appeal to the head of the department, whose decision shall be final and conclusive, a contractor must exhaust the prescribed appeal procedure before seeking judicial relief. Where the appeal procedure afforded a complete and reasonable means of correcting the alleged abuses and nothing shows that an appeal to the departmental head would have been futile or prejudicial, the contractor cannot disregard the procedure, accumulate damages, and recover in court—even if the actions of subordinate Government officers are assumed to have been unauthorized, unreasonable, and arbitrary, or so grossly erroneous as to imply bad faith. 321 U.S. at 735
  3. Federal Government Contracts — Recovery for Extra Costs — Subcontractors A prime contractor who is the only person legally bound to perform the contract with the Government may recover from the Government extra costs and services wrongfully demanded under that contract, regardless of whether such costs were incurred or services performed personally or through a subcontractor; the subcontractor's lack of privity with the Government does not bar the prime contractor's suit on the contract for such amounts. 321 U.S. at 737