Opinion · Supreme Court of the United States

United States v. Atlantic Dredging Co.

253 U.S. 1

Type
Opinion
Court
Supreme Court of the United States
Jurisdiction
Federal
Date
1920-04-26
Topic
general

How later courts describe this case

  • holding “where it is stated that the direction to contractors to visit the site and inform themselves of the actual conditions of a proposed undertaking will not relieve from defects in the plans and specifications”
  • noting a bidder is entitled to rely on the accuracy of information contained in the solicitation; it need not conduct its on explorations or surveys
  • applying Washington law to a similar government contract

Citator

UpLaw has not yet analyzed United States v. Atlantic Dredging Co.. The absence of a flag is not a finding that it is good law.

Cited by
140 opinions

Headnotes

  1. Contracts Law — Misrepresentation — Government Contracts Where the government's specifications state a belief that the material to be removed is of a certain character and expressly decline to guarantee the accuracy of that description, requiring bidders to examine the work and decide for themselves, no warranty arises from the mere expression of belief or from the disclaimer-standing alone, because the inquiry does not end there: the government's reference to maps of test borings, its representation that the general information thereby given is trustworthy, and its approval of the contractor's plant—efficient only for the lighter materials described—together amount to a confirmation of the belief that justifies the contractor in relying upon it. 253 U.S. at 9
  2. Contracts Law — Misrepresentation — Material Nondisclosure Where the government supplied specifications describing the material to be dredged and referred bidders to maps showing the results of test borings, but the maps omitted certain borings that had disclosed material more difficult to excavate than that shown, the representations were deceptive, and a contractor that relied upon them and whose reliance was confirmed by the government's approval of its plant was entitled to recover the difference between the cost of the excavation done and the amount received under the contract. 253 U.S. at 9
  3. Contracts Law — Waiver A contractor does not lose its right to stop work and recover for misrepresentation by continuing to perform, where at the time it continued it did not know of the manner in which the test borings had been made or that the government's expressed belief was unjustified; the right is lost only when the contractor, with knowledge of the deception, elects to proceed, and the contractor's attempt to struggle on against difficult conditions with an inefficient plant is not chargeable against it as such an election. 253 U.S. at 11
  4. Contracts Law — Nature of Action — Supplement Contract A contractor's action upon such misrepresentation sounds in contract, not in tort; and the right of recovery is not defeated by the contractor's entry into a supplementary contract, made after the heavier materials were encountered but before the contractor learned of the results of the test borings, where the representation of the character of the material was in the nature of a warranty and the judgment is simply compensatory of the cost of work of which the government received the benefit. 253 U.S. at 12