Opinion · Supreme Court of the United States
Trainor Co. v. Aetna Casualty & Surety Co.
54 S. Ct. 1
- Type
- Opinion
- Court
- Supreme Court of the United States
- Jurisdiction
- Federal
- Date
- 1933-11-06
- Topic
- general
citing, inter alia, Kidd v. McCormick, 83 N.Y. 391 (1881) for the proposition that “The measure of damage on a bond guaranteeing completion is the cost of completion,” and adding, “it seems to us that the... decisions, ... cited above, are plainly right”
Citator
- Cited by
- 32 opinions
TRAINOR CO.v. AETNA CASUALTY CO.,290 U.S. 47(1933)
54 S.Ct. 1
TRAINOR CO.v. AETNA CASUALTY SURETY CO.
CERTIORARI TO THE CIRCUIT COURT OF APPEALS FOR THE THIRD CIRCUIT.
No. 13.
Argued October 12, 1933.
Decided November 6, 1933.
CERTIORARI,289 U.S. 718, to review a judgment affirming a
judgment of the District Court, 49 F.2d 769, awarding nominal
damages in a suit on a guaranty bond.
There is a well-established distinction between an affirmative covenant for a specific thing and one of indemnity against damage by reason of the non-performance of the thing specified.Purdyv.Massey,306 Pa. 288;Weightmanv.Union Trust Co.,208 Pa. 449; 3 Sutherland, Damages, 4th ed., § 765.
The basic question in this case is whether or not the bond in suit is one of guaranty or indemnity.
To the same effect areWheelerv.Equitable Trust Co.,206 Pa. 428;Equitable Trust Co. v.National Surety Co.,214 Pa. 159;Weightmanv.Union Trust Co.,208 Pa. 449;Union TrustCo. v.Citizens Trust Co.,185 Pa. 217;Wickerv.Hoppock, 6 Wall. 94;Cudabackv.Hay,Page 49134 F. 120, s.c. 139 F. 369;Belloniv.Freeborn,63 N.Y. 383;Kiddv.McCormick,83 N.Y. 391;United Real Estate Co. v.McDonald,140 Mo. 605. Distinguishing:Schwartz Co. v.Aimwell Co.,227 N.Y. 184.
Whether the case be regarded as presenting a question of suretyship or of the measure of damages, the decisions of the state court of last resort should be followed by the federal courts. No federal question is involved. The law invoked is of local character.Community Bldg. v.Maryland Casualty Co.,8 F.2d 678;Sturtevant Co. v.Fidelity Deposit Co., 285 F. 367;Mullins Lumber Co. v.Williamson Brown Co., 255 F. 645; Hughes, Federal Practice, Jurisdiction Procedure (1931), vol. 6, § 3735, p. 375;McLainv.Provident SavingLife Assur. Society110 F. 80, 91;Warren Countyv.Southern Surety Co.,34 F.2d 168,170.
This is not a case where a series of decisions have established a federal rule, opposed to a state rule, to which the federal courts feel bound by the principle ofstare decisis.Mr. Joseph W. Henderson, with whomMr. Thomas F. Mountwas on the brief, for respondent.
There is no substantial difference between the measure of damages recoverable by a mortgagee-obligee for the breach of a bond giving an absolute guarantee of completion and for the breach of a bond indemnifying against loss for failure to complete.Purdyv.Massey,306 Pa. 288,297.
If the contractor defaults and the building is not fully erected, the legal interest of the mortgagee which is adversely affected and which the law will be compelled to protect, and as to which compensation may be claimed, is the loss to the mortgagee of his security by reason of the contractor's default. Thus the mortgagee-obligee is entitled to recover as damages the amount by which thePage 50security has been depleted by the failure of the contractor to perform, or so much of the difference between the value of the completed and uncompleted operation as would be necessary, together with the value of the property in the condition in which it is left by the contractor, to pay the mortgage debt and the interest thereon.Province Securities Corp. v.MarylandCasualty Co.,269 Mass. 75. Distinguishing:Purdyv.Massey,306 Pa. 288;Weightmanv.Union Trust Co.,208 Pa. 449;Wickerv.Hoppock, 6 Wall. 94;Hayv.Cudaback, 139 F. 369;Belloniv.Freeborn,63 N.Y. 383;Kiddv.McCormick,83 N.Y. 391. Cf.Schwartz Co. v.Aimwell Co.,227 N.Y. 184.
The measure of damages is limited to the difference between the value of the property in the condition in which it existed at default and the amount of principal and interest due on the mortgage and all prior liens.Province Securities Corp. v.Maryland Casualty Co.,269 Mass. 75;Norway Plains SavingsBankv.Moors,134 Mass. 129;Longfellowv.McGregor,61 Minn. 494;German American T. T. Co. v.Citizens T. S.Co.,190 Pa. 247;Purdyv.Massey, dissenting opinion,306 Pa. 288,297. Distinguishing:Wickerv.Hoppock, 6 Wall. 94.
Federal courts exercise an independent judgment, irrespective of the decisions of the local state courts, in matters of general jurisprudence and commercial law.Swiftv.Tyson, 16 Pet. 1;Butzv.Muscatine, 8 Wall. 575, 582;Baltimore Ohio R.Co. v.Baugh,149 U.S. 368,371;Black White Co. v.BrownYellow Co.,276 U.S. 518. Cf. the dissenting opinion inKuhnv.Fairmont Coal Co.,215 U.S. 349.
That the doctrine ofSwiftv.Tyson, supra, is recognized and applied by all of the Circuit Courts of Appeals is shown by the following decisions:Searsv.Greater N.Y. DevelopmentCo.,51 F.2d 46;Colev.Pennsylvania R. Co.,43 F.2d 953;Trainor Co. v.Aetna CasualtyPage 51Surety Co.,62 F.2d 487;Longv.Monarch Accident Ins.Co.,30 F.2d 929;Home Insurance Co. v.Currie,54 F.2d 203;Farmers' Bankv.Hayes,58 F.2d 34;Aetna LifeIns. Co. v.Roewe,38 F.2d 393;Odegardv.GeneralCasualty Surety Co.,44 F.2d 31;Community Bldg. Co. v.Maryland Casualty Co.,8 F.2d 678;Bu-Vi-Bar PetroleumCorp. v.Krow,40 F.2d 488.
Questions of suretyship are matters of general jurisprudence, and those relating to the measure of damages are also.
The use of completion bonds throughout the Nation requires a national uniform law and, therefore, questions pertaining thereto are matters of general jurisprudence.
Irrespective of whether the question of measure of damages in this case be considered a matter of general jurisprudence, the federal courts below were entitled to exercise an independent judgment concerning it.Burgessv.Seligman,107 U.S. 20;Kuhnv.Fairmont Coal Co.,215 U.S. 349;Concordia InsuranceCo. v.School District,282 U.S. 545;Putnam MemorialHospitalv.Allen,34 F.2d 927;Hartv.Adair, 244 F. 897;Dernbergerv.Baltimore Ohio R. Co., 243 F. 21.
Suit was brought in a federal district court for the eastern district of Pennsylvania to recover damages for a breach of the bond. A jury was waived; and after a hearing, the trial judge found that on August 13, 1928, the date fixed for the completion of the buildings and improvements, twenty-four of the houses had been completed and twenty-eight had not been fully completed. The value of the lots with the twenty-eight uncompleted houses, as of the date last mentioned, was $6,700 each, an amount slightly in excess of the sum of petitioner's mortgage on each and of all prior liens. Completed, they would, on that date, have been worth $7,950 each. It is not disputed that at the time of the breach of the bond petitioner, under the terms of the mortgages, was powerless to protect itself by foreclosure; and the court found that thereafter the value of real estate, generally and in the locality, had steadily declined. On January 25, 1930, the first mortgage was foreclosed and the property bought in for the sum of $50, thus wiping out the second mortgage and the equity of petitioner therein. Petitioner hasPage 53received on account of the indebtedness of $28,000 the sum of $13,026.02 only, leaving $14,973.98 still owing on the principal.
Upon these facts the trial court held that while theownerof property, in case of a default after partial performance of a building contract, would be entitled to recover from the surety the difference between the value of the property with the uncompleted buildings and its value with the buildings completed, the rule is otherwise in the case of amortgagee-obligee. Following this view, that court concluded that the measure of damages in the instant case "is so much of the difference between the value of the property as of August 13, 1928, with the houses uncompleted, and the value it would have had on that date had the houses been completed as would have been necessary to pay the plaintiff's mortgage debt as well as all prior liens. Since the value of the property as of August 13, 1928, was more than the sum of the plaintiff's mortgage and prior liens, the plaintiff is not entitled to any substantial damages." The court, therefore, awarded nominal damages only. 49 F.2d 769. This judgment the circuit court of appeals affirmed.62 F.2d 487. With that conclusion we are unable to agree.
It is very clear that the settled rule in Pennsylvania is to the contrary. InPurdyv.Massey,306 Pa. 288;159 A. 545, where prior cases are reviewed, the court held that where there is an absolute undertaking to erect and complete a building, the surety in case of default is bound to take the place of the principal and erect the building, and the cost of doing that which should have been done is the measure of damages for which the surety is liable, not exceeding the amount of the bond. There the owner of a first purchase-money mortgage had subordinated her security to another mortgage in consideration of the giving of a bond in all substantial respects like the one here under consideration. The building provided for was notPage 54erected, and the mortgagee brought suit against the surety on the bond. The court held that the bond was one of guaranty and awarded as damages the full cost of completion, such cost not exceeding the amount due on the mortgage. The applicable rule is thus stated (p. 295):
"In fixing compensation for damage resulting from breach of a contract the general rule is that the injured party should be placed in the same position as if there had been no breach. The object of the law is to place such party in as good position as if the contract had been kept. In the instant case the bond guaranteed the completion of the building; if there had not been a breach of the obligation of the bond, the building would have been erected. Since this was not done, the plaintiff can only be put in as good position as if the contract had been carried out by giving her the cost of construction, not exceeding, of course, the amount of the bond. The measure of damage on a bond guaranteeing completion is the cost of completion: . . . And in a case such as this, where the work was never begun, this cost will be the whole cost of construction."
See alsoMechanics Trust Co. v.Fid. Cas. Co.,304 Pa. 526,533,et seq.;156 A. 146. A like rule obtains in other states.United Real Estate Co. v.McDonald,140 Mo. 605,612;41 S.W. 913;Kiddv.McCormick,83 N.Y. 391. CompareWickerv.Hoppock, 6 Wall. 94, 99.
The circuit court of appeals held that the Pennsylvania decisions merely declared the common law of that state with regard to suretyship, and, since that law is derived from the principles of general jurisprudence common to all the states, a federal court in determining what it is might exercise an independent judgment. We do not deem it necessary to discuss the principle enunciated or to decide whether the Pennsylvania decisions come within it. It is enough to say that even where the principle applies, "for the sake of harmony and to avoid confusion, the FederalPage 55courts will lean towards an agreement of views with the State courts if the question seems to them balanced with doubt."Burgessv.Seligman,107 U.S. 20,33-34. And seeSimv.Edenborn,242 U.S. 131,135, where the authorities are collected;Community Bldg. Co. v.Maryland Casualty Co.,8 F.2d 678,680. In the present case it would not be going far enough to say merely that the question is "balanced with doubt," for it seems to us that the Pennsylvania decisions, and those of the other states cited above, are plainly right. CompareMessengerv.Anderson,225 U.S. 436,444.
The petitioner here, not being willing to accept a third mortgage on the unimproved land to secure its debt, required the added security which would be afforded by completed improvements. These improvements the building company agreed to make within a definitely fixed time, and for the performance of that undertaking respondent, for a valuable consideration, stood sponsor. Plainly the obligation of the bond was one of guaranty and not indemnity, and could be fulfilled only by the erection of the buildings or payment of the penalty in case of default. It is no answer to say that the value of the property immediately after the default exceeded the sum of the mortgage together with all prior liens. Petitioner was then without remedy against the property because its mortgage was not in default. It was, therefore, obliged to sit by and await the action of others over which it had no control. In the meantime, the uncompleted buildings necessarily lay unrented, subject to expense in the way of taxes, insurance, accumulating interest, etc., deteriorating in quality and steadily declining in value. Petitioner is entitled to be put in as good position in respect of its debt as it would have occupied if the buildings had been completed in accordance with the terms of the undertaking; and this can be done here only by giving it the amount of the difference between thePage 56value of the unfinished buildings and their value as it would have been if completed in accordance with the agreement — seeKiddv.McCormick, supra, p. 398 — but exceeding neither the amount due on its debt nor the amount of the bond.
It appears from the findings that this difference would be about $26,000, while the amount now due petitioner is $14,973.98, together with interest thereon from August 13, 1928. It follows that the judgments of the courts below must be reversed and the cause remanded to the district court with directions to enter judgment for the last named sum.Reversed.