Opinion · Supreme Court of the United States

Sweeney v. United States

Sweeney v. United States, 109 U.S. 618 (1884)

Type
Opinion
Court
Supreme Court of the United States
Jurisdiction
Federal
Date
1884-01-07
Topic
general

Mr. Chief Justice "Waite delivered the opinion of the court. This judgment is affirmed on the authority of Kihlberg v. United States, 91 U. S. 398.

Citator

UpLaw has not yet analyzed Sweeney v. United States. The absence of a flag is not a finding that it is good law.

Authority status
pending
Cited by
108 opinions

Headnotes

  1. Contracts Law — Condition Precedent — Engineer's Certificate Where a contract with the United States for construction work provides that payment shall not be made until an agent designated by the United States certifies, after inspection, that the work is in all respects as contracted for, the agent's certificate is a condition precedent to payment; and this is so where the designated agent refuses to give the certificate and there is no fraud, no such gross mistake as would necessarily imply bad faith, and no failure to exercise honest judgment on the agent's part. 109 U.S. 618 (citing Kihlberg v. United States, 97 U.S. 398)
  2. Contracts Law — Government Contracts — Conclusiveness of Agent's Determination The ruling that a designated agent's determination, made honestly and without fraud or such gross mistake as would necessarily imply bad faith, is binding on the parties is adhered to and applied. Kihlberg v. United States, 97 U.S. 398, adhered to in 109 U.S. 618
  3. Contracts Law — Government Contracts — Right to Cure A contractor who has been notified of the defective character of his material before incorporating it into the work, and who completes the work after being informed it will not be accepted, is not entitled to notice of the government's intent to tear down the structure or to a further opportunity to correct the defects he was already told of. 109 U.S. 618