Opinion · Supreme Court of the United States
Sweeney v. United States
Sweeney v. United States, 3 S. Ct. 344 (1884)
- Type
- Opinion
- Court
- Supreme Court of the United States
- Jurisdiction
- Federal
- Date
- 1884-01-07
- Topic
- general
Mr. Chief Justice "Waite delivered the opinion of the court. This judgment is affirmed on the authority of Kihlberg v. United States, 91 U. S. 398.
Citator
- Cited by
- 81 opinions
SWEENEY v. UNITED STATES,109 U.S. 618(1883)
3 S.Ct. 344
SWEENEYv. UNITED STATES.
APPEAL FROM THE COURT OF CLAIMS.
Submitted November 13th, 1883.
Decided December 17th, 1883.
The plaintiff contracted to construct the wall by a written agreement, of which the following were the material parts:
First. That the said A.W. Sweeney shall build a wall of brick at the National Military Cemetery at Fort Harrison, Virginia, according to the plans and specifications attached to this contract. . . .
Fourth. It is agreed that from time to time, and when completed, the said wall shall be inspected by an officer of the U.S. Army, or by a civil engineer or other agent, to be designated by the party of the first part, and after such officer, or civil engineer, or other agent, shall have certified that it is in all respects as contracted for, it shall be received and become the property of the United States. . . .
Sixth. It is agreed that upon inspection and report of materials furnished, or work done, during the performance of this contract, payment in part may be made to the contractor, said payment in no case to exceed 80 per cent. of the estimated value of the material and work actually furnished.
The following were the material findings of the court ofPage 619claims in regard to the work for which payment was demanded in this action.
XIII. After the completion of the wall as aforesaid the said Chenoweth, under orders, inspected the same, and made the following report:
RICHMOND, VA.,Oct. 22d 1874. Col. A.F. ROCKWELL,A.Q.M., U.S.A.:
SIR: I have the honor to report a visit this day, with Capt. T.J. Eckerson, to the Fort Harrison National Cemetery.
Mr. Sweeney, contractor for the enclosing wall, has entirely completed the work, without paying any attention whatever to the instructions given him relative to the material to be used, nor has he paid any attention to the order of the quartermaster-general with regard to the gate-posts.
The condemned material has been used, and I consider the workmanship is very unsatisfactory.
Very respectfully, your obedient servant, G.D. CHENOWETH,Civil Eng'r.
XIV. In consequence of this report the wall so constructed was taken down by order of the quartermaster-general, and a new wall, made of other material, was constructed in its place. The cost of the new wall was $7,829.03. It was not shown that the claimant had any notice of the intent to take down the wall constructed by him, or that any further opportunity was offered him to correct or remedy any defects or errors therein, or that there was any other attempt to complete the wall in accordance with the terms of the contract.
XV. It was not shown that there was any fraud, or any such gross mistake as would necessarily imply bad faith, or any failure to exercise an honest judgment on the part of the said Chenoweth in making the inspections hereinbefore referred to or set forth.
XVI. No officer of the army of the United States, nor civil engineer, nor other agent of the United States, has ever certified that the said wall constructed by the claimant was in all respects as contracted for, or in any respect as contracted for, other than as shown by the said reports of the said Chenoweth.Page 620
XVII. The claimant then offered evidence tending to show that the wall as completed by him was in compliance with the requirements of the contract; but the court refused to hear such evidence, or to make any finding on that subject.