Opinion · Supreme Court of the United States

Priebe & Sons, Inc. v. United States

68 S. Ct. 123

Type
Opinion
Court
Supreme Court of the United States
Jurisdiction
Federal
Date
1947-11-17
Topic
general

observing that “[tjoday the law does not look with disfavor upon ‘liquidated damages’ provisions in contracts! ] [wjhen they are fair and reasonable attempts to fix just compensation for anticipated loss caused by breach” | observing that “[t]oday the law does not look with disfavor upon ‘liquidated damages’ provisions in contracts! ][w]hen they are fair and reasonable attempts to fix just compensation for anticipated loss caused by breach” | describing contractual penalties as oppressive and unjust based on common law of contracts, not constitutional principles | describing contractual penalties as oppressive and unjust based on common law of contracts, not constitutional principles | describing contractual penalties as oppressive and unjust based on common law of contracts, not constitutional principles | “It is customary, where Congress has not adopted a different standard, to apply to the construction of government contracts the principles of general contract law” | Liquidated damages provisions "serve a particularly useful function when damages are uncertain in nature or amount or are unmeasurable[.]” | “It is customary ... to apply to the construction of government contracts the principles of general contract law” | “It is customary, where Congress has not adopted a different standard, to apply to the construction of government contracts the principles of general contract law.” | liquidated damages are enforceable “[w]hen they are fair and reasonable attempts to fix just compensation for anticipated loss caused by breach of contract” | "[We] apply to the construction of government contracts the principles of general contract law." | “These provisions are to be judged as of the time of making the contract.” (citing Bethlehem Steel, 205 U.S. at 121) | overruled by United States v. Detroit, 355 U.S. 466, 78 S.Ct. 474, 2 L.Ed.2d 424 (1958) | “Suits to enforce contracts with federal agencies are governed by federal common law . . . .” | “It is customary, where Congress has not adopted a different standard, to apply to the construction of government contracts the principles of general contract law.” | overruled by United States v. Detroit, 355 U.S. 466, 78 S.Ct. 474, 2 L.Ed.2d 424 (1958) | “[T]he fact that the damages suffered are shown to be less than the damages contracted for is not fatal. These provisions are to be judged as of the time of making the contract.” | "[We] apply to the construction of government contracts the principles of general contract law." | "liquidated damages" provision that was inserted in a contract in order to give government contractor incentive to meet contractual deadlines was a nonenforceable penalty when the liquidated damages were not related to, the government's actual damage | “It is well-established that government contracts are governed by federal common law.” | “It is well-established that government contracts are governed by federal common law.” | applying general principles of contract law to a government contract | overruled by United States v. Detroit, 355 U.S. 466 [] (1958) | breach of contract with the Federal Surplus Commodities Corp.

Citator

Cited by
125 opinions