Opinion · Supreme Court of the United States
Moseley v. Electronic & Missile Facilities, Inc.
10 L. Ed. 2d 818
- Type
- Opinion
- Court
- Supreme Court of the United States
- Jurisdiction
- Federal
- Date
- 1963-06-17
- Topic
- general
holding that the Court does not reach the issue of arbitrability because the issue of fraud needed to be reached before arbitrability. | holding that when the petitioner “attacked not only the subcontracts, but also the arbitration clauses contained therein, as having been procured through fraud,” the district court must determine whether there was fraud in the inducement of the arbitration clause | if there is a substantial allegation of fraudulent inducement that would negate the existence of an agreement to arbitrate, “it seems clear that the issue of fraud should first be adjudicated before the rights of the parties . . . can be determined”
Citator
- Cited by
- 52 opinions
delivered the opinion of the Court.
The primary issue in this case is whether a claim under the Miller Act, 40 U. S. C. §§ 270a-270d, as amended, based upon arbitration clauses in two subcontracts providing for arbitration of any dispüte arising thereunder, is enforceable under the provisions of the United States Arbitration Act. 9 U. S. C. §§ 1, 2 and 3. The institution of this suit was directed toward the recovery of compensation alleged to be due under two subcontracts between the petitioner, a plumbing and heating contractor, and the respondent Electronic & Missile Facilities, Inc., who was the prime contractor under a contract with the United States Corps of Engineers, Savannah District, covering certain Nike Hercules missile installations at Robins Air Force Base Defense Area and Turner Air Force Base Defense' Area, both of which are located in the State of Georgia. The subcontracts provided for arbitration in New York, and, disputes having arisen thereunder, the respondent filed suit in the Supreme Court of New York seeking an order directing arbitration in accordance with the arbitration provisions. Petitioner then filed this suit in the Middle District of Georgia, where the work under the subcontracts was performed, seeking (1) recovery of the amounts alleged to be due under the subcontracts; (2) rescission of the subcontracts — on grounds of fraud — and recovery on a quantum, meruit basis; (3) in the alternative, failing in both of these claims, recovery of the reasonable value of the labor and materials furnished; and (4) an injunction enjoining the respondent from proceeding with its arbitration efforts in New York. Neither party sought to compel specific performance of the arbitration agreement. The District Court, holding (1) that the Miller Act gave petitioner the right to sue in the District Court where
I.
We need not elaborate at length on the involved factual situation since it is detailed in the opinions of the Court of Appeals and the District Court. As we have said, petitioner filed suit in the United States District Court for the Middle District, of Georgia, the district in which the subcontracts were performed, alleging breach of contract for refusal to pay and seeking recovery for work which had been performed and, alternatively, rescission of the subcontracts on grounds of' fraud. The suit was brought under the provisions of the Miller Act, which provides in pertinent part:
“Every suit instituted under this section shall be brought in the name of the United States.for the use of the person suing, in the United States District Court for any district in which the contract was to be performed, and executed and not elsewhere, irrespective of the amount in controversy . . . .” 40 U. S. C. §t270b (b).
The Court of Appeals, with one judge dissenting, reversed on the theory that the Miller Act was not enacted for the benefit of plaintiffs in the selection of a forum, but rather for the convenience of the defendant, and that this is the type of dispute that is and should be subject to arbitration. As to the issue of fraud, it held that federal law controls in determining whether an allegation of fraud precludes arbitration of a dispute arising under the subcontracts and concluded that, in order to bar arbitration under federal law, the allegation of fraud must be specifically directed to the arbitration clause rather than to the entire contract. Thus, it reversed the District Court on both points.
II.
At the outset we note, as we have indicated, that no request has been made here for the enforcement of the arbitration agreement included within the subcontracts. Indeed, the petitioner has attacked not only the subcontracts, but also the arbitration clauses contained therein,
In view of our holding here, it is not necessary to reach the issues relating to arbitrability of disputes arising under these subcontracts. In "fact, disposition of the fraud issue may dispose of the entire suit. In the event the fraud issue is decided favorably to the respondent, and the United States District Court for the Middle District of Georgia should be called upon to decide the question of arbitrability of such disputes and related problems in Miller Act cases, its decision on that point would then, of course, be subject to review.
It is so ordered.
Mr. Justice Stewart would affirm the judgment substantially for the reasons stated in Chief Judge Tuttle’s opinion for the Court, of Appeals. 30.6 F. 2d 554.