Opinion · Supreme Court of the United States

Martinsburg & Potomac Railroad v. March

Martinsburg & Potomac R.R. v. March, 114 U.S. 549 (1885)

Type
Opinion
Court
Supreme Court of the United States
Jurisdiction
Federal
Date
1885-05-04
Topic
general

Me. Justige HaklaN delivered the opinion of the court. This case is within the principles announced in Kihlberg v. United States, 97 U. S. 398, and Sweeney v.

Citator

UpLaw has not yet analyzed Martinsburg & Potomac Railroad v. March. The absence of a flag is not a finding that it is good law.

Cited by
192 opinions

Headnotes

  1. Contracts Law — Conclusive Determination by Engineer Where parties to a construction contract expressly agree that the company's engineer shall determine all questions relating to the execution of the contract, including the quantity of work and the compensation earned, and that his estimate shall be final and conclusive, the engineer's action in the premises is conclusive upon both parties in the absence of fraud, or such gross mistake as would necessarily imply bad faith, or a failure to exercise an honest judgment. 114 U.S. 549 (citing Kihlberg v. United States, 97 U.S. 398, and Sweeney v. United States, 109 U.S. 618)
  2. Contracts Law — Conditions Where a construction contract provides that the company's obligation to pay the balance due arises only upon the engineer's written certification of complete performance, together with his estimate of the work done and the compensation due, no liability to pay attaches, and no right to sue on the contract arises, absent such certificate, unless facts excusing its absence are alleged. 114 U.S. 549
  3. Contracts Law — Impeachment of Engineer's Estimate A plaintiff seeking to go behind the engineer's estimate must allege that the engineer was guilty of fraud, made such gross mistake in his estimates as necessarily implied bad faith, or failed to exercise an honest judgment; a bare claim that the price fixed was inadequate or unjust is insufficient to impeach the determination. 114 U.S. 549
  4. Contracts Law — Mistake Where the final estimate of a contract engineer is conclusive absent fraud or intentional misconduct, an instruction permitting the jury to consider mere "gross mistake" is misleading unless the jury is informed that the mistake must be so gross or of such a nature as necessarily to imply bad faith on the engineer's part. 114 U.S. 549
  5. Contracts Law — Conclusiveness of Engineer's Estimate — Inadequacy of Price Where the engineer's classification and valuation of work is within the terms of the contract, his estimate at the contract rate is conclusive unless impeached for fraud or such gross mistake as necessarily implies bad faith; the inadequacy or injustice of the agreed price is not a permissible ground for the jury to presume fraud or disregard the engineer's estimate, as that would enable the jury to make a contract the parties did not themselves choose to make. 114 U.S. 549