Mr. Justice Bean delivered the opinion of the court. The controlling propositions made by the defendant on this appeal are: First, there never ivas any agreement or understanding for an extension or waiver of time of performance; second, if such an agreement were, made, Schulze had no authority to act for or to bind' the defendant thereby; third, if such *388contract were made, and Schulze bad authority to bind the defendant, it was void because within the statute of frauds, and not in writing; and fourth, the court erred in ruling and instructing. the jury that the measure of damages for a breach of the contract was the value of the land agreed to be conveyed at the. time of the breach, less the balance due on the purchase price, and in admitting evidence tending to prove such value. 1. The first two points involve questions of fact. They were submitted to and decided by the jury adversely to the defendant, and if there was evidence to support the verdict, it cannot be disturbed.
Citator
- Cited by
- 31 opinions
delivered the opinion of the court.
The controlling propositions made by the defendant on this appeal are: First, there never ivas any agreement or understanding for an extension or waiver of time of performance; second, if such an agreement were, made, Schulze had no authority to act for or to bind' the defendant thereby; third, if such
1. The first two points involve questions of fact. They were submitted to and decided by the jury adversely to the defendant, and if there was evidence to support the verdict, it cannot be disturbed. We are only required, therefore, to look far enough into the record to ascertain whether or not this is so, and not to determine whether it is in accordance with the weight of the testimony.
2. The plaintiff testified that he was a half owner with Himpel in the contract for the purchase of the land, and that such fact was known to the defendant and its officers at the time it was made; that after the contract had been executed, in the latter part of the summer or early fall- of 1883, Himpel told him that there was a question about the title to the land which the defendant had agreed to sell to them, and that Schulze had been talking to him about it; that thereupon he and Himpel immediately went to the office of Schulze to see about the matter, and Schulze told them that there was a dispute between the defendant and the Northern Pacific Eailroad Co. concerning the land, and in his (Schulze’s) opinion the Northern Pacific would finally get it; that in view of this controversy he would not accept any further payments on the contract with the defendant until it was settled; that be was the land agent of each company, and that, if the Northern Pacific Co. got the land, he would sell it to them on the same terms, but in that event they must take their money back from the defendant without interest, and without making any trouble; that, if the Northern Pacific should lose the land, they should commence making the payments on their contract with the defendant the same as before; that witness and Himpel agreed to this arrangement, and relied upon the same; that they heard nothing more about the matter, but when the second payment became due witness went to the office
Continuing, he says that when Col. Moores, who was acting as land agent during Schulze’s absence, learned of the payment, he refused to accept it, and told witness that he had positive instructions from Schulze not to take the money or receive any more payments oh the land until the overlap controversy was settled; that the money was then handed back to witness, and Moores erased, the credit on the contract by drawing lines with red ink through it; that nothing more was done, until about the time the third payment became due, when plaintiff and Himpel again went to the office of the defendant to inquire about the overlap controversy, and to see whether it was ready-to receive payments on the contract, and there had a conversation with Mr. Andrews, who in the mean time had succeeded Schulze as land agent; that witness asked Andrews about the. controversy, and whether he and Himpel should go ahead with their payments, and talked over with him- the arrangements they had made with Schulze; that Andrews said: “Schulze is certainly mistaken about our not getting the land,” whereupon Himpel said: “We will make the payments any time that you are prepared to make your deed. We stand prepared to pay the whole contract right up at any time. Are you ready now?” And Andrews said: “No, we are not in a position to make a deed now; there is only one thing to be done, and that is to let the matter rest until this controversy between the. Oregon & California Eailroad Co. and the Northern Pacific Eailroad Co. is settled, and whep it is I will personally notify you”; that Andrews took the addresses of witness and Himpel, and they went away from the office; that a few weeks later when witness returned from one of his trips in the country, he found a note to him from Andrews, requesting him to deliver an inclosed sealed letter to Himpel; that on May 3, 1885 — the first time he saw Himpel thereafter — he delivered the note to him; that it was from Andrews; dated April (&, 1885, and informed Himpel that the second and third payments on the
Himpel corroborates this testimony of the plaintiff, and Schulze himself testified that the refunding to the plaintiff and Himpel of the second payment tendered by them on the contract was made by Moores in jmrsuance of a general order given by him that no further payments were to be received on the contract because the title to the land was in dispute; that “I gave orders to this effect to my assistant, I. R. Moores, and told purchasers of lands under like conditions at every opportunity that the company would not accept any further payments on lands of this character until the question of title, had been settled, but that mean while the contracts should not be forfeited. * * I especially remember in this connection a number of sections sold tq the late A. G-. Cunningham. This gentleman also tendered payment on • his contract, but I refused to accept it for the reasons stated. * * I had also told Himpel before (March 24, 1884) — Himpel and Mr. Neppach, to whom the contract under consideration is now assigned — what the policy of the company would be.” This testimony was clearly sufficient for the jury to find in favor of the plaintiff upon the issue of the extension agreement or waiver t. of the time of performance by the plaintiff and Himpel of the contract made by them with the defendant for the purchase of the land in question. Counsel make a strong and persuasive argument, based upon alleged contradictions and inconsistencies in the testimony and the pleadings and the conduct of the parties, that no such agreement was made or intended to be made; but we are not authorized to review the facts to ascertain whether, in our opinion, the verdict is in harmony therewith. It is sufficient that there was competent evidence to support it.
4. That there was sufficient evidence to support the verdict oí the jury that Schulze had authority to make the contract or agreement in question under the law is hardly open for argument. The evidence showed or tended to show that he was appointed land agent of the defendant by its president, and served as such from 1878 to 1884, during which time the defendant was engaged in practically two lines of business and owned and dealt with two classes of property- — the one. a line of railroad from Portland to the southern part of the State, and the other the listing, selection, sale, disposition, and management of the lands granted to it by congress. The two departments were conducted separately and under different managements. The office of the land department was during a great part of the time in one building; that of the railroad proper in another. The land department was in the sole and exclusive charge of Schulze, who had under him a number of clerks and assistants, who took their orders from him. He listed and selected the lands accruing to the. defendant under its grant, fixed the prices and terms at which it was to be sold, made and executed all contracts in reference thereto, and received and receipted for all moneys, due on account thereof. During his term of office he thus made and executed on behalf of the defendant more than 1,200 land contracts, duplicates of which were retained by the company, and comprise five large volumes, which were introduced and admitted in evidence. He made various agreements with many of the purchasers from timé to time, extending the time, of payment or waiving a default for divers and sundry reasons. He was advertised extensively by the defendant in the newspapers and by circulars and maps as its land agent and in charge of its land department, and as the person to whom intending purchasers should apply. In short, he was held out as the authorized representative of the company in that respect, and transacted its entire business in relation to the acquisition, sale, and disposition of its lands. His authority and acts were never disavowed or disapproved by'his principal. He testified that he had full charge of the land interests of the defendant in Oregon, made and signed all contracts for the sale thereof, fixed the terms and prices at
“The rule is elementary and universal,” says Mr. Justice Moore, “that every grant of power by a principal to his agent, where no limitations are apparent, is to be construed as carrying with it, as an incident thereto, the authority to do all things proper, usual, necessary, and reasonable to carry into effect the objects and purposes sought to be áccomplished by the authority conferred”: Durkee v. Carr, 38 Or. 189 (63 Pac. 117), and authorities cited. That it was the natural and reasonable thing, under the circumstances, for Schulze to make the contract with the plaintiff and Himpel extending the time of payment is apparent. The company was bound by a written agreement to convey a large, tract of valuable land upon the payment of the purchase price at certain designated dates and in specified amounts. They were ready and willing to make the payments as agreed upon. The controversy between the defendant and the Northern Pacific Eailroad Co. put it out of the defendant’s
5. But it is argued that the extension contract or agreement was void because it was an oral modification of a contract within the statute of frauds. Ever since the decision of Lord Ellen-borough in Cuff v. Penn, 1 Maule & S. 21, holding that a subsequent parol modification of the time of performance specified in a contract within the statute of frauds was valid, there, has been much learning exhibited by judges and text-writers in the discussion of such question. The settled doctrine in England now seems to be contrary to that case, and it is now held that an agreement required by the statute of frauds to be in writing cannot be subsequently changed or modified as to the time of performance, or in any other respect, by an oral executory contract: Stead v. Dawber, 10 Ad. & El. 57; Hickman v. Haynes, L. R. 10 C. P. 598. In this country the cases are in conflict. Some of the courts, notably of Massachusetts, have followed Guff v. Penn, making a distinction between the contract, which the statute requires to be in writing, - and the time of performance, to which it is held the statute does not apply. The courts in
But we deem it unnecessary to decide at this time whether a contract required by the statute to be in writing can be altered as to the time or manner of performance by a subsequent parol executory agreement between the parties. Conceding the law to be as contended for by the defendant, and that the oral extension agreement or contract was invalid as an executory contract, and did not change or modify the terms of the written agreement, it was, nevertheless, acted upon by the plaintiff and Himpel, and the defendant cannot now assert its invalidity to their injury. The stipulation as to the times of payment by them was for the benefit of the defendant, and could be waived by it: 2 Eeed, Stat. Frauds, §459; 2 Warvelle, Vendors (2 ed.), §819; Blood v. Hardy, 15 Me. 61. It did so when it made the agreement that no subsequent payments should be made on the contract until the overlap controversy should be settled and such agreement
And the doctrine is thus summed up by Lindley, J., in Hide-man v. Haynes, L. E. 10 C. P. 598, 605: “The proposition that one party to a contract should thus discharge himself from his own obligations by inducing the other party to give him time for their performance is, to say the least, very startling, and, if well-founded, will enable the defendants in this ease to make use of the statute, of frauds, not to prevent a fraud on themselves, but to commit a fraud upon the plaintiff. It need hardly be said that there must be some very plain enactment or strong authority to force the court to countenance such a doctrine. The statute of frauds contains no enactment to the effect contended for.” The statute of frauds may not be invoked to perpetrate a fraud, nor will a party be permitted to insist upon the statute to protect him in the enjoyment of advantages procured from another, who, relying on an oral agreement, has acted and placed himself in a situation in which he must suffer wrong and injustice if the agreement is not enforced. /'A party to a contract for the sale of land, who knowingly consents or agrees to a postponement of the performance by the other at the time spécified of some stipulation for his benefit, cannot, after the other has acted upon such consent, avail himself of the default, and treat the contract as forfeited, although the performance of the stipulation at the time specified may have been made of the essence of the contract: 29 Am. & Eng. Enc. Law (2 ed.), 826; Missouri, K. & T. R. Co. v. Pratt, 64 Kan. 118 (67 Pac. 464); Brown, Stat. Frauds, §§ 424, 425; Longfellow v. Moore, 102 Ill. 289; Sheridan v. Nation, 159 Mo. 27 (59 S. W. 972); Long v. Hartwell, 34 N. J. Law, 116; Scheerschmidt v. Smith, 74 Minn. 224 (77 N. W. 34); Smiley v. Barker, 83 Fed. 684 (28 C. C. A. 9); Stearns v. Hall, 9 Cush. 31; Dodge v. Wellman, 1 Abb. Dec. 512; Wilber v. Paine, 1 Ohio, 251; Fleming v. Gilbert, 3 Johns. 528.
It may be. suggested that the oral agreement between the plaintiff and Himpel and Schulze amounted to more than a
If the extension agreement was not valid and binding on the defendant because within the statute of frauds, and amounted to nothing more than an oral stipulation to waive, a strict performance of the contract, it probably cordd have been revoked at any time upon giving the vendees notice of its intention to do so, and a reasonable time after such notice in which to make the prior payments. No such action is pleaded as a defense, or was ever taken by it. Andrews’ letter to Himpel of April 4, 1885, makes no reference to the extension agreement, or to the understanding between the vendees and Schulze as to the time in which the ¡Dayments should be made, or of any intention to revoke or rescind such agreement. Moreover, a reasonable time was not allowed the vendees in which to make the payments after the receipt of such letter. It was dated April 4, 1885, and was not received by Himpel, to whom it was addressed, until May 3d, the day on which the time allowed to make the payments expired.
6. The remaining question involves the competency of evidence given by some of the witnesses as to the value of the timber growing on the land which the defendant contracted and agreed to sell to plaintiff and Himpel, and the proper measure of damages for the breach of the contract. It is the law that the value of real estate cannot be shown by proving the value
This is the rule adopted and adhered to by the trial court. The court ruled that the value of the land in question could not be ascertained from the estimated stumpage value of the timber growing thereon, but that a witness who had given an opinion as to the market value of the land might state the facts upon which such opinion was based, which in-this case involved the character and value of the timber. The witnesses were first asked to give their opinions as to the market value of the land, and, after they had done so, were permitted to state, the amount. and value of the stumpage as showing upon what they based their opinions; and this they had a right to do under the law, as we understand it. The court instructed the jury that the measure of damages in this case would be the market value of the land at the time of the breach of the contract, less the amount of the. unpaid purchase price. Mr. Warvelle says, in sneaking on the subject of the measure of damages in an action by a vendee against a vendor for the breach of a contract to convey real estate: "The rule is well established that where the
7. Where a vendor acting in good faith and without knowledge of a defect in his title agrees to sell and convey land, and is unable to do so because of a failure of title, or if, upon discovery of such defect, he refuses further to perform or to be bound by the contract, leaving the vendee to his action for damages, there is some conflict in the authorities as to whether the vendee can recover anything more than the amount paid, with interest. No such case, however, is presented here. The defendant knew, or was chargeable with knowledge, at the time the contract was made, of the condition of its title, and that the land which it agreed to sell to the plaintiff and Himpel was included in the. limits of a prior grant to the Northern Pacific Railroad Go. It. did not at any time attempt to repudiate or rescind the contract on account of the controversy about the title, or decline, to be bound further thereby on that account, but, on the contrary, induced the vendees to make an agreement or contract with it for its benefit, and unon which they relied and acted, to postpone performance until the title was settled. It does not
There being no error in the record, the judgment is affirmed.
Aeeirmed.