Opinion · Oregon Supreme Court
Giaconi v. City of Astoria
Giaconi v. City of Astoria, 60 Or. 12 (Or. 1911)
- Type
- Opinion
- Court
- Oregon Supreme Court
- Jurisdiction
- Oregon
- Date
- 1911-10-10
- Topic
- employee-benefits-and-executive-compensation
Mr. Justice Moore delivered the opinion of the court. The alleged failure to adopt a plan for the proposed improvement and defendant’s averred supervision of the work will be considered. To render these questions intelligible requires a more detailed statement of facts than has been hereinbefore given. The resolution adopted by the council declaring an intention to improve Irving avenue required the city surveyor to make and file with the auditor plans and specifications for and estimates of the work, and provided that any matter of construction or drainage found necessary to make the improvement safe or substantial should be done by the contractor, whether specified or not, without extra charge.
Citator
- Cited by
- 29 opinions
delivered the opinion of the court.
The alleged failure to adopt a plan for the proposed improvement and defendant’s averred supervision of the work will be considered. To render these questions intelligible requires a more detailed statement of facts than has been hereinbefore given. The resolution adopted by the council declaring an intention to improve Irving avenue required the city surveyor to make and file with the auditor plans and specifications for and estimates of the work, and provided that any matter of construction or drainage found necessary to make the improvement safe or substantial should be done by the contractor, whether specified or not, without extra charge. Pursuant to the resolution, the surveyor ran cross-section lines, examined the land, and filed with the auditor specifications for the improvement, which provided that cuts and fills should be made to make the highway conform to the established grade, and that on certain lines, conduits of designated material and dimensions should be used. The established grade of Irving avenue at Eighteenth and Nineteenth streets is 185 and 191 feet, respectively, above low water on the Columbia Eiver, which stream is nearly parallel with and about 500 feet from the avenue. Though the specifications filed provided for the disposal of surface water the draining of block 24 was not required, nor was any bulkhead or other means suggested to prevent a possible slide. The ordinance limiting the time and prescribing the manner of the grading demanded that the performance of the work be let to the lowest bidder, and that “the contract shall provide that said improvements shall be constructed and completed to the satisfaction of the committee on streets and public ways, and the superintendent of streets and the city surveyor.” The contract stipulated that the improvement should be made strictly as provided for by the plans
A. S. Tee, who had been city surveyor of Astoria nearly 10 years, and whose experience as a civil engineer covered a period of 31 years, testified that he was not requested by any one to ascertain whether or not the surface of the ravine was sufficient to sustain an embankment of 32 feet, which was. its height at the deepest place in the gulch; that until the ground began to settle he had never entertained a doubt on the subject of the stability
W. A. Goodin testified that in clearing the right of way on Irving avenue, before the resolution was adopted declaring an intention to make the improvement, he discovered cracks in the earth at the place where the slide subsequently occurred. This witness did not inform the city surveyor or any one of this fact, so far as disclosed by the transcript.
G. B. Hegardt and T. H. Curtis, civil engineers of many years’ experience, who examined the premises after the injury, severally testified that, before any improvement was undertaken at that place, the subsoil should have been examined by boring to determine whether or not a foundation could have been secured sufficient to sustain the weight of the fill, and that provision should have been made for a system of drainage which was as essential as a safe basis for the fill.
1. Predicated on such testimony, a finding was made that defendant did not exercise care or skill in providing plans or specifications for the improvement or for drainage. The conclusion thus reached seems to have been questioned by the trial court, for with the findings was filed an opinion wherein it was said:
“But, even if there should be a doubt as to the question of negligence in preparing or failing to prepare a proper plan of improvement, the subsequent conduct of the city in regard -to the fill in the gulch after the hillside began to move out leaves my mind entirely free from doubt as to the liability of the city.”
A municipal corporation in devising plans for improving public highways within its borders acts judicially, and when proceeding in good faith is not liable for errors of judgment; but in constructing the work it acts ministerially, and is bound to see that the plan is executed in a
2. The exemption of a municipal corporation from liability for injuries resulting from errors or defects in the plan of public work is criticised by a text-writer who in referring to decisions upholding the principle says:
“We think, however that the rule is too broadly stated in these cases, and that there are instances in which a city may be liable for injuries caused by defects in the plan of a street or sewer. It seems to us that a distinction should be drawn between those cases in which the defect in the plan arises from a mere error of judgment and those in which the defect arises from negligence in devising or adopting the plan.” Elliott, Roads & Streets (2 ed.) § 473.
In the succeeding section the learned author elucidates this animadversion by the following statement:
“If the city has obtained the professional advice of one skilled in such matters, and has used due care in selecting its adviser, it will generally be free from liability, if, in consequence of following such advice, the structure, or other improvement, as the case may be, turns out to be defective.”
We concur in what Judge Elliott has said respecting a sewer, for the rule seems to be that for a defect in a plan therefor, in consequence of which an injury results, the city is liable for ensuing damages. Plaintiff’s counsel cites many cases in support of this principle, but no reference thereto will be made, since it is believed they are not in point because the improvement of an unopened street is an exercise of governmental power by a municipal corporation as the agent of the state and made for
3. In order to devise a proper plan defendant had the service of its surveyor, who is a competent engineer, and in running the cross-section lines to determine the amount of the cut and fill, he examined the ground where the improvement was to have been made, and prepared specifications based on such investigation. We think his judgment respecting the plan was all that could reasonably have been required from an inspection of the then condition of the soil, when it is remembered that no slide had ever been known in that vicinity, and that he was never informed, so far as we can determine, of the existance of the fissures which Goodin saw. It was not difficult for the expert engineers who examined the premises after the injury, accurately to state what precautions should have been taken. It will be kept in mind that the conditions presented to their attention were very different from what were seen when the city surveyor made his observations, and, in view thereof and of the further fact that the city employed a competent engineer, we think there was not such negligence in adopting a plan as to render the defendant liable.
4. The remaining question is whether or not the improvement was made under defendant’s direction as alleged in the complaint. The execution of the plan is a ministerial service, and for any negligent performance thereof liability attaches. The contract did not stipulate that any officer of the city should direct the manner by which the fill was required to be made. The specifica-
5. A careful examination of the entire testimony which has been sent up fails to disclose that any direction was given by defendant’s officers or agents respecting a performance of the work, except that Goodin was required to place a box flume in the fill, a duty imposed upon him by the resolution whenever necessity demanded a drain. Before the slide occurred, the city surveyor and other officers knew that injury might result from a continuance of the work, but no effort was made to suspend operations until it was too late to be of any service. However, as no power to superintend the making of the improvement was reserved, the defendant was not liable on the ground of estoppel.
As we view the testimony, there is no controversy respecting the facts, and, believing the conclusions of law as deduced by the court below are erroneous, the judgment is reversed, and the cause remanded for such further proceedings as may be necessary not inconsistent with this opinion. Reversed.