Opinion · Ohio Supreme Court

Brown v. City of Dayton

Brown v. City of Dayton, 89 Ohio St. 3d 245 (Ohio 2000)

Type
Opinion
Court
Ohio Supreme Court
Jurisdiction
Ohio
Date
2000-07-12
Topic
general

stating that to “find otherwise would be to allow” the defendants “to come under constant attack simply by replenishing the ranks of plaintiffs” | explaining that under Ohio’s broad definition of privity for res judicata purposes, all that is necessary is a “mutuality of interest, [which] includ[es] an identity [as to the] desired result” | finding privity for taxpayers and residents of a city that was a party to a prior suit | finding taxpayers in privity with each other for purposes of res judicata where they sought the same general disallowance of a local ordinance for the same reasons | finding taxpayers in privity with each other for the purposes of res judicata where they sought the same general disallowance of a local ordinance for the same reasons | “[w]hether the original claim explored all the possible theories of relief is not relevant.” | “[A] mutuality of interest, including an identity of desired result,.creates privity.”

Citator

Cited by
53 opinions
[This opinion has been published in Ohio Official Reports at 
89 Ohio St.3d 245
.]




      BROWN ET AL., APPELLEES, v. CITY OF DAYTON ET AL., APPELLANTS.
                     [Cite as Brown v. Dayton, 
2000-Ohio-148
.]
Municipal corporations—Zoning–Proposed rezoning ordinance adopted by
        city—Validity of ordinance challenged twice—Civil procedure—
        Application of doctrine of res judicata.
          (No. 99-164—Submitted November 17, 1999—Decided July 12, 2000.)
APPEALS from the Court of Appeals for Montgomery County, Nos. CA-16875 and
                                        CA-16876.
                                  __________________
        {¶ 1} This case involves the efforts of appellant Waste Management of
Ohio, Inc. (“WMO”) to construct a waste disposal and recycling facility within the
boundaries of appellant city of Dayton (“City”). Appellees seek to overturn the
rezoning ordinance that allowed WMO to construct the facility on land that was
previously zoned residential.
        {¶ 2} On May 23, 1990, WMO submitted an application to rezone one
hundred thirteen acres of land in Dayton from a single-family residential
classification to light industrial, so that it could operate a recycling and disposal
facility. On July 12, 1990, WMO filed an additional application for a “planned
development,” in an effort to operate a sanitary landfill on the land as well.
        {¶ 3} The “planned development” concept is a part of the Dayton Revised
Code of General Ordinances, R.C.G.O. 150.260.                 The planned development
classification allowed for multiple uses and functions within one large tract of land.
By law, an applicant for a planned development must provide a development plan,
which must contain a site plan showing “the location and arrangement of all
existing and proposed buildings and structures, the proposed traffic circulation
                              SUPREME COURT OF OHIO




pattern within the Planned Development, the location and width of all proposed
streets and public ways” and other structures. R.C.G.O. 150.266.
        {¶ 4} The Plan Board of the City, which reviews planned development
applications and makes recommendations thereon to the City Commission, held a
public hearing on WMO’s proposal on November 13, 1990. Following that
hearing, the Plan Board recommended disapproval of the proposed rezoning.
        {¶ 5} On November 14, 1990, WMO appealed that decision to the
commission. The commission, after a hearing on the matter, took no action. By
ordinance, if the commission does not act within three months, the proposal is
deemed defeated. R.C.G.O. 150.481.
        {¶ 6} On February 22, 1991, WMO responded to the proposal’s defeat by
filing suit in federal court against the City, the City Commission, and the City Plan
Board. The judge in that case issued an order directing settlement, and the parties
eventually entered into a settlement agreement and consent decree.
        {¶ 7} On February 19, 1992, the commission set a public hearing for March
25, 1992, concerning WMO’s proposed rezoning ordinance. On February 22, 1992,
the Clerk of the commission published notice of the hearing and placed maps and
text of proposed Ordinance 28527 (“Ordinance”) on file for public inspection.
        {¶ 8} At the beginning of the March 25, 1992 hearing, the clerk read the
proposed Ordinance. The Ordinance read was identical to the one placed on file
for public view but for one relevant difference. Section 2 of the Ordinance, which
included the details of the proposed plan development, modified the development’s
setback, reducing from three hundred feet to one hundred fifty feet the green buffer
strip that had to be provided on all sides of the landfill. After the hearing, the
commission set the Ordinance for an April 8, 1992 vote.
        {¶ 9} On March 27, 1992, the clerk made available to the public the text of
the proposed Ordinance as it was read at the March 25, 1992 hearing. On March
30, 1992, opponents of the landfill, including one of the plaintiffs in this case, James




                                           2
                                 January Term, 2000




L. Sweeney, filed a complaint seeking to enjoin the commission from voting on or
enacting the proposed Ordinance.        That complaint was based in part on the
argument that the City Commission could not vote on the Ordinance because the
Ordinance as it was to be voted on would not have been on file for thirty days on
the date of the vote, as required by R.C.G.O. 150.478.
       {¶ 10} The trial court held hearings on April 6 and 7, 1992. In its April 8,
1992 order, the court declined to enjoin a vote on the ordinance, but instead required
the City to disclose information regarding the settlement negotiations between the
City and WMO and also to provide “ ‘an explanation of what led to the revision of
the planned development reducing the buffer zone of the landfill from 300 to 150
feet * * *.’ ” Wall v. Dayton (May 4, 1993), Montgomery App. No. 13419,
unreported, 
1993 WL 143770
, quoting the trial court’s order. The court specifically
found no violation of the thirty-day rule.
       {¶ 11} The commission scheduled a second public hearing and vote for
April 15, 1992. The Wall plaintiffs did not seek a stay or injunction pending their
appeal of the trial court’s order. Having complied with the trial court’s order for
disclosure, the commission voted at the April 15, 1992 hearing to adopt the
proposed Ordinance. The plaintiffs all concede that they either had actual notice of
the modified setback or that the setback was irrelevant to them because they were
opposed to the landfill anyway.
       {¶ 12} On May 4, 1993, the Montgomery County Court of Appeals
dismissed the appeals from the trial court’s decision in Wall, holding that plaintiffs’
claims were moot because they sought to enjoin a vote that had already been taken.
The Wall plaintiffs did not appeal the appellate court’s decision. WMO went
forward with its purchase of the land and constructed a landfill in that location.
Neither the Wall plaintiffs nor the plaintiffs in this case ever sought an injunction
against the construction of the landfill.




                                             3
                            SUPREME COURT OF OHIO




       {¶ 13} Appellees commenced the present action on October 14, 1993. Of
the appellees in this case, only Sweeney was also a plaintiff in Wall. Appellees
again challenged the validity of the Ordinance based upon the same grounds as in
Wall, i.e., that the Ordinance as voted upon was not made public for the required
thirty-day period. This time, the plaintiffs sought a declaratory judgment that the
Ordinance was invalid. WMO intervened in the action as a defendant.
       {¶ 14} On September 25, 1997, the trial court granted the City’s and
WMO’s motions for summary judgment. Appellees appealed. The Montgomery
County Court of Appeals reversed the trial court in part, finding that the City had
failed to give adequate notice of the setback modification. Because the written text
reflecting the modified setback had not been on file for thirty days, the court of
appeals found that Section 2 of the Ordinance was invalid.
       {¶ 15} This cause is before the court upon the allowance of discretionary
appeals.
                              __________________
       Charles A. Smiley, Jr., for appellees.
       Freund, Freeze & Arnold, Neil F. Freund and Shawn M. Blatt, for appellant
city of Dayton.
       Vorys, Sater, Seymour & Pease, John Winship Read, Marcel C. Duhamel
and Gail C. Ford, for appellant Waste Management of Ohio, Inc.
       Barry M. Byron, Stephen L. Byron and John Gotherman, urging reversal for
amicus curiae, Ohio Municipal League.
                              __________________
       PFEIFER, J.
       {¶ 16} We find that that the doctrine of res judicata applies to this case, and
accordingly reverse the court of appeals.
       {¶ 17} At the outset, we must determine whether there is an identity of
parties in the two actions. Res judicata operates as “ ‘a complete bar to any




                                            4
                                 January Term, 2000




subsequent action on the same claim or cause of action between the parties or those
in privity with them.’ ” (Emphasis added.) Johnson’s Island, Inc. v. Danbury Twp.
Bd. of Trustees (1982), 
69 Ohio St.2d 241, 243
, 
23 O.O.3d 243
, 245, 
431 N.E.2d 672
, 674, quoting Norwood v. McDonald (1943), 
142 Ohio St. 299
, 
27 O.O. 240
,
52 N.E.2d 67
, paragraph one of the syllabus. The plaintiffs in these consolidated
cases are Rev. William J. Brown, Rev. Richard L. Righter, Jacqueline J. Patterson,
James L. Sweeney, and Leonard L. Howie. Sweeney was a plaintiff in the Wall
case, and Howie testified as a witness for the plaintiffs in that case. The privity
between Brown, Righter, and Patterson and the Wall plaintiffs is at issue.
        {¶ 18} What constitutes privity in the context of res judicata is somewhat
amorphous. A contractual or beneficiary relationship is not required:
        “In certain situations * * * a broader definition of ‘privity’ is warranted. As
a general matter, privity ‘is merely a word used to say that the relationship between
the one who is a party on the record and another is close enough to include that
other within the res judicata.’ Bruszewski v. United States (C.A.3, 1950), 
181 F.2d 419, 423
 (Goodrich, J., concurring).” Thompson v. Wing (1994), 
70 Ohio St.3d 176, 184
, 
637 N.E.2d 917, 923
.
        {¶ 19} We find that a mutuality of interest, including an identity of desired
result, creates privity between the plaintiffs in this case and those in Wall. In neither
case did the plaintiffs seek personally tailored relief to fit their unique circumstance
or factual situation. All have sought the general disallowance of the Ordinance,
and all for the same reason—an alleged violation of the thirty-day publication rule.
Plaintiffs all simply refer to themselves as residents and taxpayers within the city
of Dayton. We find that their legal interests are the same and that they are in privity
with each other for purposes of res judicata. To find otherwise would be to allow
the Ordinance to come under constant attack simply by replenishing the ranks of
plaintiffs.




                                           5
                             SUPREME COURT OF OHIO




        {¶ 20} In Grava v. Parkman Twp. (1995), 
73 Ohio St.3d 379
, 
653 N.E.2d 226
, paragraph one of the syllabus, this court held that under the doctrine of res
judicata, “[a] valid, final judgment rendered upon the merits bars all subsequent
actions based upon any claims arising out of the transaction or occurrence that was
the subject matter of the previous action.”
        {¶ 21} Whether the original claim explored all the possible theories of relief
is not relevant. “It has long been the law of Ohio that ‘an existing final judgment
or decree between the parties to litigation is conclusive as to all claims which were
or might have been litigated in a first lawsuit.’                (Emphasis added.)
* * * The doctrine of res judicata requires a plaintiff to present every ground for
relief in the first action, or be forever barred from asserting it.” Natl. Amusements,
Inc. v. Springdale (1990), 
53 Ohio St.3d 60, 62
, 
558 N.E.2d 1178, 1180
, quoting
Rogers v. Whitehall (1986), 
25 Ohio St.3d 67, 69
, 25 OBR 89, 90, 
494 N.E.2d 1387, 1388
.
        {¶ 22} In Grava, this court held that res judicata “ ‘applies to extinguish a
claim by the plaintiff against the defendant even though the plaintiff is prepared in
the second action (1) To present evidence or grounds or theories of the case not
presented in the first action, or (2) To seek remedies or forms of relief not demanded
in the first action.’ (Emphasis added.)” Grava, 73 Ohio St.3d at 383, 
653 N.E.2d at 229
, quoting 1 Restatement of the Law 2d, Judgments (1982) 209, Section 25.
        {¶ 23} The Wall plaintiffs and the plaintiffs in this action complained of the
same alleged defect in the Ordinance, that the setback provision was not on file the
full thirty days before the commission hearing. Whereas the first action sought to
prevent a vote on the Ordinance, this action seeks to nullify the Ordinance after it
has passed. The only difference in the two cases is the remedy sought. The exact
same facts are at issue. The court of appeals recognized that the Wall court “did
rule on the same procedural issue being raised by the appellants in [this case].”




                                          6
                                 January Term, 2000




Under Grava, even though plaintiffs are seeking a different remedy, res judicata
extinguishes their claim.
        {¶ 24} The court of appeals rejected appellants’ res judicata argument not
because the facts did not fit the situation, but because the court opined that applying
res judicata “would result in a manifest injustice.” The same court in Wall had
stated that “we do not reach the issue of whether the Ordinance is invalid and void,”
since the Wall plaintiffs “could not and did not request that the Ordinance be
declared invalid before its enactment.” The court added in Wall that “[a]ny
determination of the validity of the Ordinance must wait upon a future day.” Thus,
in the present case below, the court found that applying res judicata under those
circumstances “would result in a manifest injustice to appellants because it would
shield the trial court’s ruling on the procedural validity of the Ordinance from
appellate review, thereby denying appellants their right of appeal.”
        {¶ 25} The trial court’s decision in Wall was announced on April 8, 1992.
A vote on the Ordinance was not taken until April 15, 1992. The appellees had
their chance at appellate review. Again, the status of the ordinance as “proposed”
or “enacted” did not matter as to the factual basis of the appellees’ claim. Their
only argument was the lack of a complete thirty-day display of amendments to the
plan. Whether that fact affected the validity of the Ordinance was the only thing at
issue. Appellees should have sought a stay of the trial court’s judgment pending
their appeal to the appellate court. That way, very simply, the appellate court could
have reviewed the trial court’s ruling. The fact that the issue was mooted is the
fault of appellees alone. Thus, any “injustice” is self-perpetuated and certainly does
not rise to the level of nullifying res judicata.
        {¶ 26} Accordingly, we reverse the judgment of the court of appeals and
reinstate the judgment of the trial court.
                                                                  Judgment reversed.




                                             7
                             SUPREME COURT OF OHIO




          MOYER, C.J., DOUGLAS, F.E. SWEENEY and LUNDBERG STRATTON, JJ.,
concur.
          RESNICK and COOK, JJ., concur in judgment.
                               __________________




                                         8