1348.102 Policies. (a) Contracting activities shall send contractor-submitted Value Engineering Change Proposals (VECPs) to the appropriate technical personnel for review. (b) Technical personnel shall conduct a comprehensive review of VECPs for technical feasibility, usefulness, and adequacy of the contractor's estimate of cost savings; make a written report; and recommend acceptance or rejection to the contracting officer. (c) The designee authorized to grant exemptions from value engineering provisions in appropriate supply, service, architect-engineer and construction contracts is set forth in CAM 1301.70. 1348.201 Clauses for supply or service contracts. The designee authorized to grant exemptions from the requirements of FAR Part 48 for a contract or class of contracts is set forth in CAM 1301.70.

Citator

UpLaw has not yet analyzed 48 C.F.R. Part 1348 — VALUE ENGINEERING. The absence of a flag is not a finding that it is good law.

1348.102 Policies. (a) Contracting activities shall send contractor-submitted Value Engineering Change Proposals (VECPs) to the appropriate technical personnel for review. (b) Technical personnel shall conduct a comprehensive review of VECPs for technical feasibility, usefulness, and adequacy of the contractor's estimate of cost savings; make a written report; and recommend acceptance or rejection to the contracting officer. (c) The designee authorized to grant exemptions from value engineering provisions in appropriate supply, service, architect-engineer and construction contracts is set forth in CAM 1301.70.

1348.201 Clauses for supply or service contracts. The designee authorized to grant exemptions from the requirements of FAR Part 48 for a contract or class of contracts is set forth in CAM 1301.70.