Opinion · Court of Appeals for the Fourth Circuit

East Tennessee Natural Gas Co. v. Sage

E. Tenn. Nat. Gas Co. v. Sage, 361 F.3d 808 (4th Cir. 2004)

Type
Opinion
Court
Court of Appeals for the Fourth Circuit
Jurisdiction
Federal
Date
2004-03-22
Topic
general

How later courts describe this case

  • recognizing that “[scheduling and conducting those hearings ... hvill obviously take an extended period of time.’”
  • concluding that a claim that early possession would disturb the productive capacity of the land "is simply a timing argument because productive capacity would still be disturbed, albeit at a later time, if just compensation was determined first"
  • recognizing the need for natural gas supply as a “substantial public interest”
  • observing the financial strength of the gas company and its parent corporation would enable payment if the security fell short
  • finding irreparable harm where “[i]t would not be possible to meet FERC’s deadline without a preliminary injunction”
  • taking into account that natural-gas company’s “parent company reported earnings of $1.17 billion from its natural gas transmission division”
  • discussing “adequate provision” in the context of injunctive relief rather than the pipeline company’s eminent-domain authority
  • finding pipeline project served public interest because it would make gas available to consumers and electric power plants, as well as help local communities to attract new business

Citator

UpLaw has not yet analyzed East Tennessee Natural Gas Co. v. Sage. The absence of a flag is not a finding that it is good law.

Cited by
175 opinions