How later courts describe this case

  • issuing writ of mandamus ordering Secretary to confer mineral patent to a claimant who had successfully demonstrated compliance with the statutory prerequisites

Citator

UpLaw has not yet analyzed Wilbur v. United States Ex Rel. Krushnic. The absence of a flag is not a finding that it is good law.

Cited by
95 opinions

Headnotes

  1. Energy & Utilities Law — Nature of a Perfected Claim A perfected location of a mining claim under the General Mining Law operates as a grant by the United States of the right of present and exclusive possession; the claim is property in the fullest sense, and so long as the owner complies with the mining laws, that possessory right is, for all practical purposes of ownership, as good as though secured by a patent. 280 U.S. 306, 316
  2. Energy & Utilities Law — Failure to Perform Annual Assessment Work Failure to perform the required annual assessment labor does not ipso facto forfeit a mining claim but only renders it subject to loss through relocation by another claimant, and no relocation may be made if the owner resumes work after the default and before the relocation. 280 U.S. 306, 317
  3. Energy & Utilities Law — Government's Interest in Annual Labor As against the United States, omission of assessment labor in any year is without effect; whenever $500 worth of labor in the aggregate has been performed and the other requirements, including payment of the purchase price, have been met, the owner is entitled to a patent even though annual assessment labor was omitted in some years. 280 U.S. 306, 317
  4. Energy & Utilities Law — Savings Clause of the Mineral Leasing Act Under § 37 of the Mineral Leasing Act, which saves valid claims existent at the date of the Act and "thereafter maintained in compliance with the laws under which initiated," the owner of a claim valid at the date of the Act who performs no labor for the assessment year in which the Act was passed nonetheless "maintains" the claim by resuming work in a subsequent year, unless at least some form of challenge on behalf of the United States to the valid existence of the claim has intervened. 280 U.S. 306, 317
  5. Administrative Law — Mandamus to Executive Officer Where the Secretary of the Interior, in declining to issue a patent for a mining claim, interprets and applies a statute contrary to its explicit terms, he departs from a plain official duty, and the error may be corrected by mandamus in the Supreme Court of the District of Columbia. 280 U.S. 306, 318
  6. Energy & Utilities Law — Scope of Relief Mandamus should direct disposal of the patent application on its merits, unaffected by the temporary default in assessment labor, with further proceedings conforming to the proper interpretation of the excepting clause of the Leasing Act and of Rev. Stats. § 2324. 280 U.S. 306, 319