Opinion · Supreme Court of the United States

H. E. Crook Co. v. United States

H. E. Crook Co. v. United States, 270 U.S. 4 (1926)

Type
Opinion
Court
Supreme Court of the United States
Jurisdiction
Federal
Date
1926-01-25
Topic
general

Mr. Justice Holmes delivered the opinion of the Court. This is an. appeal from a judgment of the Court of Claims, taken under § 242 of the Judicial Code before that section was repealed by the Act of February 13, 1925, c. 229, § 13; 43 Stat. 936, 941. The claim is for damages due to delay in enabling the plaintiff to perform a contract. The Court of Claims held that the plaintiff waived any claim that it might have had by going on with the work without protest and without taking any steps to protect itself. 59 Ct.

Citator

UpLaw has not yet analyzed H. E. Crook Co. v. United States. The absence of a flag is not a finding that it is good law.

Cited by
67 opinions

Headnotes

  1. Contracts Law — Government Contracts — Delays Where a government contract shows on its face that the contractor's progress will depend on the progress of buildings being erected by other contractors, and the contract strictly limits the contractor's time for performance while making no reference to government-caused delays except as grounds for extending the contractor's time, the Government is not obligated to compensate the contractor for losses resulting from delays in completing the buildings. 270 U.S. at 6-7
  2. Contracts Law — Government Contracts — Contract Price as Full Satisfaction A contractor's agreement to accept the contract price, reduced by liquidated damages for its delays and adjusted for the price of government-ordered changes, in full satisfaction for all work done under the contract, together with a provision that the contract price cover all expenses of every nature connected with the work, bars a claim for delay damages absent an express provision imposing such liability on the Government. 270 U.S. at 7-8