Opinion · Supreme Court of the United States

Ripley v. United States

223 U.S. 695

Type
Opinion
Court
Supreme Court of the United States
Jurisdiction
Federal
Date
1912-03-11
Topic
general

How later courts describe this case

  • recognizing “a corresponding duty that the agent’s judgment should be exercised — not capriciously or fraudulently, but reasonably and with due regard to the rights of both contracting parties”

Citator

UpLaw has not yet analyzed Ripley v. United States. The absence of a flag is not a finding that it is good law.

Cited by
90 opinions

Headnotes

  1. Contracts Law — Government Contracts — Finality of Agent's Decision Where a government contract makes the decision of the agent in charge conclusive as to a matter submitted to his judgment, the contractor has no right to relief for delay or damage resulting from that decision unless the refusal was the result of fraud or of such gross mistake as would imply fraud. 223 U.S. 695
  2. Contracts Law — Government Contracts — Duty of Deciding Agent The very extent of the agent's power and the conclusive character of his decision raise a corresponding duty that his judgment be exercised not capriciously or fraudulently, but reasonably and with due regard to the rights of both contracting parties; a finding that the agent's refusal was a gross mistake and an act of bad faith therefore entitles the contractor to recover the damages caused thereby. 223 U.S. 695
  3. Contracts Law — Government Contracts — Exhaustion of Appeals Where the contract contains no provision for an appeal from the decision of the agent in charge, the contractor does not forfeit his right to recover damages for the agent's improper decision by failing to appeal to a higher officer; a clause making the decision of the Engineer in Charge conclusive as to the quality and quantity of work and material does not extend to a matter of fact expressly left to the judgment of the agent in charge. 223 U.S. 695
  4. Contracts Law — Government Contracts — Conclusiveness of Engineer's Decision Where the contract provides that the decisions of the engineer in charge are final, those decisions are conclusive in the absence of fraud or gross mistake implying fraud; the contract does not contemplate that the opinion of the court should be substituted for that of the engineer, and his decision is binding on all matters submitted to him under the contract. 223 U.S. 695
  5. Contracts Law — Government Contracts — Retroactive Effect of Supplemental Agreement A supplemental agreement permitting a different method of measurement is not retroactive so as to give the contractor a cause of action for the prior rejection of materials, even though a different method was thereafter allowed. 223 U.S. 695
  6. Contracts Law — Government Contracts — Remission of Inspection Expenses Where the contract provides that expenses of inspection may in some cases be remitted but only with the prior consent of the Chief of Engineers, the contractor cannot recover such expenses absent a finding that such consent was given. 223 U.S. 695
  7. Contracts Law — Damages For a contractor to recover damages caused by an improper decision of the government's agent in charge, the burden is on him, and where the record lacks findings sufficient to support his calculations of the delay period, the court must base its decision on the record as it stands. 223 U.S. 695