Opinion · Supreme Court of the United States

Minneapolis, St. Paul & Sault Ste. Marie Railway Co. v. Doughty

Minneapolis, St. Paul & Sault Ste. Marie Ry. Co. v. Doughty, 208 U.S. 251 (1908)

Type
Opinion
Court
Supreme Court of the United States
Jurisdiction
Federal
Date
1908-02-03
Topic
general

How later courts describe this case

  • approval of map vests title in railway company, but the right of way is determined by where the railway is actually built

Citator

UpLaw has not yet analyzed Minneapolis, St. Paul & Sault Ste. Marie Railway Co. v. Doughty. The absence of a flag is not a finding that it is good law.

Cited by
24 opinions

Headnotes

  1. Environmental Law — Railroad Right of Way — Grant Under Act of March 3, 1875 Under the Act of March 3, 1875, granting railroads a right of way through public lands, the grant takes effect only upon actual construction of the road or upon the approval by the Secretary of the Interior of a profile of the road filed in the local land office pursuant to § 4 of the Act; the grant does not attach upon mere location of the road. 208 U.S. 251 (opinion of the Court)
  2. Environmental Law — Priority Between Railroad Right of Way and Homestead Entry A valid homestead entry made after final survey, but before either the railroad's actual construction of its road or the Secretary of the Interior's approval of the filed profile, is superior to the rights of the railroad company. 208 U.S. 251 (opinion of the Court)
  3. Environmental Law — Statutory Construction — Priority of Rights Under § 4 Section 4 of the Act of March 3, 1875, fixes the priority of rights between railroads and settlers by explicit language: to secure the right of way, three things are required — location of the road, filing of a profile in the local land office, and approval thereof by the Secretary of the Interior to be noted upon the plats; only after these acts are done does the statute subject the disposition of the land under the land laws to the railroad's right. The word "thereafter" in the statute will not be construed to mean after the mere location of the road, and the doctrine of relation will not be applied to vest the railroad's title as of the date of location. 208 U.S. 251 (opinion of the Court)