Opinion · Supreme Court of the United States

United States v. Northern Pacific Railway Co.

United States v. N. Pac. Ry. Co., 256 U.S. 51 (1921)

Type
Opinion
Court
Supreme Court of the United States
Jurisdiction
Federal
Date
1921-04-11
Topic
general

How later courts describe this case

  • discussing whether the United States can cancel a patent issued by mistake to Northern Pacific for land in Montana

Citator

UpLaw has not yet analyzed United States v. Northern Pacific Railway Co.. The absence of a flag is not a finding that it is good law.

Cited by
50 opinions

Headnotes

  1. Contracts Law — Public Lands — Railroad Land Grants The Northern Pacific Railroad Act of 1864 and the Joint Resolution of 1870 embodied a proposal to the company that if it would bring about the construction and operation of the desired railroad, it should receive in return the lands comprehended by the granting provisions of the legislation. 256 U.S. at 63
  2. Contracts Law — Formation Where a railroad company accepts the terms of a land-grant proposal and performs by constructing and operating the railroad, which is then accepted by the President, the proposal is converted into a contract entitling the company to performance by the Government. 256 U.S. at 64
  3. Constitutional Law — Due Process The provision for indemnity lands is as much a part of the grant and contract as the provision for land in place, and the grantee's right to land within the indemnity limits in lieu of land lost within the place limits is a substantial right protected by the Due Process Clause of the Constitution. 256 U.S. at 64
  4. Environmental Law — Railroad Land Grants — Power of Government Over Indemnity Lands After the company has earned the right to receive what was intended by the grant, the Government may not reserve or appropriate to its own uses lands in the indemnity limits required to supply losses in the place limits; if it could take part of the lands required for that purpose it could take all and thereby wholly defeat the indemnity provision. 256 U.S. at 64-66
  5. Environmental Law — Railroad Land Grants — Selection of Indemnity Lands The general rule that no right attaches to any specific tract within the indemnity limits until the company has selected it applies as between the company and settlers under the homestead and preemption laws, and as between the company and the United States where the lands available for indemnity exceed the losses, but it has no application as between the company and the United States where the lands available for indemnity are insufficient for that purpose. 256 U.S. at 65
  6. Environmental Law — Administrative Determination — Land Department The question whether lands remaining within the indemnity limits were sufficient to satisfy losses in the place limits rests primarily with the Land Department for determination. 256 U.S. at 67
  7. Environmental Law — Judicial Review Where the Land Department, without deciding whether a deficiency existed, reserved part of the indemnity lands for forest purposes and afterwards inadvertently issued a patent therefor upon the company's selection, the question of deficiency may be determined in a later suit by the Government to set the patent aside, but only upon a clear showing of the facts, since the decision might conclude both parties as to other lands as well as those immediately involved. 256 U.S. at 67
  8. Environmental Law — Administrative Reports — Evidentiary Weight A report of the Commissioner of the General Land Office on the adjustment of a railroad land grant showing a deficiency is not sufficient to establish the existence of such a deficiency unless shown to have been approved or consented to by the Secretary of the Interior, since under the adjustment Act of March 3, 1887, supervision of the adjustment was specially devolved upon the Secretary. 256 U.S. at 67
  9. Environmental Law — Railroad Land Grants — Measure of the Grant A stipulation that all lands received by the company under its grant, and all it was possible for it to receive thereafter as place or indemnity lands, did not equal the aggregate of all odd-numbered sections within the place limits is not enough to establish a deficiency, because the measure of the grant may be less than that aggregate due to partial overlapping with another like grant or to deductions required where the route followed the general line of another railroad with a prior grant, and the presence or absence of such conditions is not a matter of which courts take judicial notice. 256 U.S. at 68
  10. Environmental Law — Evidence — Time of Deficiency The existence of a deficiency in the grant at the time the Government withdrew the lands in controversy is not established by a later finding of the Secretary of the Interior that a deficiency existed, where the finding related to the situation existing nearly six years afterward. 256 U.S. at 69